505 W 31ST ST #1-73 90007

Certificate Information: 505 W 31ST ST #1-73 90007

Application / Permit
16010-10000-06041
Plan Check / Job No.
B16LA20281
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5-STORY TYPE III-A 73-UNIT AFFORDABLE HOUSING APT BLDG (6 VERY LOW INCOME & 2 MODERATE INCOME) OVER 2-STORY TYPE 1-A APT BLDG/PARKING GARAGE AND 1-LEVEL TYPE 1-A BASEMENT GARAGE (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 4/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2016 APPLICANT
Application Withdrawn 12/22/2016 APPLICANT
Re-Activate Applicaton 12/22/2016 APPLICANT
Assigned to Plan Check Engineer 1/26/2017 NILOOFAR MEHRAIN
Corrections Issued 2/1/2017 NILOOFAR MEHRAIN
Quality Review Completed 2/1/2017 GUANG MIN TUNG
Building Plans Picked Up 2/3/2017 APPLICANT
Applicant returned to address corrections 8/14/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/29/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/6/2018 NILOOFAR MEHRAIN
Plan Check Approved 11/15/2018 NILOOFAR MEHRAIN
Issued 4/25/2019 LADBS
TCO Issued (Expire Date: 02-02-2022) 8/6/2021 ERNESTO CORRAL
CofO in Progress 1/19/2022 JAMES POWERS
CofO in Progress 1/21/2022 JAMES POWERS
CofO in Progress 1/27/2022 JAMES POWERS
Permit Finaled 1/27/2022 ERNESTO CORRAL
CofO Issued 1/27/2022 ERNESTO CORRAL
Permit Finaled 1/27/2022 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/5/2018 GEORGE SUCHAND
Green Code Cleared 7/26/2018 NILOOFAR MEHRAIN
Address approval Cleared 8/1/2018 KRISTEN LY
Eng Process Fee Ord 176,300 Cleared 8/8/2018 STEVE MELGAR
Permit Cleared 8/8/2018 STEVE MELGAR
Project located in CRA area Cleared 8/8/2018 JIM URQUHART
Housing rent stabilization Cleared 8/10/2018 CHARLES GARCIA
Low Impact Development Cleared 9/7/2018 SAM NAVID
Fire Marshall Fire Life Safety Cleared 9/13/2018 DOMINIQUE MEDINA
Roof/Waste drainage to street Cleared 9/18/2018 STEVE MELGAR
Bicycle Parking Cleared 9/25/2018 STEVE MELGAR
DAS Clearance Cleared 10/26/2018 NILOOFAR MEHRAIN
DCP conditions approval Cleared 10/30/2018 JAMES MCCARTHY
Housing density bonus Cleared 10/30/2018 JAMES MCCARTHY
CPC Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
CPC Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
Encroachment in public way Cleared 11/5/2018 KARAN PATEL
Frnt yard landscape/Water mgmt Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
Opn space landscape/Water mgmt Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
Supp. Use District POD/CDO/TDO Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
ZI Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
ZI Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
ZI Cleared 11/5/2018 SOPHIE GABEL-SCHEINBAU
Building over 3-story or 36-ft Cleared 11/15/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/15/2018 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 12/11/2018 BOK GOH
Highway dedication Cleared 12/12/2018 NAZILA NOORIFAR
Sewer availability Cleared 12/12/2018 NAZILA NOORIFAR

Contact Information

Architect Blatter, Jay Irwin; Lic. No.: C22984 622 ROLLING BROOK LANE      SANTA BARBARA, CA 93110
Contractor Westside Contractors Inc; Lic. No.: 971757-B 10474 SANTA MONICA BLVD STE402      LOS ANGELES, CA 90025
Engineer Smith,, Chris W.; Lic. No.: S6106 35 CATAMARAN ST      MARINA DEL REY, CA 90292
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Engineer Young,, Don Yuk-Man; Lic. No.: C35713 149 PASADENA AVE STE B      SOUTH PASADENA, CA 91030

