6446 W BRYN MAWR DR 90068
Certificate Information: 6446 W BRYN MAWR DR 90068
- Application / Permit
- 16010-10000-05542
- Plan Check / Job No.
- B16LA19155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SINGLE FAMILY DWELLING W/ATT CARPORT AND BASEMENT
- Permit Issued
- Issued on 6/5/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2016 | APPLICANT |
| Green Plans Picked Up | 1/4/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2017 | LAMAR DAVIS |
| Corrections Issued | 2/10/2017 | LAMAR DAVIS |
| Building Plans Picked Up | 3/7/2017 | APPLICANT |
| Quality Review Completed | 3/10/2017 | MINYE PAK |
| Applicant returned to address corrections | 4/28/2017 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/12/2017 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/30/2017 | LAMAR DAVIS |
| Applicant returned to address corrections | 11/20/2017 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/25/2018 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/24/2018 | LAMAR DAVIS |
| Plan Check Approved | 6/5/2018 | LAMAR DAVIS |
| Issued | 6/5/2018 | LADBS |
| CofO in Progress | 2/26/2022 | BRIAN SULLIVAN |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2017 | SEVAK ISAKHAYAN |
| Permit | Cleared | 3/21/2017 | SEVAK ISAKHAYAN |
| Certificate of Compliance | Cleared | 4/5/2018 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2018 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 4/5/2018 | GEORGE SUCHAND |
| Sewer availability | Cleared | 4/5/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 4/19/2018 | SARAH ABOULHOSN |
| Low Impact Development | Cleared | 4/19/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 4/19/2018 | MICHAEL CASTILLO |
| Excavation more than 5-ft deep | Cleared | 4/25/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/25/2018 | LAMAR DAVIS |
| Grading Pre-Inspection | Cleared | 4/25/2018 | LAMAR DAVIS |
| Encroachment in public way | Cleared | 5/25/2018 | FATIMA GUERRA |
| Work Adjacent to Public Way | Cleared | 6/4/2018 | BOK GOH |
Contact Information
| Architect | Herrasti, Jose I; Lic. No.: C32295 | 108 WEST 2ND STREET # 809 LOS ANGELES, CA 90012 |
| Contractor | Owner-Builder | , |
| Engineer | Beck, Russell John; Lic. No.: L4857 | 1312 E LOMA ALTA DR ALTADENA, CA 91001 |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Engineer | Koh, William Kim; Lic. No.: S3473 | 5695 STARWOOD CT WESTLAKE VILLAGE, CA 91362 |
| Geologist | Irvine, Jon A; Lic. No.: EG1691 | 1150 ENCANTO DR ARCADIA, CA 91007 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2019 | Approved | ROBERT CORNELL |
| Deputy Reinf. Concrete | 4/20/2020 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 4/22/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/29/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 5/5/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 5/6/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 5/27/2020 | Partial Approval | JOSEPH MCGARRY |
| Piling/Pier/Caisson | 5/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/9/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Reinf. Concrete | 6/10/2020 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 6/10/2020 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/25/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/25/2020 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/17/2020 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 7/17/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/17/2020 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/23/2020 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/7/2020 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/5/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/5/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/5/2020 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/14/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/14/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 10/15/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 10/20/2020 | No Access for Inspection | ELMER BLAND |
| Special/Order Compliance | 10/26/2020 | Partial Inspection | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 10/27/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 10/27/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 11/12/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Structural Steel Frame | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 11/12/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 11/17/2020 | Conditional Approval | ROBERT CORNELL |
| BUILDING-Rough-Frame | 12/4/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/4/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 12/16/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/16/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/16/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 12/17/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 1/6/2021 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 1/6/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/6/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/11/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 1/11/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/11/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 1/13/2021 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/3/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/3/2021 | Partial Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 2/3/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 2/24/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/5/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 3/23/2021 | Conditional Approval | BRIAN SULLIVAN |
| Green Building Rough | 3/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Structural Steel Frame | 3/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 3/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 3/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/30/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/4/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 5/4/2021 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/4/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/5/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 5/5/2021 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/5/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/5/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/13/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 5/13/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 5/13/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 5/19/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 6/2/2021 | Approved | BRIAN SULLIVAN |
| Shower Pan | 6/15/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/17/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/2/2021 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/16/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 8/16/2021 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/24/2021 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 8/24/2021 | Partial Approval | RAUL BARAJAS |
| Sewer | 8/24/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/2/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/2/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 9/3/2021 | Approved | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 9/13/2021 | Approved | BRIAN SULLIVAN |
| Final | 2/3/2022 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 2/3/2022 | Approved | BRIAN SULLIVAN |
| Reinforced Masonry Frame | 2/3/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 2/3/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 2/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Structural Steel Frame | 2/3/2022 | Approved | BRIAN SULLIVAN |
| Final | 2/25/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 2/25/2022 | Approved | BRIAN SULLIVAN |