20944 W VANOWEN ST 91303

Certificate Information: 20944 W VANOWEN ST 91303

Application / Permit
16010-10000-04924
Plan Check / Job No.
B16LA16547
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6-STORY 38 UNITS TYPE IIIA APARTMENT BUILDING OVER 1-STORY TYPE IA BASEMENT GARAGE PER DIR-2016-3485-AC.
Permit Issued
Issued on 3/8/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2016 APPLICANT
Assigned to Plan Check Engineer 11/17/2016 SHUNYU ZHANG
Corrections Issued 11/28/2016 HOK CHI CHIU
Green Plans Picked Up 12/8/2016 APPLICANT
Disabled Access Plans Picked Up 12/9/2016 APPLICANT
Quality Review Completed 12/16/2016 BILL STUTSMAN
Applicant returned to address corrections 2/6/2017 HOK CHI CHIU
Applicant returned to address corrections 5/31/2017 LARRY LEE
Applicant returned to address corrections 6/8/2017 LARRY LEE
Applicant returned to address corrections 9/6/2017 LARRY LEE
Plan Check Approved 9/18/2017 LARRY LEE
Issued 3/8/2018 LADBS
TCO Issued (Expire Date: 06-10-2024) 12/13/2023 JEFFREY DURAN
CofO in Progress 2/20/2024 DEANDRE HOFFMAN
Permit Finaled 3/4/2024 RICKEY JACKSON
CofO Issued 3/4/2024 RICKEY JACKSON
Permit Finaled 3/4/2024 RICKEY JACKSON

Permit Application Clearance Information

DAS Clearance Cleared 3/8/2017 SHINE LIN
Hydrant and Access approval Cleared 3/13/2017 JOHN DALLAS
Green Code Cleared 3/20/2017 MICKEY YAMASHITA
Address approval Cleared 6/8/2017 CARLA VALLADARES
Eng Process Fee Ord 176,300 Cleared 6/8/2017 CARLA VALLADARES
Work Adjacent to Public Way Cleared 6/8/2017 RAVIL MANAPOV
Fire Marshall Fire Life Safety Cleared 6/12/2017 MENOA AGHAJANI
Highway dedication Cleared 6/20/2017 LEE GUILBEAUX
Sewer availability Cleared 6/20/2017 LEE GUILBEAUX
Low Impact Development Cleared 6/30/2017 SAM NAVID
Frnt yard landscape/Water mgmt Cleared 9/1/2017 DANIEL SKOLNICK
Miscellaneous Cleared 9/1/2017 DANIEL SKOLNICK
Miscellaneous Cleared 9/1/2017 DANIEL SKOLNICK
Miscellaneous Cleared 9/1/2017 DANIEL SKOLNICK
Opn space landscape/Water mgmt Cleared 9/1/2017 DANIEL SKOLNICK
Specific Plan Cleared 9/1/2017 DANIEL SKOLNICK
ZI Cleared 9/1/2017 DANIEL SKOLNICK
Building over 3-story or 36-ft Cleared 9/6/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/6/2017 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 9/8/2017 PATRICK YUAN
Specific Plan Cleared 9/11/2017 VICENTE CORDERO
Permit Cleared 9/14/2017 MARKOS PEREZ-BRAN

