NEW 32-UNITS AFFORDABLE HOUSING APARTMENT BUILDING PER DIR-2017-181-DB FOUR STORY WITH MEZZ III-A OVER 1 LEVEL OF PARKING AND BASEMENT LEVEL I-A. (4 VERY LOW INCOME UNTIS)
Permit Issued
Issued on 5/25/2018
Issuing Office
Metro
Current Status
Issued on 5/25/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/8/2016 APPLICANT
Disabled Access Plans Picked Up 12/27/2016 APPLICANT
Green Plans Picked Up 12/28/2016 APPLICANT
Assigned to Plan Check Engineer 12/29/2016 ARMEN JIVALAGIAN
Corrections Issued 1/4/2017 ARMEN JIVALAGIAN
Quality Review Completed 1/13/2017 BILL STUTSMAN
Building Plans Picked Up 3/6/2017 APPLICANT
Applicant returned to address corrections 8/28/2017 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/18/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/19/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/18/2018 ARMEN JIVALAGIAN
Plan Check Approved 4/26/2018 ARMEN JIVALAGIAN
Issued 5/25/2018 LADBS

Permit Application Clearance Information

Address approval Cleared 6/22/2017 RAVIL MANAPOV
Bicycle Parking Cleared 6/22/2017 JACOB BIGLER
Eng Process Fee Ord 176,300 Cleared 6/22/2017 RAVIL MANAPOV
Hydrant and Access approval Cleared 6/27/2017 JOHN CONNEALLY
Internal circulation Cleared 7/13/2017 COLLINS ALLAN
Sewer availability Cleared 7/13/2017 CELINA MORENO
Construction near power lines Cleared 7/17/2017 WALTER RAMIREZ
ZA Case Cleared 8/21/2017 JOHN DACEY
DAS Clearance Cleared 9/21/2017 WAI LAU
Fire Marshall Fire Life Safety Cleared 11/17/2017 MENOA AGHAJANI
DCP conditions approval Cleared 12/12/2017 KENNETH LE
Housing density bonus Cleared 12/12/2017 KENNETH LE
Project located in CRA area Cleared 12/13/2017 JIM URQUHART
Miscellaneous Cleared 12/15/2017 BRIDGETTE WOOTEN
Miscellaneous Cleared 12/15/2017 BRIDGETTE WOOTEN
Frnt yard landscape/Water mgmt Cleared 12/19/2017 BRIDGETTE WOOTEN
Miscellaneous Cleared 12/19/2017 BRIDGETTE WOOTEN
Opn space landscape/Water mgmt Cleared 12/19/2017 BRIDGETTE WOOTEN
Building over 3-story or 36-ft Cleared 12/21/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/21/2017 CALOSHA APPROVED
Encroachment in public way Cleared 12/28/2017 FATIMA GUERRA
Highway dedication Cleared 12/28/2017 STEVE MELGAR
Permit Cleared 12/28/2017 STEVE MELGAR
Work Adjacent to Public Way Cleared 12/28/2017 BOK GOH
Low Impact Development Cleared 4/13/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/13/2018 CARLA VALLADARES
Green Code Cleared 5/18/2018 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Babayan, Raffi Samuel; Lic. No.: C72168 1140 N COLUMBUS AVE 112      GLENDALE, CA 91202
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277
Engineer Tosounian, Oshin Bedros; Lic. No.: C43739 7136 HASKELL AVE STE 301      VAN NUYS, CA 91406

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 8/8/2018 Partial Inspection LARRY ARNICK
Footing/Foundation/Slab 8/10/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 8/13/2018 Conditional Approval LARRY ARNICK
Piling/Pier/Caisson 8/13/2018 Approved LARRY ARNICK
Deputy Reinf. Concrete 8/14/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 8/14/2018 Partial Inspection LARRY ARNICK
Deputy Reinf. Concrete 8/15/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/16/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/17/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 8/20/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/21/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/22/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/23/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/24/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/27/2018 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 8/27/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/28/2018 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 8/28/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/29/2018 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 8/29/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/30/2018 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 8/30/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 8/31/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/31/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/24/2018 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 10/12/2018 No Access for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/8/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/10/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/11/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/11/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/11/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 1/11/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/23/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/23/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/25/2019 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/25/2019 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/25/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/30/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/30/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/30/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 1/30/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/30/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/30/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 1/31/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/31/2019 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 2/1/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/8/2019 Partial Approval GREGORY POMISH
Green Building Rough 2/8/2019 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 2/8/2019 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 2/8/2019 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 2/9/2019 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/9/2019 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 2/15/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/15/2019 Partial Approval LARRY ARNICK
Green Building Rough 2/15/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 2/15/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/15/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/21/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 2/21/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/22/2019 Partial Approval LARRY ARNICK
