10830 W CHALON ROAD 90077

Certificate Information: 10830 W CHALON ROAD 90077

Application / Permit
16010-10000-05072
Plan Check / Job No.
B16LA17139
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCTION OF A NEW 3-STORY SINGLE FAMILY DWELLING OVER BASEMENT WITH ATTACHED REAR DECK.
Permit Issued
Issued on 8/11/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2016 APPLICANT
Assigned to Plan Check Engineer 12/15/2016 CAROLYNN NEPOMUCENO
Corrections Issued 1/12/2017 CAROLYNN NEPOMUCENO
Green Plans Picked Up 1/18/2017 APPLICANT
Quality Review Completed 1/19/2017 ALLEN MANALANSAN
Building Plans Picked Up 1/20/2017 APPLICANT
Applicant returned to address corrections 1/31/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 3/7/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 3/16/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/19/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 4/27/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 5/5/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 5/24/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 7/5/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 7/20/2017 CAROLYNN NEPOMUCENO
Plan Check Approved 8/7/2017 CAROLYNN NEPOMUCENO
Issued 8/11/2017 LADBS
CofO in Progress 6/19/2024 CHRISTOPHER WILSON
Permit Finaled 6/24/2024 DANIEL ORRANTE
CofO Issued 6/24/2024 DANIEL ORRANTE
Permit Finaled 6/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2017 CELINA MORENO
Hydrant and Access approval Cleared 1/27/2017 JOHN CONNEALLY
Miscellaneous Cleared 1/27/2017 GRACIELA ACOSTA
Permit Cleared 1/27/2017 CELINA MORENO
Sewer availability Cleared 1/27/2017 CELINA MORENO
Building over 3-story or 36-ft Cleared 4/11/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/11/2017 CALOSHA APPROVED
Green Code Cleared 7/5/2017 NEGAR NEJAD
Low Impact Development Cleared 7/31/2017 MARTIN FRAGOSO
Address approval Cleared 8/1/2017 MARYAM AZARBAYJANI
GPI Written Notices Cleared 8/1/2017 ALLEN MANALANSAN
Grading Pre-Inspection Cleared 8/1/2017 ALLEN MANALANSAN
Roof/Waste drainage to street Cleared 8/1/2017 ARMENIA AGUILAR
Work Adjacent to Public Way Cleared 8/1/2017 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/3/2017 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/3/2017 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/3/2017 MARYAM AZARBAYJANI

Contact Information

Contractor Hy-Max Building Corp; Lic. No.: 702339-B 28376 CONSTELLATION ROAD      VALENCIA, CA 91355
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Melnyk, Matthew John; Lic. No.: S5853 2100 N MAIN STREET, SUITE A1      LOS ANGELES, CA 90031
Engineer Zhang, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/26/2017 Partial Approval MATT KELLERMAN
Pre-Inspection 1/30/2018 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 2/20/2018 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 2/20/2018 Partial Approval ANTHONY ANDERSON
Protected Tree Letter 2/20/2018 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 2/26/2018 Conditional Approval ANTHONY ANDERSON
Piling/Pier/Caisson 2/26/2018 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 2/28/2018 Corrections Issued ANTHONY ANDERSON
Piling/Pier/Caisson 2/28/2018 Partial Inspection ANTHONY ANDERSON
Special/Order Compliance 3/10/2018 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/21/2018 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 3/23/2018 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 3/23/2018 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 3/23/2018 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 3/28/2018 Conditional Approval ANTHONY ANDERSON
Pre-Inspection 4/9/2018 Partial Inspection ANTHONY ANDERSON
Piling/Pier/Caisson 4/12/2018 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 4/16/2018 Approved MATT KELLERMAN
Piling/Pier/Caisson 5/4/2018 Partial Inspection ANTHONY ANDERSON
Piling/Pier/Caisson 5/21/2018 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 5/23/2018 Partial Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 5/29/2018 Partial Inspection THOMAS FINNILA
Deputy Reinf. Concrete 5/31/2018 Conditional Approval JONATHAN HOM
Special/Order Compliance 6/2/2018 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/13/2018 Conditional Approval MATT KELLERMAN
Footing/Foundation/Slab 9/21/2018 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/5/2018 Partial Approval MATT KELLERMAN
Green Building Rough 10/12/2018 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 10/12/2018 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/12/2018 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 12/4/2018 Not Ready for Inspection DANIEL ORRANTE
Sewer 12/4/2018 Not Ready for Inspection DANIEL ORRANTE
ELECTRICAL-Rough 1/10/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/10/2019 Partial Approval CHRISTOPHER WILSON
Pool Piping 1/10/2019 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 2/25/2019 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 2/28/2019 Partial Approval ROBERT SHELLY
Piling/Pier/Caisson 3/21/2019 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 4/8/2019 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 4/30/2019 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/1/2019 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 5/3/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/7/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/9/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/9/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Pre-Stress Concrete 5/10/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/14/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Shotcrete 5/14/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 5/14/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 5/15/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/17/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/21/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/21/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 5/21/2019 Partial Inspection CHRISTOPHER WILSON
Pool/Spa Cover 5/21/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/21/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/21/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Shotcrete 5/22/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/24/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Shotcrete 6/12/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/13/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/14/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/18/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/18/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/19/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/21/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 6/21/2019 Partial Inspection CHRISTOPHER WILSON
Pool Piping 6/21/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 6/21/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/21/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/25/2019 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 6/25/2019 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 6/25/2019 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 6/25/2019 Not Ready for Inspection CARLOS MATAMOROS
