20179 W RINALDI ST 91326

Certificate Information: 20179 W RINALDI ST 91326

Application / Permit
16010-10000-06136
Plan Check / Job No.
B16LA20427
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
NEW 1-STORY TYPE V-B CORE AND SHELL RETAIL/RESTAURANT BUILDING PER CPC-2016-837-SP-MCUP-DRB-SPP-SPR
Permit Issued
Issued on 2/21/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2016 APPLICANT
Assigned to Plan Check Engineer 2/16/2017 HERNAN ARREOLA
Building Plans Picked Up 3/8/2017 APPLICANT
Green Plans Picked Up 3/15/2017 APPLICANT
Disabled Access Plans Picked Up 3/17/2017 APPLICANT
Corrections Issued 3/20/2017 RICARDO SUPAN
Quality Review Completed 3/28/2017 ARMEN SARKISIAN
Applicant returned to address corrections 4/20/2017 RICARDO SUPAN
Applicant returned to address corrections 5/10/2017 RICARDO SUPAN
Applicant returned to address corrections 5/18/2017 RICARDO SUPAN
Applicant returned to address corrections 5/25/2017 RICARDO SUPAN
Applicant returned to address corrections 6/8/2017 RICARDO SUPAN
Applicant returned to address corrections 6/14/2017 RICARDO SUPAN
Applicant returned to address corrections 6/15/2017 RICARDO SUPAN
Applicant returned to address corrections 6/22/2017 RICARDO SUPAN
Applicant returned to address corrections 7/5/2017 RICARDO SUPAN
Applicant returned to address corrections 7/20/2017 RICARDO SUPAN
Plan Check Approved 2/12/2018 RICARDO SUPAN
Issued 2/21/2018 LADBS
TCO Issued (Expire Date: 07-19-2020) 1/21/2020 JAMES STEPHENS
TCO Issued (Expire Date: 01-03-2021) 7/7/2020 JEFFREY DURAN
TCO Issued (Expire Date: 07-04-2021) 1/5/2021 JEFFREY DURAN
TCO Issued (Expire Date: 03-16-2022) 9/17/2021 JEFFREY DURAN
CofO in Progress 10/6/2021 JEFFREY DURAN
Permit Finaled 11/24/2021 RICKEY JACKSON
CofO Issued 11/24/2021 RICKEY JACKSON
Permit Finaled 11/24/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 5/11/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 5/11/2017 RAVIL MANAPOV
Driveway location Cleared 6/16/2017 VICENTE CORDERO
Internal circulation Cleared 6/16/2017 VICENTE CORDERO
Specific Plan Cleared 6/16/2017 VICENTE CORDERO
Low Impact Development Cleared 8/2/2017 MITESH PATEL
Hydrant and Access approval Cleared 8/25/2017 JOHN DALLAS
Highway dedication Cleared 9/18/2017 KENNETH PHAM
Permit Cleared 9/28/2017 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/28/2017 LEE GUILBEAUX
Sewer availability Cleared 10/11/2017 MARKOS PEREZ-BRAN
"D" conditions Cleared 10/20/2017 ANNA VIDAL
"T" removal Cleared 10/20/2017 ANNA VIDAL
CPC Cleared 10/20/2017 ANNA VIDAL
CPC Cleared 10/20/2017 ANNA VIDAL
CPC Cleared 10/20/2017 ANNA VIDAL
Certificate of Compliance Cleared 10/20/2017 ANNA VIDAL
Miscellaneous Cleared 10/20/2017 ANNA VIDAL
Miscellaneous Cleared 10/20/2017 ANNA VIDAL
Miscellaneous Cleared 10/20/2017 ANNA VIDAL
Prkng lot landscape/Water mgmt Cleared 10/20/2017 ANNA VIDAL
Site Plan review Cleared 10/20/2017 ANNA VIDAL
Specific Plan Cleared 10/20/2017 ANNA VIDAL
Tract Map conditions Cleared 10/20/2017 ANNA VIDAL
Tract Map conditions Cleared 10/20/2017 ANNA VIDAL
Tract Map conditions Cleared 10/20/2017 ANNA VIDAL
Tract Map conditions Cleared 10/20/2017 ANNA VIDAL
ZA Case Cleared 10/20/2017 ANNA VIDAL
ZA Case Cleared 10/20/2017 ANNA VIDAL
ZA Case Cleared 10/20/2017 ANNA VIDAL
Green Code Cleared 10/24/2017 RUSSELL KELLY
DAS Clearance Cleared 10/26/2017 RICARDO SUPAN
Fire Marshall Fire Life Safety Cleared 11/8/2017 MENOA AGHAJANI
Building over 3-story or 36-ft Cleared 2/12/2018 CALOSHA APPROVED
GPI Written Notices Cleared 2/12/2018 RICARDO SUPAN
Grading Pre-Inspection Cleared 2/12/2018 RICARDO SUPAN

