812 N CHESTNUT AVE 90042

Certificate Information: 812 N CHESTNUT AVE 90042

Application / Permit
16010-10000-06190
Plan Check / Job No.
B16LA20512
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 4-STORY SFD WITH ATTACHED GARAGE PURSUANT TO TENTATIVE PARCEL MAP VTT 73755-SL. A CERTIFICATE OF OCCUPANCY (TEMP. OR FINAL) SHALL NOT BE ISSUDED PRIOR TO MAP RECORDATION. (PARCEL 5)
Permit Issued
Issued on 2/7/2018
Issuing Office
Metro
Current Status
CofO Issued on 7/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2016 APPLICANT
Green Plans Picked Up 2/1/2017 APPLICANT
Assigned to Plan Check Engineer 2/2/2017 LAWRENCE QUIRANTE
Corrections Issued 2/6/2017 LAWRENCE QUIRANTE
Quality Review Completed 2/8/2017 CHARMIE HUYNH
Building Plans Picked Up 2/9/2017 APPLICANT
Applicant returned to address corrections 2/23/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/1/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/7/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/13/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/26/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/13/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/16/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/10/2018 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/25/2018 LAWRENCE QUIRANTE
Plan Check Approved 1/29/2018 LAWRENCE QUIRANTE
Issued 2/7/2018 LADBS
CofO in Progress 7/14/2025 BRENDAN MORELLI
CofO Issued 7/14/2025 DEROLD HAUFF
Permit Finaled 7/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/9/2017 JOHNNY KAZARIAN
Address approval Cleared 2/23/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 4/7/2017 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 4/14/2017 JOHN CONNEALLY
Low Impact Development Cleared 5/2/2017 MICHAEL SCADUTO
Sewer availability Cleared 5/2/2017 CARLA VALLADARES
Building over 3-story or 36-ft Cleared 5/22/2017 CALOSHA APPROVED
Miscellaneous Cleared 8/25/2017 JOHN DACEY
Tract Map conditions Cleared 8/25/2017 JOHN DACEY
Roof/Waste drainage to street Cleared 9/14/2017 CRISTIAN GUERRERO
Miscellaneous Cleared 11/16/2017 ZEMAMU GEBREWOLD
Green Code Cleared 1/9/2018 DONALD CRICHLOW

Contact Information

Contractor Kor Construction Inc; Lic. No.: 965685-B 11130 DANBURY STREET      ARCADIA, CA 91006
Engineer Lee, Jack C; Lic. No.: GE2153 576 E LAMBERT RD      BREA, CA 92821
Engineer Wong, Jim Chu Man; Lic. No.: C69393 PO BOX 91522      PASADENA, CA 91109

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2018 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 5/23/2018 No Access for Inspection SCOTT FINNILA
Footing/Foundation/Slab 6/8/2018 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 6/27/2018 Conditional Approval MICHAEL FAUNCE
Footing/Foundation/Slab 7/2/2018 Conditional Approval MICHAEL FAUNCE
Footing/Foundation/Slab 9/28/2018 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/28/2018 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 9/28/2018 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/2/2018 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 10/4/2018 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/16/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/19/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/21/2018 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/24/2018 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 12/24/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
MERV13>=Rough 12/24/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/24/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/26/2018 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/10/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 1/10/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
MERV13>=Rough 1/10/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/10/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Drywall Nailing 1/11/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/11/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 1/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
MERV13>=Rough 1/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/13/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 3/13/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
MERV13>=Rough 3/13/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/13/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 3/14/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/19/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 6/3/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
MERV13>=Rough 6/3/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/3/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Gas Test 6/4/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/4/2019 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/10/2019 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/10/2019 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 8/19/2019 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/27/2019 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 8/27/2019 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/27/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/3/2019 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Rough 9/3/2019 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 9/3/2019 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/3/2019 Approved ALEJANDRO DE ARTOLA
Insulation 9/9/2019 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/13/2019 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 12/11/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/12/2019 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 4/30/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Final 5/29/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 6/9/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/10/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/2/2020 Approved ALEJANDRO DE ARTOLA
Gas Test 10/13/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/29/2021 Approved ALEJANDRO DE ARTOLA
Final 1/29/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/29/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/1/2021 Corrections Issued ALEJANDRO DE ARTOLA
Special/Order Compliance 10/12/2023 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 10/23/2023 Approved BRENDAN MORELLI
Special/Order Compliance 3/13/2024 Corrections Issued BRENDAN MORELLI
Final 6/17/2024 Corrections Issued WILLIAM KUEHN
Green Building Final 6/17/2024 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Final 6/17/2024 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved WILLIAM KUEHN
Service/Power Release 6/17/2024 Not Ready for Inspection WILLIAM KUEHN
Smoke Detectors 6/17/2024 Approved WILLIAM KUEHN
Special/Order Compliance 7/2/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 7/16/2024 Corrections Issued BRENDAN MORELLI
Final 7/16/2024 Partial Inspection BRENDAN MORELLI
Gas Test 7/16/2024 Corrections Issued BRENDAN MORELLI
Green Building Final 7/16/2024 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 7/16/2024 Corrections Issued BRENDAN MORELLI
MERV13>=Final 7/16/2024 Approved BRENDAN MORELLI
PLUMBING-Final 7/16/2024 Approved BRENDAN MORELLI
Service/Power Release 11/6/2024 Approved BRENDAN MORELLI
Special/Order Compliance 2/6/2025 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 2/25/2025 Corrections Issued BRENDAN MORELLI
Final 7/7/2025 OK to Issue CofO BRENDAN MORELLI
Green Building Final 7/7/2025 Approved BRENDAN MORELLI