6446 W BRYN MAWR DR 90068

Certificate Information: 6446 W BRYN MAWR DR 90068

Application / Permit
16010-10000-05542
Plan Check / Job No.
B16LA19155
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SINGLE FAMILY DWELLING W/ATT CARPORT AND BASEMENT
Permit Issued
Issued on 6/5/2018
Issuing Office
Metro
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2016 APPLICANT
Green Plans Picked Up 1/4/2017 APPLICANT
Assigned to Plan Check Engineer 1/19/2017 LAMAR DAVIS
Corrections Issued 2/10/2017 LAMAR DAVIS
Building Plans Picked Up 3/7/2017 APPLICANT
Quality Review Completed 3/10/2017 MINYE PAK
Applicant returned to address corrections 4/28/2017 LAMAR DAVIS
Applicant returned to address corrections 5/12/2017 LAMAR DAVIS
Applicant returned to address corrections 5/30/2017 LAMAR DAVIS
Applicant returned to address corrections 11/20/2017 LAMAR DAVIS
Applicant returned to address corrections 4/25/2018 LAMAR DAVIS
Applicant returned to address corrections 5/24/2018 LAMAR DAVIS
Plan Check Approved 6/5/2018 LAMAR DAVIS
Issued 6/5/2018 LADBS
CofO in Progress 2/26/2022 BRIAN SULLIVAN
Permit Finaled 3/5/2022 DEROLD HAUFF
CofO Issued 3/5/2022 DEROLD HAUFF
Permit Finaled 3/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/21/2017 SEVAK ISAKHAYAN
Permit Cleared 3/21/2017 SEVAK ISAKHAYAN
Certificate of Compliance Cleared 4/5/2018 MARC WOERSCHING
Eng Process Fee Ord 176,300 Cleared 4/5/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 4/5/2018 GEORGE SUCHAND
Sewer availability Cleared 4/5/2018 ADRIAN SANCHEZ
Green Code Cleared 4/19/2018 SARAH ABOULHOSN
Low Impact Development Cleared 4/19/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/19/2018 MICHAEL CASTILLO
Excavation more than 5-ft deep Cleared 4/25/2018 CALOSHA APPROVED
GPI Written Notices Cleared 4/25/2018 LAMAR DAVIS
Grading Pre-Inspection Cleared 4/25/2018 LAMAR DAVIS
Encroachment in public way Cleared 5/25/2018 FATIMA GUERRA
Work Adjacent to Public Way Cleared 6/4/2018 BOK GOH

Contact Information

Architect Herrasti, Jose I; Lic. No.: C32295 108 WEST 2ND STREET # 809      LOS ANGELES, CA 90012
Contractor Owner-Builder       ,
Engineer Beck, Russell John; Lic. No.: L4857 1312 E LOMA ALTA DR      ALTADENA, CA 91001
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Koh, William Kim; Lic. No.: S3473 5695 STARWOOD CT      WESTLAKE VILLAGE, CA 91362
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2019 Approved ROBERT CORNELL
Deputy Reinf. Concrete 4/20/2020 Conditional Approval BRIAN SULLIVAN
Piling/Pier/Caisson 4/22/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/29/2020 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 4/30/2020 Conditional Approval ROBERT CORNELL
Footing/Foundation/Slab 5/5/2020 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 5/6/2020 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 5/27/2020 Partial Approval JOSEPH MCGARRY
Piling/Pier/Caisson 5/28/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 6/9/2020 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Reinf. Concrete 6/10/2020 Conditional Approval BRIAN SULLIVAN
Piling/Pier/Caisson 6/10/2020 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 6/25/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 6/25/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 7/17/2020 Partial Approval BRIAN SULLIVAN
Masonry Wall/Backfill 7/17/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 7/17/2020 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 7/21/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 7/21/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 7/21/2020 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 7/23/2020 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 8/7/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/5/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/5/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 10/5/2020 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 10/7/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 10/14/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 10/14/2020 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 10/15/2020 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 10/20/2020 No Access for Inspection ELMER BLAND
Special/Order Compliance 10/26/2020 Partial Inspection BRIAN SULLIVAN
Deputy Drilled-In Anchors 10/27/2020 No Access for Inspection ELMER BLAND
Deputy Steel/Welding 10/27/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 11/12/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 11/12/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 11/12/2020 Partial Approval BRIAN SULLIVAN
Reinforced Concrete Frame 11/12/2020 Partial Approval BRIAN SULLIVAN
Structural Steel Frame 11/12/2020 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 11/17/2020 Conditional Approval ROBERT CORNELL
BUILDING-Rough-Frame 12/4/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 12/4/2020 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/4/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/16/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 12/16/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 12/16/2020 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 12/17/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 1/6/2021 Partial Approval BRIAN SULLIVAN
Masonry Wall/Backfill 1/6/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 1/6/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/11/2021 Not Ready for Inspection BRIAN SULLIVAN
Masonry Wall/Backfill 1/11/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 1/11/2021 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 1/13/2021 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 2/3/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/3/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 2/3/2021 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 2/3/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 2/24/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 3/5/2021 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 3/23/2021 Conditional Approval BRIAN SULLIVAN
Green Building Rough 3/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Structural Steel Frame 3/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 3/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 3/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 3/30/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 5/4/2021 Approved BRIAN SULLIVAN
HVAC-Rough 5/4/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 5/4/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/5/2021 Approved BRIAN SULLIVAN
HVAC-Rough 5/5/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 5/5/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 5/5/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/13/2021 Approved BRIAN SULLIVAN
Green Building Rough 5/13/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/13/2021 Approved BRIAN SULLIVAN
Insulation 5/19/2021 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 6/2/2021 Approved BRIAN SULLIVAN
Shower Pan 6/15/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/17/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/2/2021 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 8/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Sewer 8/16/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 8/24/2021 Partial Approval RAUL BARAJAS
HVAC-Rough 8/24/2021 Partial Approval RAUL BARAJAS
Sewer 8/24/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/2/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/2/2021 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 9/3/2021 Approved BRIAN SULLIVAN
Masonry Wall/Backfill 9/13/2021 Approved BRIAN SULLIVAN
Final 2/3/2022 Corrections Issued BRIAN SULLIVAN
Green Building Final 2/3/2022 Approved BRIAN SULLIVAN
Reinforced Masonry Frame 2/3/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Not Ready BRIAN SULLIVAN
Service/Power Release 2/3/2022 Approved BRIAN SULLIVAN
Smoke Detectors 2/3/2022 Not Ready for Inspection BRIAN SULLIVAN
Structural Steel Frame 2/3/2022 Approved BRIAN SULLIVAN
Final 2/25/2022 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 2/25/2022 Approved BRIAN SULLIVAN