Contact Information

Architect Rose, Hugh Mason; Lic. No.: C30461 144 N ORANGE STREET      ORANGE, CA 92866
Contractor Moorefield Construction Inc; Lic. No.: 397892-B 600 N TUSTIN AVENUE SUITE #210      SANTA ANA, CA 92705
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Schroeder, Mark Ernest; Lic. No.: S4110 16969 VON KARMAN AVE 240      IRVINE, CA 92606
Geologist Putnam, Lance Richard; Lic. No.: EG2469 25134 MARKEL DR      NEWHALL, CA 91321
Landscape Architect Larkins, David Kenneth; Lic. No.: LA4226 10335 JEFFERSON BLVD      CULVER CITY, CA 90232

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/19/2018 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 7/3/2018 Not Ready for Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 7/10/2018 Partial Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 7/19/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 7/20/2018 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 7/20/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 7/20/2018 Not Ready for Inspection ROBERT COLE
Deputy Wood Construction 9/13/2018 Conditional Approval JAMES STEPHENS
Green Building Rough 10/1/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 10/1/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 10/1/2018 Partial Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/28/2018 Partial Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/10/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 12/10/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 12/10/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 12/10/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/13/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Approval ROBERT COLE
Interior/Exterior Lathing 1/4/2019 Partial Approval ROBERT COLE
Interior/Exterior Lathing 1/7/2019 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 2/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/4/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/11/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 2/11/2019 Partial Inspection ROBERT COLE
Drywall Nailing 2/20/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/20/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/26/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/26/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 3/19/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 3/19/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/19/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 3/19/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 3/28/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/28/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 3/28/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 4/8/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/8/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/8/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 4/8/2019 Partial Inspection ROBERT COLE
Insulation 4/16/2019 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 5/3/2019 Conditional Approval JAMES STEPHENS
Light Gage Steel Frame 8/16/2019 Partial Inspection ROBERT COLE
Drywall Nailing 9/17/2019 Not Ready for Inspection ROBERT COLE
Final 9/17/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 9/17/2019 Not Ready for Inspection ROBERT COLE
Green Building Final 9/17/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 9/17/2019 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 9/17/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 9/17/2019 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 9/17/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 9/17/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 9/17/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/7/2019 Not Ready for Inspection ROBERT COLE
Final 10/7/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 10/7/2019 Not Ready for Inspection ROBERT COLE
Green Building Final 10/7/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 10/7/2019 Approved ROBERT COLE
SGSOV-Seismic Gas S/O Valve 10/7/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 10/7/2019 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 10/7/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 10/7/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 10/7/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/12/2019 Not Ready for Inspection ROBERT COLE
Final 11/12/2019 Partial Inspection ROBERT COLE
Footing/Foundation/Slab 11/12/2019 Not Ready for Inspection ROBERT COLE
Green Building Final 11/12/2019 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 11/12/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 11/12/2019 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 11/12/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 11/12/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 11/12/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/18/2019 Not Ready for Inspection ROBERT COLE
Final 11/18/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 11/18/2019 Not Ready for Inspection ROBERT COLE
Green Building Final 11/18/2019 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 11/18/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 11/18/2019 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 11/18/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 11/18/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 11/18/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/16/2019 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 12/26/2019 Approved ROBERT COLE
Final 12/26/2019 Partial Inspection ROBERT COLE
Footing/Foundation/Slab 12/26/2019 Approved ROBERT COLE
Green Building Final 12/26/2019 Approved ROBERT COLE
SGSOV-Seismic Gas S/O Valve 12/26/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 12/26/2019 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 12/26/2019 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 12/26/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 12/26/2019 Partial Inspection ROBERT COLE
Special/Order Compliance 6/26/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 7/7/2020 Approved ROBERT COLE
Final 7/10/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Approved ROBERT COLE
Smoke Detectors 7/10/2020 Approved ROBERT COLE
Structural Steel Frame 7/10/2020 Approved ROBERT COLE
Verify Sprinkler Sign Off 7/10/2020 Approved ROBERT COLE
Wood Frame 7/10/2020 Approved ROBERT COLE
Special/Order Compliance 12/10/2020 Approved HAMID PISHEHVAR
Special/Order Compliance 6/9/2021 Not Ready for Inspection JEFFREY DURAN
Final 10/6/2021 OK to Issue CofO JEFFREY DURAN