3101 N BELDEN DR 90068
Certificate Information: 3101 N BELDEN DR 90068
- Application / Permit
- 16010-10000-06191
- Plan Check / Job No.
- B16LA20514
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/19/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2017 | MANUEL MONTUFAR |
| Green Plans Picked Up | 3/7/2017 | APPLICANT |
| Corrections Issued | 3/14/2017 | EDMOND HAGOPYAN |
| Quality Review Completed | 3/22/2017 | CELESTE MORRIS |
| Building Plans Picked Up | 3/23/2017 | APPLICANT |
| Applicant returned to address corrections | 12/29/2017 | EDMOND HAGOPYAN |
| Plan Check Approved | 6/19/2019 | MANUEL MONTUFAR |
| Issued | 6/19/2019 | LADBS |
| CofO in Progress | 2/14/2024 | BRIAN SULLIVAN |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
| CofO Issued | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2017 | CARLA VALLADARES |
| BHO/Hillside ordinance | Cleared | 4/10/2017 | CARLA VALLADARES |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2017 | CARLA VALLADARES |
| Hydrant and Access approval | Cleared | 4/10/2017 | JOHN CONNEALLY |
| Permit | Cleared | 4/10/2017 | CARLA VALLADARES |
| Sewer availability | Cleared | 4/10/2017 | CARLA VALLADARES |
| Disturb/Remove Protected Trees | Cleared | 8/18/2017 | ADRIAN SANCHEZ |
| Work Adjacent to Public Way | Cleared | 11/6/2017 | HOK CHI CHIU |
| Low Impact Development | Cleared | 11/20/2017 | MITESH PATEL |
| Green Code | Cleared | 11/29/2017 | WILLIAM ROSE |
| Landscape for retaining wall | Cleared | 8/23/2018 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 8/23/2018 | SOPHIE GABEL-SCHEINBAU |
| Roof/Waste drainage to street | Cleared | 8/23/2018 | CELINA MORENO |
| Specific Plan | Cleared | 8/23/2018 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 9/7/2018 | JOHN DALLAS |
| Miscellaneous | Cleared | 9/17/2018 | WESTON PRINGLE |
| ZA Case | Cleared | 10/2/2018 | SOPHIE GABEL-SCHEINBAU |
| Excavation more than 5-ft deep | Cleared | 5/23/2019 | CALOSHA APPROVED |
| BHO/Hillside ordinance | Cleared | 5/31/2019 | NGOC KIEM |
| BHO/Hillside ordinance | Cleared | 6/14/2019 | ELAINE LEI |
| GPI Written Notices | Cleared | 6/14/2019 | MANUEL MONTUFAR |
| Grading Pre-Inspection | Cleared | 6/14/2019 | MANUEL MONTUFAR |
| Miscellaneous | Cleared | 6/17/2019 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian,, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/25/2020 | Partial Inspection | SCOTT FINNILA |
| Piling/Pier/Caisson | 2/12/2021 | No Access for Inspection | SCOTT FINNILA |
| Piling/Pier/Caisson | 2/16/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/22/2021 | Partial Approval | BRIAN SULLIVAN |
| Underground Mechanical | 4/22/2021 | Partial Approval | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 4/29/2021 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 5/12/2021 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 6/1/2021 | Partial Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 6/1/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/24/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Partial Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 2/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 4/5/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/5/2022 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 4/7/2022 | Conditional Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 4/7/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 5/10/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 5/10/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/10/2022 | Approved | BRIAN SULLIVAN |
| Shower Pan | 5/10/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 9/26/2023 | Partial Inspection | BRIAN SULLIVAN |
| Service/Power Release | 9/26/2023 | Partial Inspection | BRIAN SULLIVAN |
| Service/Power Release | 10/19/2023 | Approved | BRIAN SULLIVAN |
| Final | 12/18/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/18/2023 | Approved | BRIAN SULLIVAN |
| Green Building Final | 12/18/2023 | Approved | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 12/18/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 12/18/2023 | Approved | BRIAN SULLIVAN |
| Final | 2/14/2024 | OK to Issue CofO | BRIAN SULLIVAN |