Deputy Shotcrete 6/26/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/27/2019 Approved ROBERT SHELLY
Green Building Rough 6/27/2019 Not Ready for Inspection ROBERT SHELLY
Reinforced Concrete Frame 6/27/2019 Partial Approval ROBERT SHELLY
Verify Sprinkler Sign Off 6/27/2019 Not Ready for Inspection ROBERT SHELLY
Deputy Shotcrete 6/28/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/2/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/2/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/3/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/3/2019 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 7/3/2019 Not Ready for Inspection MICHAEL TEMPLE
Reinforced Concrete Frame 7/3/2019 Partial Approval MICHAEL TEMPLE
Verify Sprinkler Sign Off 7/3/2019 Not Ready for Inspection MICHAEL TEMPLE
Deputy Reinf. Concrete 7/11/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 7/11/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 7/11/2019 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/11/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 7/13/2019 Off-Hour Fees Due
Reinforced Concrete Frame 7/13/2019 Off-Hour Fees Due
Verify Sprinkler Sign Off 7/13/2019 Off-Hour Fees Due
Deputy Reinf. Concrete 7/15/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/4/2019 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/5/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/5/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 9/6/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/24/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/24/2019 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 9/24/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 9/24/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/24/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 9/27/2019 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 10/8/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/4/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/5/2019 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 11/7/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/18/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/20/2019 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 11/21/2019 Partial Approval MATT KELLERMAN
Deck 11/25/2019 Approved ANTHONY MCDOWALL
Deputy Reinf. Concrete 11/25/2019 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 11/26/2019 No Access for Inspection MATT KELLERMAN
Deputy Reinf. Concrete 12/2/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/14/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/15/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/16/2020 Partial Approval MATT KELLERMAN
Green Building Rough 1/16/2020 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/16/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Shotcrete 1/17/2020 No Access for Inspection MATT KELLERMAN
Footing/Foundation/Slab 1/17/2020 Corrections Issued MATT KELLERMAN
Reinforced Concrete Frame 1/17/2020 Not Ready for Inspection MATT KELLERMAN
Deputy Shotcrete 1/21/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/21/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/22/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/4/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/5/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/5/2020 Partial Approval ANTHONY MCDOWALL
Deputy Shotcrete 2/6/2020 Partial Approval MATT KELLERMAN
Deputy Shotcrete 2/7/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/27/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 3/6/2020 Partial Approval MATT KELLERMAN
Green Building Rough 4/1/2020 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 4/1/2020 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/1/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 4/17/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/20/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/21/2020 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 4/21/2020 Partial Inspection CHRISTOPHER WILSON
Underground Mechanical 4/21/2020 Partial Inspection CHRISTOPHER WILSON
Deck 4/22/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 4/22/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/22/2020 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 4/22/2020 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 4/22/2020 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/22/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/23/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/23/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/24/2020 Partial Approval MATT KELLERMAN
Reinforced Masonry Frame 4/24/2020 Partial Approval CHRISTOPHER WILSON
Deck 4/27/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/27/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/11/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/12/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 5/13/2020 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 5/26/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/27/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 5/28/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 6/4/2020 Conditional Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 6/4/2020 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 6/5/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/5/2020 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 6/9/2020 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 6/26/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/29/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 6/29/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/1/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Masonry 7/13/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Masonry 7/14/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Masonry 7/15/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Masonry 7/16/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Masonry 7/17/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Masonry 7/28/2020 Conditional Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 7/29/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 8/5/2020 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 8/13/2020 Corrections Issued CHRISTOPHER WILSON
Wood Frame 8/18/2020 Partial Approval CHRISTOPHER WILSON
Insulation 10/6/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 10/21/2020 Partial Approval CHRISTOPHER WILSON
Insulation 10/21/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 10/21/2020 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/4/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 11/4/2020 Not Ready for Inspection ANTHONY MCDOWALL
Insulation 11/4/2020 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 11/19/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/23/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 12/30/2020 Partial Approval MATT KELLERMAN