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 5/2/2019 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/3/2019 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/7/2019 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/8/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/8/2019 Partial Approval JAMES POWERS
METHANE-Barrier 5/8/2019 Partial Approval JAMES POWERS
METHANE-Subgrade 5/8/2019 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/9/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/15/2019 Partial Approval JAMES POWERS
METHANE-Barrier 5/15/2019 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 5/15/2019 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/21/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/23/2019 Not Ready for Inspection JAMES POWERS
Green Building Rough 5/23/2019 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/23/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/23/2019 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/23/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/28/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/28/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/29/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/30/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/31/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/31/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/31/2019 Partial Approval JAMES POWERS
Green Building Rough 6/10/2019 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/10/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/10/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/10/2019 Not Ready for Inspection JAMES POWERS
Deputy Shotcrete 6/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/18/2019 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/18/2019 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 7/18/2019 Approved RAFAEL ESPINOZA
METHANE-Subgrade 7/18/2019 Approved RAFAEL ESPINOZA
Deputy Steel/Welding 7/19/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/19/2019 Partial Approval JAMES POWERS
METHANE-Rough 7/19/2019 Approved JAMES POWERS
Deputy Reinf. Concrete 8/12/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/14/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/15/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/21/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/22/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/22/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/23/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/28/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/30/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/4/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/6/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Masonry Frame 9/7/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/10/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/11/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/12/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/16/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 9/16/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 9/17/2019 Partial Approval JAMES POWERS
Green Building Rough 9/17/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/17/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/17/2019 Not Ready for Inspection JAMES POWERS
Green Building Rough 9/23/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/23/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/23/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/26/2019 Partial Approval JAMES POWERS
Deputy Other (see comments) 10/1/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/9/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/10/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/15/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/25/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/28/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/31/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/31/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/1/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 11/4/2019 Partial Approval JAMES POWERS
Green Building Rough 11/4/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/4/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/4/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 11/5/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/8/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/8/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/13/2019 Partial Approval JAMES POWERS
Green Building Rough 11/13/2019 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/13/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/13/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 11/14/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/15/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/19/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/21/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/22/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/22/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/22/2019 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 11/25/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/25/2019 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/25/2019 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 11/26/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/26/2019 Approved JOEY BUCHANAN
Green Building Rough 11/26/2019 Not Ready for Inspection JOEY BUCHANAN
Reinforced Concrete Frame 11/26/2019 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 11/26/2019 Not Ready for Inspection JOEY BUCHANAN
Deputy Drilled-In Anchors 11/27/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/27/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 12/3/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/5/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/12/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/16/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/17/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/19/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/26/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/27/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/30/2019 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 1/2/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/2/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 1/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/6/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/6/2020 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 1/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/7/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/7/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/8/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/13/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/17/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/21/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/22/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/23/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/24/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/27/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/3/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/3/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/3/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/4/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/6/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/19/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/21/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/24/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/25/2020 Partial Approval JAMES POWERS
Green Building Rough 2/25/2020 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 2/25/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/25/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 2/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/27/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/28/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/28/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 2/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/2/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/3/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/3/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/9/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/10/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/19/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/20/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/20/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/25/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/25/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/26/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/27/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/27/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/31/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/1/2020 Partial Approval JAMES POWERS
Drywall Nailing 4/1/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/2/2020 Partial Approval JAMES POWERS
Insulation 4/7/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/8/2020 Partial Approval JAMES POWERS
Insulation 4/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/13/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/13/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/14/2020 Partial Approval JAMES POWERS
Drywall Nailing 4/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/16/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/16/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/16/2020 Partial Approval JAMES POWERS
