20000 W RINALDI ST 91326

Certificate Information: 20000 W RINALDI ST 91326

Application / Permit
16010-10000-05339
Plan Check / Job No.
B16LA18454
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
CONSTRUCTION OF NEW 3 STORY MEDICAL OFFICE BUILDING.
Permit Issued
Issued on 7/10/2017
Issuing Office
Metro
Current Status
Issued on 7/10/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/23/2016 APPLICANT
Disabled Access Plans Picked Up 12/7/2016 APPLICANT
Assigned to Plan Check Engineer 12/23/2016 TSE MING HUANG
Green Plans Picked Up 12/28/2016 APPLICANT
Corrections Issued 1/3/2017 TSE MING HUANG
Quality Review Completed 1/6/2017 LARRY LEE
Building Plans Picked Up 1/9/2017 APPLICANT
Applicant returned to address corrections 3/16/2017 TSE MING HUANG
Applicant returned to address corrections 4/28/2017 TSE MING HUANG
Applicant returned to address corrections 5/31/2017 TSE MING HUANG
Applicant returned to address corrections 6/9/2017 TSE MING HUANG
Plan Check Approved 7/6/2017 TSE MING HUANG
Issued 7/10/2017 LADBS
TCO Issued (Expire Date: 12-14-2019) 6/17/2019 RICKEY JACKSON
TCO Issued (Expire Date: 02-24-2026) 8/28/2025 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 1/11/2017 JOHN DACEY
ZA Case Cleared 1/11/2017 JOHN DACEY
ZA Case Cleared 1/11/2017 JOHN DACEY
Address approval Cleared 1/20/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 1/20/2017 ROCHELLE DUNGCA
Hydrant and Access approval Cleared 3/3/2017 JOHN DALLAS
Encroachment in public way Cleared 3/17/2017 LEE GUILBEAUX
Internal circulation Cleared 4/5/2017 DURRE SHAMSI
Specific Plan Cleared 4/5/2017 DURRE SHAMSI
Sewer availability Cleared 4/13/2017 CARLA VALLADARES
Miscellaneous Cleared 4/17/2017 MARC WOERSCHING
Highway dedication Cleared 4/19/2017 CARLA VALLADARES
DAS Clearance Cleared 4/24/2017 SHINE LIN
Low Impact Development Cleared 4/27/2017 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 5/3/2017 CELINA MORENO
Stormwater Pollution Mitigatn Cleared 5/3/2017 AMMAR ELTAWIL
Green Code Cleared 6/20/2017 TSE MING HUANG
"D" conditions Cleared 6/22/2017 ANNA VIDAL
"T" removal Cleared 6/22/2017 ANNA VIDAL
Building over 3-story or 36-ft Cleared 6/22/2017 CALOSHA APPROVED
CPC Cleared 6/22/2017 ANNA VIDAL
CPC Cleared 6/22/2017 ANNA VIDAL
CPC Cleared 6/22/2017 ANNA VIDAL
Grading Pre-Inspection Cleared 6/22/2017 TSE MING HUANG
Prkng lot landscape/Water mgmt Cleared 6/22/2017 ANNA VIDAL
Site Plan review Cleared 6/22/2017 ANNA VIDAL
Specific Plan Cleared 6/22/2017 ANNA VIDAL
Permit Cleared 6/23/2017 LINDA MARGARET

Contact Information

Architect Poliquin, Brian Richard; Lic. No.: C21165 5126 CLARETON DRIVE # 110      AGOURA HILLS, CA 91301
Contractor R C I Builders Inc; Lic. No.: 835114-B 2985 E HILLCREST DR #107      THOUSAND OAKS, CA 91362
Engineer Broad, Michael Charles; Lic. No.: C37457 2417 SHADY FOREST LANE      ORANGE, CA 92667
Geologist Putnam, Lance Richard; Lic. No.: EG2469 25134 MARKEL DR      NEWHALL, CA 91321
Landscape Architect Eichelberger, Derrik Tate; Lic. No.: LA3513 202 E COTA      SANTA BARBARA, CA 93101