Green Building Rough 2/22/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 2/22/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/22/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 2/25/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/25/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 2/26/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 2/26/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 2/27/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 2/28/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/1/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/5/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/6/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/7/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/8/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/12/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 3/12/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/14/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 3/14/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 3/14/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 3/14/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/19/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 3/19/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 3/20/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/20/2019 Not Ready for Inspection LARRY ARNICK
Piling/Pier/Caisson 3/20/2019 Approved LARRY ARNICK
Deputy Reinf. Concrete 3/21/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/21/2019 Approved LARRY ARNICK
Footing/Foundation/Slab 3/21/2019 Approved LARRY ARNICK
Deputy Reinf. Concrete 3/22/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/2/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/3/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/4/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/4/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 4/5/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/5/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 4/5/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/5/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/5/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/8/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/11/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 4/11/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/11/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/11/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/12/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/15/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 4/16/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/16/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/16/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/19/2019 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/22/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/23/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 4/23/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 4/23/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/23/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/25/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/30/2019 Partial Approval TED RIES
Green Building Rough 4/30/2019 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 4/30/2019 Partial Approval TED RIES
Verify Sprinkler Sign Off 4/30/2019 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 5/1/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/23/2019 Partial Approval LARRY ARNICK
Green Building Rough 5/24/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/24/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/24/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 5/28/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/30/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 5/30/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/30/2019 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/30/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 5/31/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/4/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/5/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/5/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 6/5/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/5/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/6/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/7/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 6/27/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/27/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 6/27/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/27/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/1/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/1/2019 Approved LARRY ARNICK
Special/Order Compliance 7/1/2019 Partial Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/2/2019 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 7/12/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/12/2019 Partial Approval LARRY ARNICK
Drywall Nailing 7/19/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 7/22/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/23/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 7/25/2019 Conditional Approval LARRY ARNICK
Drywall Nailing 7/29/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/29/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/30/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/1/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/2/2019 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 8/2/2019 Not Ready for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 8/6/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/6/2019 Not Ready for Inspection LARRY ARNICK
Piling/Pier/Caisson 8/8/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/9/2019 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 8/9/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/14/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/16/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/16/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/20/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/21/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/22/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/3/2019 Partial Approval LARRY ARNICK
Green Building Rough 9/5/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/5/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/5/2019 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 9/6/2019 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/6/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 9/9/2019 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Partial Approval LARRY ARNICK
Green Building Rough 9/10/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/10/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/10/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/16/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/19/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/20/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/27/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 10/2/2019 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/3/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/7/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/9/2019 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/10/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 10/16/2019 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 10/16/2019 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 10/22/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 11/8/2019 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 11/15/2019 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/18/2019 Conditional Approval LARRY ARNICK
