437 N FRIES AVE 90744

Certificate Information: 437 N FRIES AVE 90744

Application / Permit
16010-10000-05608
Plan Check / Job No.
B16LA19387
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 2-STORY 4-UNITS APARTMENT BUILDING WITH 9 ON-SITE UNCOVERED PARKING.
Permit Issued
Issued on 8/25/2017
Issuing Office
Metro
Current Status
CofO Issued on 7/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2016 APPLICANT
Assigned to Plan Check Engineer 1/5/2017 BIDYUT RATH
Green Plans Picked Up 1/5/2017 APPLICANT
Corrections Issued 1/9/2017 HOK CHI CHIU
Disabled Access Plans Picked Up 1/13/2017 APPLICANT
Quality Review Completed 1/25/2017 BILL STUTSMAN
Building Plans Picked Up 1/30/2017 APPLICANT
Applicant returned to address corrections 3/1/2017 HOK CHI CHIU
Applicant returned to address corrections 3/22/2017 BIDYUT RATH
Applicant returned to address corrections 4/26/2017 BIDYUT RATH
Applicant returned to address corrections 6/12/2017 BIDYUT RATH
Plan Check Approved 7/26/2017 BIDYUT RATH
Issued 8/25/2017 LADBS
TCO Issued (Expire Date: 12-04-2022) 6/7/2022 DAVID TSAU
CofO in Progress 7/12/2022 JOEY BUCHANAN
Permit Finaled 7/26/2022 DAVID TSAU
CofO Issued 7/26/2022 DAVID TSAU
Permit Finaled 7/26/2022 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 2/7/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 2/9/2017 RYMBEAU ROSELL
Highway dedication Cleared 2/9/2017 RYMBEAU ROSELL
Miscellaneous Cleared 2/9/2017 RYMBEAU ROSELL
Permit Cleared 2/9/2017 RYMBEAU ROSELL
Sewer availability Cleared 2/9/2017 RYMBEAU ROSELL
Hydrant and Access approval Cleared 2/14/2017 JOHN CONNEALLY
"Q" conditions Cleared 4/7/2017 JESSE RAMOS
Clean Up Green Up Cleared 4/7/2017 EDBER MACEDO
ZA Case Cleared 4/7/2017 EDBER MACEDO
ZI Cleared 4/7/2017 EDBER MACEDO
DAS Clearance Cleared 4/19/2017 EDDIE GARIN
Low Impact Development Cleared 4/19/2017 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/19/2017 CELINA MORENO
Green Code Cleared 4/20/2017 NEGAR NEJAD

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD   SUITE 834    LOS ANGELES, CA 90064
Contractor V C Construction & Development; Lic. No.: 959583-B 24132 MEADOW FALLS DRIVE      DIAMOND BAR, CA 91765
Engineer , ; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Benavides, Jose Alexander; Lic. No.: C72968 644 POPLAR UNIT B      ORANGE, CA 92868
Engineer Nester, Melvin Russell Jr; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Zhong, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/12/2018 Partial Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 3/14/2018 Partial Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 12/10/2018 No Access for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/7/2019 Corrections Issued NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/11/2019 Corrections Issued NICK LAROCCA
Deputy Methane Barrier 6/12/2019 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/25/2019 Partial Inspection NICK LAROCCA
Footing/Foundation/Slab 7/5/2019 Corrections Issued NICK LAROCCA
METHANE-Barrier 7/5/2019 Approved NICK LAROCCA
METHANE-Subgrade 7/5/2019 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/10/2019 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/29/2019 Partial Approval NICK LAROCCA
Deputy Wood Construction 10/25/2019 Approved RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/13/2019 Approved NICK LAROCCA
Green Building Rough 4/22/2020 Approved JOEY BUCHANAN
METHANE-Rough 4/22/2020 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 4/22/2020 Approved JOEY BUCHANAN
Wood Frame 4/22/2020 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 5/6/2020 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 5/6/2020 Not Ready for Inspection JOEY BUCHANAN
Insulation 8/19/2020 Not Ready for Inspection NICK LAROCCA
Insulation 8/25/2020 Approved JOEY BUCHANAN
Drywall Nailing 9/4/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 4/19/2022 Approved JOEY BUCHANAN
Green Building Final 4/19/2022 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 4/19/2022 Approved JOEY BUCHANAN
Wood Frame 4/19/2022 Approved JOEY BUCHANAN
Final 4/20/2022 Corrections Issued JOEY BUCHANAN
Final 7/6/2022 Corrections Issued JOEY BUCHANAN
Final 7/11/2022 Conditional Approval JOEY BUCHANAN