Insulation 1/29/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 2/8/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Approval MATT KELLERMAN
Piling/Pier/Caisson 6/4/2021 Off-Hour Fees Due
Piling/Pier/Caisson 6/4/2021 Partial Approval MATT KELLERMAN
Green Building Rough 6/9/2021 Not Ready for Inspection MATT KELLERMAN
Piling/Pier/Caisson 6/9/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/9/2021 Not Ready for Inspection MATT KELLERMAN
Reinforced Masonry Frame 6/9/2021 Not Ready for Inspection MATT KELLERMAN
Verify Sprinkler Sign Off 6/9/2021 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 6/15/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 6/15/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/15/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/22/2021 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 8/18/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 8/18/2021 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/18/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 8/19/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/20/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/1/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 9/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/3/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/17/2021 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 9/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 9/22/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
Masonry Wall/Backfill 10/22/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 12/7/2021 Partial Approval BRENDAN LOONEY
Structural Steel Frame 12/10/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 1/24/2022 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/11/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 3/3/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 3/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 3/10/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 3/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Shotcrete 3/14/2022 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 5/4/2022 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 5/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/5/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 5/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/10/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 5/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/24/2022 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/25/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 6/9/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/14/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 6/14/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 6/14/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Approved CHRISTOPHER WILSON
Green Building Rough 6/16/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/16/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 8/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/11/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 8/18/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/23/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 8/23/2022 Partial Approval CHRISTOPHER WILSON
Final 8/24/2022 Corrections Issued CHRISTOPHER WILSON
Wood Frame 8/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/30/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/8/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 9/8/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 9/27/2022 Conditional Approval MICHAEL PELHAM
Insulation 9/30/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 10/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 10/3/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 10/3/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/5/2022 Conditional Approval CHRISTOPHER WILSON
Insulation 10/6/2022 Partial Approval CLAYTON GRAHAM
Special/Order Compliance 10/6/2022 Partial Inspection STEPHANIE SWANSON
Final 10/13/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 10/13/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 10/13/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 10/17/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/17/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 11/7/2022 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 11/16/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 12/15/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 12/15/2022 Approved CHRISTOPHER WILSON
Shower Pan 2/16/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 2/17/2023 Approved CHRISTOPHER WILSON
Shower Pan 2/17/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 2/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 3/10/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 4/7/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 4/14/2023 Approved CHRISTOPHER WILSON
Pre-Inspection 8/15/2023 Partial Approval CHRISTOPHER WILSON
Service/Power Release 10/4/2023 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 11/10/2023 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 11/13/2023 Approved CHRISTOPHER WILSON
HVAC-Final 11/15/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 11/15/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 11/16/2023 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/17/2023 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 11/17/2023 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Not Required CHRISTOPHER WILSON
HVAC-Final 11/27/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 11/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 11/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 12/1/2023 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 12/5/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 12/20/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 12/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/25/2024 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 4/3/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 4/4/2024 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 4/23/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Final 4/30/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 5/10/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 5/15/2024 No Access for Inspection CHRISTOPHER WILSON
PLUMBING-Final 5/17/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 5/20/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 5/20/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 5/21/2024 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 5/24/2024 Approved CHRISTOPHER WILSON
Green Building Final 5/24/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 5/24/2024 Approved CHRISTOPHER WILSON
Final 6/7/2024 Corrections Issued CHRISTOPHER WILSON
Final 6/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 6/17/2024 OK to Issue CofO CHRISTOPHER WILSON