Insulation 4/16/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/17/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/17/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/20/2020 Partial Approval JAMES POWERS
Drywall Nailing 4/20/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/21/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 4/21/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/22/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/23/2020 Conditional Approval JAMES POWERS
Deputy Drilled-In Anchors 4/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/23/2020 Conditional Approval JAMES POWERS
Deputy Steel/Welding 4/23/2020 Conditional Approval JAMES POWERS
Deputy Wood Construction 4/23/2020 Partial Approval JAMES POWERS
Insulation 4/24/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/28/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/28/2020 Partial Approval JAMES POWERS
Wood Frame 4/29/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/30/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/1/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/1/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/1/2020 Partial Approval JAMES POWERS
Insulation 5/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/4/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/4/2020 Partial Approval JAMES POWERS
Wood Frame 5/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/5/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/5/2020 Partial Approval JAMES POWERS
Wood Frame 5/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/7/2020 Partial Approval JAMES POWERS
Wood Frame 5/7/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/11/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/11/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/11/2020 Partial Approval JAMES POWERS
Insulation 5/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/12/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/12/2020 Partial Approval JAMES POWERS
Wood Frame 5/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/14/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/14/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/14/2020 Partial Approval JAMES POWERS
Insulation 5/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/15/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/15/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/19/2020 Partial Approval JAMES POWERS
Insulation 5/19/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/19/2020 Partial Approval JAMES POWERS
Drywall Nailing 5/20/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/21/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/22/2020 Partial Approval JAMES POWERS
Insulation 5/26/2020 Partial Approval JAMES POWERS
Wood Frame 5/26/2020 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 5/27/2020 Partial Approval JAMES POWERS
Drywall Nailing 5/27/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/5/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/5/2020 Partial Approval JAMES POWERS
Insulation 6/5/2020 Partial Approval JAMES POWERS
Wood Frame 6/5/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/9/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/9/2020 Partial Approval JAMES POWERS
Insulation 6/9/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/11/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/11/2020 Partial Approval JAMES POWERS
Green Building Rough 6/11/2020 Approved JAMES POWERS
Reinforced Concrete Frame 6/11/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/11/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/12/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 6/12/2020 Partial Approval JAMES POWERS
Insulation 6/15/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval JAMES POWERS
Insulation 6/16/2020 Partial Approval JAMES POWERS
Wood Frame 6/16/2020 Partial Approval JAMES POWERS
Insulation 6/18/2020 Partial Approval JAMES POWERS
Wood Frame 6/18/2020 Partial Approval JAMES POWERS
Insulation 6/22/2020 Partial Approval JAMES POWERS
Insulation 6/24/2020 Partial Approval JAMES POWERS
Drywall Nailing 6/29/2020 Partial Approval JAMES POWERS
Insulation 6/29/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/1/2020 Partial Approval JAMES POWERS
Insulation 7/1/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/6/2020 Partial Approval JAMES POWERS
Wood Frame 7/6/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/8/2020 Not Ready for Inspection JAMES POWERS
Insulation 7/8/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 7/10/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/15/2020 Partial Approval JAMES POWERS
Insulation 7/16/2020 Partial Approval JAMES POWERS
Wood Frame 7/16/2020 Partial Approval JAMES POWERS
Insulation 7/17/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 7/22/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/22/2020 Partial Approval JAMES POWERS
Insulation 7/23/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 7/23/2020 Partial Approval JAMES POWERS
Insulation 7/24/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/29/2020 Partial Approval JAMES POWERS
Wood Frame 7/29/2020 Partial Approval JAMES POWERS
Insulation 7/31/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/4/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/5/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/7/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/10/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/12/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Not Ready for Inspection JAMES POWERS
Insulation 8/14/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Not Ready for Inspection JAMES POWERS
Insulation 8/17/2020 Partial Approval JAMES POWERS
Wood Frame 8/17/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/19/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval JAMES POWERS
Wood Frame 8/19/2020 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 8/20/2020 Partial Approval JAMES POWERS
Insulation 8/20/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 8/20/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/21/2020 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/24/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/25/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/26/2020 Partial Approval JAMES POWERS
Insulation 8/28/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/2/2020 Partial Approval KATY RAMIREZ
Insulation 9/2/2020 Partial Approval KATY RAMIREZ
Deputy Wood Construction 9/3/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 9/4/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/10/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/21/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/21/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/5/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/9/2020 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/9/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/22/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/22/2020 Partial Approval JAMES POWERS
Insulation 10/26/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/4/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/19/2020 Partial Inspection NICK DANERI
Light Gage Steel Frame 1/8/2021 Not Ready for Inspection JAMES POWERS
T-Bar Ceiling 1/8/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/25/2021 Partial Approval JAMES POWERS
Insulation 1/28/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/8/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/25/2021 Partial Approval JAMES POWERS
Posting Pre-Inspection 3/11/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/27/2021 Partial Approval DANIEL COLLINS
Pre-Inspection 5/18/2021 Partial Approval JAMES POWERS
Special/Order Compliance 5/18/2021 Partial Approval JAMES POWERS
Pre-Inspection 6/1/2021 Partial Approval JAMES POWERS
Green Building Final 7/14/2021 Approved JAMES POWERS
Posting Pre-Inspection 7/14/2021 Approved JAMES POWERS
Pre-Inspection 7/14/2021 Approved JAMES POWERS
Special/Order Compliance 7/14/2021 Approved JAMES POWERS
Final 7/19/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/19/2021 Approved JAMES POWERS
Pre-Inspection 7/19/2021 Approved JAMES POWERS
Reinforced Concrete Frame 7/19/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 7/19/2021 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/19/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 7/19/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/19/2021 Not Ready for Inspection JAMES POWERS
Insulation 7/21/2021 Approved JAMES POWERS
Pre-Inspection 7/21/2021 Partial Approval JAMES POWERS
Special/Order Compliance 7/21/2021 Approved JAMES POWERS
Final 7/22/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 7/22/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/22/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/22/2021 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Approved JAMES POWERS
Verify Sprinkler Sign Off 7/22/2021 Partial Approval JAMES POWERS
Final 7/26/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/26/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/26/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/26/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 7/28/2021 Approved JAMES POWERS
Pre-Inspection 8/4/2021 Not Ready for Inspection JAMES POWERS
Final 8/6/2021 OK for TCO JAMES POWERS
Reinforced Concrete Frame 8/6/2021 Approved JAMES POWERS
Reinforced Masonry Frame 8/6/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 8/6/2021 Approved JAMES POWERS
Special/Order Compliance 1/5/2022 Approved JAMES POWERS
Final 1/18/2022 OK to Issue CofO JAMES POWERS