931 N KENFIELD AVE 90049

Certificate Information: 931 N KENFIELD AVE 90049

Application / Permit
16010-10000-05232
Plan Check / Job No.
B16LA17911
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD W/ATTACHED 3 CAR GARAGE.
Permit Issued
Issued on 5/14/2018
Issuing Office
Valley
Current Status
CofO Issued on 9/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2016 APPLICANT
Assigned to Plan Check Engineer 12/8/2016 VLADIMIR ARUTYUNYAN
Corrections Issued 12/12/2016 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/29/2016 MINYE PAK
Building Plans Picked Up 1/6/2017 APPLICANT
Green Plans Picked Up 1/6/2017 APPLICANT
Plan Check Approved 7/27/2017 VLADIMIR ARUTYUNYAN
Issued 5/14/2018 LADBS
CofO in Progress 9/1/2020 TIM CHRISTENSEN
Permit Finaled 9/2/2020 VINCENT COTTON
CofO Issued 9/2/2020 VINCENT COTTON
Permit Finaled 9/2/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/28/2017 ROCHELLE DUNGCA
Permit Cleared 4/28/2017 ROCHELLE DUNGCA
ZA Case Cleared 4/28/2017 EDBER MACEDO
ZA Case Cleared 4/28/2017 EDBER MACEDO
Hydrant and Access approval Cleared 5/15/2017 ROBERT DUFF
Green Code Cleared 5/19/2017 NEGAR NEJAD
Low Impact Development Cleared 6/2/2017 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 6/2/2017 RAVIL MANAPOV
Sewer availability Cleared 6/2/2017 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 6/16/2017 LUZ RABELO
BHO/Hillside ordinance Cleared 6/16/2017 LUZ RABELO
BHO/Hillside ordinance Cleared 6/16/2017 LUZ RABELO
Excavation more than 5-ft deep Cleared 6/19/2017 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/28/2018 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 1/22/2019 Corrections Issued KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 1/23/2019 Corrections Issued KENNETH NAGLE
Reinforced Masonry Frame 1/23/2019 Not Ready for Inspection KENNETH NAGLE
Footing/Foundation/Slab 1/28/2019 Partial Approval KENNETH NAGLE
Light Gage Steel Frame 2/11/2019 Partial Approval KENNETH NAGLE
Reinforced Masonry Frame 2/11/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 2/20/2019 Partial Approval KENNETH NAGLE
PLUMBING-Rough 3/18/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/9/2019 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 4/10/2019 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 5/13/2019 Partial Approval MICHAEL TEMPLE
Piling/Pier/Caisson 5/13/2019 Partial Approval MICHAEL TEMPLE
Pre-Gunite 5/13/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/23/2019 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 5/23/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/28/2019 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 7/9/2019 Not Ready for Inspection TIM CHRISTENSEN
Deputy Wood Construction 7/17/2019 Conditional Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/18/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/7/2019 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 11/7/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Corrections Issued TIM CHRISTENSEN
HVAC-Rough 11/15/2019 Corrections Issued TIM CHRISTENSEN
PLUMBING-Rough 11/27/2019 Corrections Issued TIM CHRISTENSEN
Interior/Exterior Lathing 12/12/2019 Not Ready for Inspection TIM CHRISTENSEN
Rough-Elec/Plmb/HVAC 12/12/2019 Corrections Issued TIM CHRISTENSEN
BUILDING-Rough-Frame 1/27/2020 Partial Approval TIM CHRISTENSEN
ELECTRICAL-Rough 1/27/2020 Approved TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Approved TIM CHRISTENSEN
Green Building Rough 1/27/2020 Approved TIM CHRISTENSEN
HVAC-Rough 1/27/2020 Approved TIM CHRISTENSEN
Shower Pan 1/27/2020 Approved TIM CHRISTENSEN
Verify Sprinkler Sign Off 1/27/2020 Approved TIM CHRISTENSEN
Insulation 1/31/2020 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 1/31/2020 Partial Approval TIM CHRISTENSEN
Shower Pan 1/31/2020 Corrections Issued TIM CHRISTENSEN
Special/Order Compliance 2/3/2020 Corrections Issued MICHAEL TEMPLE
Deputy Steel/Welding 2/5/2020 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 2/5/2020 Partial Approval MICHAEL TEMPLE
Pre-Inspection 2/5/2020 Corrections Issued MICHAEL TEMPLE
Drywall Nailing 2/12/2020 Approved TIM CHRISTENSEN
Shower Pan 2/12/2020 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 2/20/2020 Approved TIM CHRISTENSEN
Service/Power Release 5/21/2020 Conditional Approval TIM CHRISTENSEN
HVAC-Final 6/12/2020 Corrections Issued TIM CHRISTENSEN
PLUMBING-Final 6/12/2020 Corrections Issued TIM CHRISTENSEN
Service/Power Release 6/17/2020 Approved TIM CHRISTENSEN
HVAC-Final 6/18/2020 Approved TIM CHRISTENSEN
PLUMBING-Final 6/18/2020 Partial Approval TIM CHRISTENSEN
ELECTRICAL-Final 6/24/2020 Approved TIM CHRISTENSEN
HVAC-Final 6/24/2020 Approved TIM CHRISTENSEN
PLUMBING-Final 6/24/2020 Partial Approval TIM CHRISTENSEN
PLUMBING-Final 7/1/2020 Conditional Approval TIM CHRISTENSEN
BUILDING-Rough-Frame 8/12/2020 Approved TIM CHRISTENSEN
Final 8/12/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 8/12/2020 Approved TIM CHRISTENSEN
Green Building Final 8/12/2020 Approved TIM CHRISTENSEN
PLUMBING-Rough 8/12/2020 Approved TIM CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Approved TIM CHRISTENSEN
Smoke Detectors 8/12/2020 Approved TIM CHRISTENSEN
Structural Steel Frame 8/12/2020 Approved TIM CHRISTENSEN
Final 8/18/2020 Conditional Approval TIM CHRISTENSEN
Final 9/1/2020 Conditional Approval TIM CHRISTENSEN