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/28/2017 Partial Inspection ROBERT COLE
Deputy Reinf. Concrete 8/1/2017 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/2/2017 Partial Approval DANNY RODRIGUEZ
Piling/Pier/Caisson 8/2/2017 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/4/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 8/10/2017 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 9/5/2017 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 9/6/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 9/6/2017 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 9/7/2017 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 9/18/2017 Conditional Approval JAMES STEPHENS
Excavation/Setback/Form/Re-Bar 9/18/2017 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 9/18/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/20/2017 Conditional Approval TROY CHRISTIAN
Deputy Reinf. Concrete 10/18/2017 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 10/24/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 10/24/2017 Partial Inspection ROBERT COLE
Green Building Rough 10/24/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 10/24/2017 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 10/24/2017 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 10/25/2017 Partial Inspection JEFFREY DURAN
Wall Anchors 10/25/2017 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 10/30/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/6/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/13/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/14/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/15/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/16/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/20/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/21/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/27/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/28/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 11/29/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/13/2017 Conditional Approval ROBERT COLE
Structural Steel Frame 12/14/2017 Partial Inspection ROBERT COLE
Deputy Steel/Welding 12/15/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/18/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/19/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/20/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/21/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/26/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/27/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/28/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 12/29/2017 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/2/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/3/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 1/3/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 1/4/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/5/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/8/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/9/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/10/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/11/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/12/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 1/17/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/17/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/18/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/19/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/22/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/23/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/24/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 1/24/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 1/25/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 1/26/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 1/30/2018 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 2/1/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/2/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/2/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/2/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/5/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/5/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/5/2018 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 2/6/2018 Partial Approval ROBERT COLE
Light Gage Steel Frame 2/8/2018 Partial Inspection JAMES STEPHENS
Light Gage Steel Frame 2/8/2018 Partial Inspection ROBERT COLE
Footing/Foundation/Slab 2/15/2018 Partial Approval ROBERT COLE
Footing/Foundation/Slab 2/16/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 2/21/2018 Conditional Approval ROBERT COLE
Wall Anchors 2/21/2018 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 2/22/2018 Conditional Approval ROBERT COLE
Green Building Rough 2/22/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/22/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/22/2018 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 2/23/2018 Conditional Approval JAMES STEPHENS
SUSMP-Std. Urban Storm Water 2/27/2018 Not Ready for Inspection ROBERT COLE
Wall Anchors 2/27/2018 Conditional Approval ROBERT COLE
Light Gage Steel Frame 3/7/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 3/29/2018 Conditional Approval ROBERT COLE