Wood Frame 12/6/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 12/11/2019 Conditional Approval LARRY ARNICK
Drywall Nailing 12/13/2019 Partial Approval LARRY ARNICK
Wood Frame 12/16/2019 Partial Approval LARRY ARNICK
Insulation 12/17/2019 Partial Approval LARRY ARNICK
Drywall Nailing 12/18/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/19/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/2/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/7/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 1/10/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 1/13/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/14/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 1/17/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Not Ready for Inspection LARRY ARNICK
Insulation 1/31/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 2/10/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 2/11/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval LARRY ARNICK
Insulation 2/14/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval LARRY ARNICK
Drywall Nailing 2/26/2020 Not Ready for Inspection JONATHAN QUACH
Insulation 2/26/2020 Partial Approval JONATHAN QUACH
Deputy Wood Construction 2/27/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval LARRY ARNICK
Drywall Nailing 3/2/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval LARRY ARNICK
Deputy Wood Construction 3/10/2020 Conditional Approval LARRY ARNICK
Deputy Wood Construction 3/11/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 3/12/2020 Partial Approval LARRY ARNICK
Drywall Nailing 3/13/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 3/16/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 3/17/2020 Partial Approval LARRY ARNICK
Drywall Nailing 3/18/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 3/19/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 No Access for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 4/23/2020 Approved LARRY ARNICK
Insulation 4/29/2020 Not Ready for Inspection LARRY ARNICK
Insulation 4/30/2020 Not Ready for Inspection LARRY ARNICK
Insulation 5/6/2020 Partial Approval LARRY ARNICK
Insulation 5/20/2020 Not Ready for Inspection LARRY ARNICK
Insulation 5/21/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 5/26/2020 Conditional Approval LARRY ARNICK
Insulation 5/28/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Not Ready for Inspection LARRY ARNICK
Insulation 5/29/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 6/2/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Not Ready for Inspection NICK DANERI
Deputy Wood Construction 6/8/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 6/10/2020 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Not Ready for Inspection RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Not Ready for Inspection LARRY ARNICK
Insulation 6/26/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval JONATHAN QUACH
Insulation 7/2/2020 Partial Approval JONATHAN QUACH
Insulation 7/7/2020 Partial Approval LARRY ARNICK
Insulation 7/10/2020 Not Ready for Inspection LARRY ARNICK
Insulation 7/13/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Not Ready for Inspection LARRY ARNICK
Insulation 7/28/2020 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 7/29/2020 Conditional Approval LARRY ARNICK
Insulation 7/29/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 8/3/2020 Partial Approval LARRY ARNICK
Drywall Nailing 8/13/2020 Partial Inspection JONATHAN QUACH
Deputy Wood Construction 8/14/2020 Conditional Approval JONATHAN QUACH
Light Gage Steel Frame 8/18/2020 Partial Approval JONATHAN QUACH
Deputy Wood Construction 8/19/2020 Conditional Approval JONATHAN QUACH
Drywall Nailing 8/26/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 8/31/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/1/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/2/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/3/2020 Partial Approval LARRY ARNICK
Drywall Nailing 9/10/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/11/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/14/2020 Partial Approval LARRY ARNICK
Insulation 9/21/2020 Partial Approval LARRY ARNICK
Drywall Nailing 9/25/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 10/26/2020 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 10/27/2020 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 10/30/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 11/5/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 11/9/2020 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 11/9/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 11/10/2020 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 11/10/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 11/13/2020 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 11/13/2020 Approved DAVID BURKHEAD
Deputy Wood Construction 11/16/2020 Conditional Approval KATY RAMIREZ
Drywall Nailing 11/25/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/25/2020 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/19/2021 Partial Approval LARRY ARNICK
Drywall Nailing 1/22/2021 Partial Approval LARRY ARNICK
Drywall Nailing 1/27/2021 Partial Approval LARRY ARNICK
Pre-Inspection 2/11/2021 Approved EDWIN GREGORYONA
Drywall Nailing 2/19/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Inspection EDWIN GREGORYONA
Wood Frame 3/24/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 3/26/2021 Corrections Issued EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 3/30/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/30/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/24/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/3/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 12/17/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 2/15/2022 Not Ready for Inspection EDWIN GREGORYONA
Final 3/2/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 3/2/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 3/2/2022 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 3/2/2022 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 3/2/2022 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 3/2/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/2/2022 Approved EDWIN GREGORYONA
Drywall Nailing 3/10/2022 Approved EDWIN GREGORYONA
Light Gage Steel Frame 3/10/2022 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/25/2022 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 4/27/2023 Partial Approval LARRY ARNICK
Final 9/17/2024 No Access for Inspection DAVID BURKHEAD
Green Building Final 9/17/2024 No Access for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 9/17/2024 No Access for Inspection DAVID BURKHEAD
Pre-Inspection 3/28/2025 Approved EDWIN GREGORYONA