1707 N BURNELL DR 90065

Certificate Information: 1707 N BURNELL DR 90065

Application / Permit
16010-10000-05643
Plan Check / Job No.
B16LA19489
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 story SFD with attached carport.
Permit Issued
Issued on 5/17/2017
Issuing Office
Metro
Current Status
CofO Issued on 6/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2016 APPLICANT
Green Plans Picked Up 12/29/2016 APPLICANT
Assigned to Plan Check Engineer 1/5/2017 VLADIMIR ARUTYUNYAN
Corrections Issued 1/9/2017 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/19/2017 MINYE PAK
Building Plans Picked Up 1/20/2017 APPLICANT
Plan Check Approved 4/5/2017 VLADIMIR ARUTYUNYAN
Issued 5/17/2017 LADBS
CofO in Progress 5/20/2020 OSVALDO PARAMO
CofO in Progress 5/20/2020 OSVALDO PARAMO
CofO in Progress 5/20/2020 OSVALDO PARAMO
Permit Finaled 6/19/2020 DEROLD HAUFF
CofO Issued 6/19/2020 DEROLD HAUFF
Permit Finaled 6/19/2020 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/7/2017 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 2/17/2017 JAMES KHO
Green Code Cleared 2/17/2017 WILLIAM ROSE
Sewer availability Cleared 2/17/2017 JAMES KHO
Specific Plan Cleared 2/23/2017 DANALYNN DOMINGUEZ
Low Impact Development Cleared 2/24/2017 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 2/24/2017 CELINA MORENO
BHO/Hillside ordinance Cleared 3/3/2017 SEVAK ISAKHAYAN
BHO/Hillside ordinance Cleared 4/5/2017 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 4/5/2017 ROCHELLE DUNGCA

Contact Information

Contractor Waconah Construction; Lic. No.: 908219-B 25 EASTWIND ST #3      MARINA DEL REY, CA 90292
Engineer Le, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2017 Approved LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 7/31/2017 Partial Approval LUIS ALVAREZ
Piling/Pier/Caisson 7/31/2017 Approved LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 8/8/2017 Partial Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 9/26/2017 Corrections Issued LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 9/29/2017 Not Ready for Inspection LUIS BARRALES
Footing/Foundation/Slab 11/27/2017 Partial Approval LUIS ALVAREZ
Deputy Reinf. Concrete 11/28/2017 Conditional Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 12/15/2017 Partial Inspection OSVALDO PARAMO
Wood Frame 1/16/2018 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/13/2018 Approved LUIS ALVAREZ
PLUMBING-Rough 2/27/2018 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/13/2018 Approved LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 3/27/2018 Approved LUIS ALVAREZ
Footing/Foundation/Slab 4/19/2018 Corrections Issued LUIS ALVAREZ
Footing/Foundation/Slab 4/30/2018 Partial Approval LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 5/24/2018 Not Ready for Inspection LUIS ALVAREZ
Footing/Foundation/Slab 5/24/2018 Approved LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 5/29/2018 Approved LUIS ALVAREZ
Insulation 7/12/2018 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Rough 8/9/2018 Partial Approval FRANCISCO MORADO
Floor/Roof Diaphrgm/Shear Wall 8/15/2018 Partial Inspection OSVALDO PARAMO
Masonry Wall/Backfill 8/15/2018 Approved OSVALDO PARAMO
PLUMBING-Rough 8/20/2018 Partial Approval OSVALDO PARAMO
Drywall Nailing 8/24/2018 Partial Inspection OSVALDO PARAMO
Green Building Rough 8/24/2018 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 9/6/2018 Not Ready for Inspection FRANCISCO MORADO
PLUMBING-Rough 9/6/2018 Approved FRANCISCO MORADO
HVAC-Rough 10/22/2018 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 10/24/2018 Approved RUBEN SALAS
PLUMBING-Rough 10/24/2018 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 10/25/2018 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 10/25/2018 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/25/2018 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 10/25/2018 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/2/2018 Approved FRANCISCO MORADO
Green Building Rough 11/2/2018 Approved FRANCISCO MORADO
Verify Sprinkler Sign Off 11/2/2018 Approved FRANCISCO MORADO
Insulation 12/6/2018 Corrections Issued RUBEN SALAS
Insulation 12/12/2018 Approved CRAIG VAUGHAN
Drywall Nailing 12/28/2018 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/29/2019 Partial Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 2/28/2019 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 3/5/2019 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/15/2019 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/7/2019 Partial Approval HAMIK HARTOUNIAN
Shower Pan 5/24/2019 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 6/5/2019 Partial Approval RUBEN SALAS
Special/Order Compliance 6/14/2019 Partial Inspection RUBEN SALAS
Gas Test 7/8/2019 Approved RUBEN SALAS
Sewer 7/8/2019 Approved RUBEN SALAS
ELECTRICAL-Final 9/5/2019 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/25/2019 Partial Approval OSVALDO PARAMO
ELECTRICAL-Final 10/1/2019 Partial Approval OSVALDO PARAMO
Gas Test 10/24/2019 Approved OSVALDO PARAMO
HVAC-Final 10/24/2019 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 10/24/2019 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 11/1/2019 Approved RUBEN SALAS
Special/Order Compliance 11/1/2019 Corrections Issued RUBEN SALAS
Reinforced Concrete Frame 11/20/2019 Corrections Issued RUBEN SALAS
Excavation/Setback/Form/Re-Bar 2/13/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 2/20/2020 Approved OSVALDO PARAMO
HVAC-Final 2/20/2020 Approved OSVALDO PARAMO
MERV13>=Final 2/20/2020 Approved OSVALDO PARAMO
Final 5/11/2020 OK to Issue CofO OSVALDO PARAMO
Green Building Final 5/11/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/11/2020 SGSOV Approved OSVALDO PARAMO
Service/Power Release 5/11/2020 Approved OSVALDO PARAMO
Smoke Detectors 5/11/2020 Approved OSVALDO PARAMO