Drywall Nailing 3/29/2018 Partial Approval ROBERT COLE
Green Building Rough 3/29/2018 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/3/2018 Partial Approval ROBERT COLE
Green Building Rough 4/3/2018 Not Ready for Inspection ROBERT COLE
Insulation 4/3/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 4/5/2018 Conditional Approval ROBERT COLE
Drywall Nailing 4/10/2018 Partial Approval ROBERT COLE
Green Building Rough 4/10/2018 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 4/12/2018 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 4/13/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 4/16/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/17/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/18/2018 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 4/18/2018 Partial Approval ROBERT COLE
Footing/Foundation/Slab 4/24/2018 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 5/9/2018 Conditional Approval ROBERT COLE
Light Gage Steel Frame 5/9/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 5/10/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 5/11/2018 Conditional Approval ROBERT COLE
Light Gage Steel Frame 5/16/2018 Partial Approval ROBERT COLE
Insulation 5/17/2018 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 5/17/2018 Conditional Approval ROBERT COLE
Light Gage Steel Frame 5/21/2018 Partial Approval ROBERT COLE
Drywall Nailing 5/24/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 5/24/2018 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 5/24/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 5/25/2018 Conditional Approval ROBERT COLE
Insulation 5/29/2018 Partial Approval ROBERT COLE
Masonry Wall/Backfill 5/29/2018 Partial Approval ROBERT COLE
Drywall Nailing 5/30/2018 Partial Approval ROBERT COLE
Green Building Rough 5/30/2018 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 5/30/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/31/2018 Conditional Approval ROBERT COLE
Drywall Nailing 6/4/2018 Partial Approval ROBERT COLE
Green Building Rough 6/4/2018 Not Ready for Inspection ROBERT COLE
Insulation 6/4/2018 Partial Approval ROBERT COLE
Drywall Nailing 6/6/2018 Partial Approval ROBERT COLE
Green Building Rough 6/6/2018 Not Ready for Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 6/7/2018 Partial Approval ROBERT COLE
Deputy Steel/Welding 6/25/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 7/2/2018 Corrections Issued ROBERT COLE
Drywall Nailing 7/9/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 7/9/2018 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 7/9/2018 Conditional Approval ROBERT COLE
Smoke Detectors 7/9/2018 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 7/13/2018 Partial Approval JEFFREY DURAN
T-Bar Ceiling 7/13/2018 Partial Approval JEFFREY DURAN
Insulation 7/18/2018 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 7/18/2018 Not Ready for Inspection ROBERT COLE
Drywall Nailing 7/20/2018 Partial Approval ROBERT COLE
Green Building Rough 7/20/2018 Not Ready for Inspection ROBERT COLE
Drywall Nailing 7/24/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 7/24/2018 Not Ready for Inspection ROBERT COLE
Insulation 7/24/2018 Partial Approval ROBERT COLE
Interior/Exterior Lathing 7/24/2018 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 7/24/2018 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 7/31/2018 Partial Inspection ROBERT COLE
Wall Anchors 7/31/2018 Conditional Approval ROBERT COLE
Insulation 8/6/2018 Not Ready for Inspection ROBERT COLE
Wall Anchors 8/6/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 8/7/2018 Conditional Approval ROBERT COLE
Wall Anchors 8/8/2018 Partial Inspection ROBERT COLE
Wall Anchors 8/22/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 10/10/2018 Partial Inspection ROBERT COLE
Light Gage Steel Frame 5/7/2019 Approved ROBERT COLE
Structural Steel Frame 5/7/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 5/10/2019 Partial Inspection ROBERT COLE
Special/Order Compliance 5/24/2019 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 5/28/2019 Partial Inspection ROBERT COLE
Drywall Nailing 6/7/2019 Approved ROBERT COLE
Final 6/7/2019 Corrections Issued ROBERT COLE
Footing/Foundation/Slab 6/7/2019 Approved ROBERT COLE
Green Building Final 6/7/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 6/7/2019 Approved ROBERT COLE
Reinforced Concrete Frame 6/7/2019 Partial Approval ROBERT COLE
Reinforced Masonry Frame 6/7/2019 Partial Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 6/7/2019 SGSOV Approved ROBERT COLE
SUSMP-Std. Urban Storm Water 6/7/2019 Approved ROBERT COLE
Smoke Detectors 6/7/2019 Approved ROBERT COLE
Verify Sprinkler Sign Off 6/7/2019 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 11/26/2019 Partial Approval ROBERT COLE
Final 6/29/2020 Not Ready for Inspection ROBERT COLE
Green Building Final 6/29/2020 Approved ROBERT COLE
Reinforced Concrete Frame 6/29/2020 Approved ROBERT COLE
Reinforced Masonry Frame 6/29/2020 Approved ROBERT COLE
Verify Sprinkler Sign Off 6/29/2020 Approved ROBERT COLE
Final 8/26/2025 Partial Inspection GREGORY POMISH
Special/Order Compliance 1/27/2026 Partial Inspection GREGORY POMISH