Contact Information

Architect Safai, Daryoush; Lic. No.: C13017 2932 WILSHIRE BLVD #210      SANTA MONICA, CA 90403
Contractor Quillin Construction Corp; Lic. No.: 574175-B 23901 CALABASAS ROAD STE 2010      CALABASAS, CA 91302
Engineer Naim, Soleiman Israel; Lic. No.: S2454 403 21ST ST      SANTA MONICA, CA 90402
Engineer Smith, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2018 Partial Inspection JEFFREY DURAN
Pre-Inspection 4/3/2018 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/6/2018 Partial Approval JEFFREY DURAN
Pre-Inspection 4/6/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 5/15/2018 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/21/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 7/26/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/7/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 8/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/10/2018 Conditional Approval JEFFREY DURAN
Piling/Pier/Caisson 8/10/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/13/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/14/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/14/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/15/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/15/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/16/2018 Partial Approval JEFFREY DURAN
Piling/Pier/Caisson 8/16/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/20/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/22/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/23/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 8/24/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/24/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/27/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/27/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/28/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/29/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/30/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/31/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/6/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/7/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/10/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/10/2018 Partial Approval JEFFREY DURAN
Deputy Shotcrete 9/11/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/11/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/12/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/18/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/18/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/20/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 9/20/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 9/21/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 9/21/2018 Approved JEFFREY DURAN
Masonry Wall/Backfill 9/21/2018 Partial Approval JEFFREY DURAN
Reinforced Concrete Frame 9/21/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/24/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/2/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 10/3/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 10/4/2018 Approved JEFFREY DURAN
Masonry Wall/Backfill 10/4/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/5/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 11/20/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/8/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/19/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/20/2019 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/20/2019 Partial Approval JEFFREY DURAN
Deputy Shotcrete 2/22/2019 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 3/5/2019 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/19/2019 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 3/19/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/26/2019 Conditional Approval JAMES STEPHENS
Excavation/Setback/Form/Re-Bar 3/26/2019 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/27/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 4/2/2019 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 4/2/2019 Partial Approval DANIEL VARNUM
Masonry Wall/Backfill 4/2/2019 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Masonry 4/3/2019 Approved JEFFREY DURAN
Masonry Wall/Backfill 4/3/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/4/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/5/2019 Conditional Approval DANIEL VARNUM
Masonry Wall/Backfill 4/5/2019 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/8/2019 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 4/8/2019 Partial Approval ROBERT COLE
Green Building Rough 4/8/2019 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 4/8/2019 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 4/8/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 4/9/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/10/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/11/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/12/2019 Approved JEFFREY DURAN
Masonry Wall/Backfill 4/12/2019 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/23/2019 No Access for Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 4/25/2019 Not Ready for Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 7/18/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 7/18/2019 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/5/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 8/5/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/8/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/19/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/21/2019 Approved JEFFREY DURAN
Green Building Rough 10/21/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 10/21/2019 Corrections Issued JEFFREY DURAN
Wood Frame 10/21/2019 Partial Inspection JEFFREY DURAN
Deputy Wood Construction 10/22/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/23/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/24/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/25/2019 Conditional Approval ALAN NOVAK
Deputy Wood Construction 11/4/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/5/2019 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/5/2019 Conditional Approval ROBERT COLE
Deputy Wood Construction 11/6/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/7/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/8/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/9/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/10/2019 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/10/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/11/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/12/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/13/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/8/2020 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 1/9/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/10/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/13/2020 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/14/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/15/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/16/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/17/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/4/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/5/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/6/2020 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/7/2020 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Partial Approval JEFFREY DURAN
Special/Order Compliance 2/7/2020 Corrections Issued JEFFREY DURAN
Special/Order Compliance 4/6/2020 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 8/14/2020 Corrections Issued JEFFREY DURAN
Green Building Rough 8/19/2020 Partial Inspection SORIN CIRSTOIU
Verify Sprinkler Sign Off 8/19/2020 Partial Inspection SORIN CIRSTOIU
Wood Frame 8/19/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 8/21/2020 Not Ready for Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 8/21/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 8/21/2020 Partial Approval JONATHAN QUACH
Deputy Wood Construction 10/5/2020 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/6/2020 Approved HAMID PISHEHVAR
Green Building Rough 10/6/2020 Not Ready for Inspection HAMID PISHEHVAR
Verify Sprinkler Sign Off 10/6/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 10/6/2020 Partial Approval HAMID PISHEHVAR
Insulation 11/5/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/13/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 11/17/2020 Approved HAMID PISHEHVAR
Green Building Rough 11/23/2020 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 11/23/2020 Approved JOHN KITCKO
Wood Frame 11/23/2020 Not Ready for Inspection JOHN KITCKO
Deputy Other (see comments) 11/24/2020 Conditional Approval RICKEY JACKSON
Deputy Wood Construction 11/24/2020 Conditional Approval RICKEY JACKSON
Deputy Other (see comments) 11/25/2020 Conditional Approval ALAN NOVAK
Deputy Wood Construction 11/25/2020 Conditional Approval ALAN NOVAK
Deputy Wood Construction 11/30/2020 Conditional Approval ALAN NOVAK
Green Building Rough 11/30/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 11/30/2020 Not Ready for Inspection HAMID PISHEHVAR
Deputy Wood Construction 12/1/2020 Approved HAMID PISHEHVAR
Green Building Rough 12/3/2020 Partial Approval HAMID PISHEHVAR
Wood Frame 12/3/2020 Partial Approval HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Order to Comply Issued HAMID PISHEHVAR
Insulation 12/22/2020 Not Ready for Inspection GRANT WOODS
Green Building Rough 12/23/2020 Not Ready for Inspection ROBERT DAVIS
Insulation 12/23/2020 Not Ready for Inspection ROBERT DAVIS
Wood Frame 12/23/2020 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Corrections Issued ROBERT DAVIS
Insulation 1/11/2021 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval HAMID PISHEHVAR
Wall Anchors 1/12/2021 Partial Approval ROBERT DAVIS
Insulation 1/20/2021 Order to Comply Issued ROBERT DAVIS
Insulation 1/21/2021 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Not Ready for Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Approved HAMID PISHEHVAR
Drywall Nailing 2/2/2021 Partial Inspection CAMERON CHABAN
Green Building Rough 2/2/2021 Partial Inspection CAMERON CHABAN
Insulation 2/4/2021 Approved HAMID PISHEHVAR
Drywall Nailing 2/17/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 2/17/2021 Partial Inspection CAMERON CHABAN
Drywall Nailing 2/19/2021 Partial Inspection CAMERON CHABAN
Green Building Rough 2/19/2021 Partial Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Corrections Issued CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Approved HAMID PISHEHVAR
Deputy Steel/Welding 3/10/2021 Approved HAMID PISHEHVAR
Deputy Steel/Welding 3/11/2021 Approved HAMID PISHEHVAR
Drywall Nailing 3/12/2021 Partial Approval CAMERON CHABAN
Green Building Rough 3/12/2021 Partial Inspection CAMERON CHABAN
Drywall Nailing 3/18/2021 Partial Approval CAMERON CHABAN
Green Building Rough 3/18/2021 Partial Inspection CAMERON CHABAN
Special/Order Compliance 3/24/2021 Partial Approval CAMERON CHABAN
Insulation 4/26/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/5/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 5/5/2021 Approved CAMERON CHABAN
Insulation 5/5/2021 Partial Approval CAMERON CHABAN
Pre-Inspection 6/3/2021 Partial Inspection HAMID PISHEHVAR
Insulation 6/7/2021 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 6/10/2021 Partial Approval CAMERON CHABAN
Insulation 6/18/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/30/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 7/1/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 7/7/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 7/8/2021 Partial Approval CAMERON CHABAN
Wood Frame 7/13/2021 Partial Approval CAMERON CHABAN
Wood Frame 7/15/2021 No Access for Inspection JEFF BYTHEWAY
Drywall Nailing 7/19/2021 Partial Approval CAMERON CHABAN
Insulation 7/27/2021 Conditional Approval CAMERON CHABAN
Wood Frame 7/29/2021 No Access for Inspection DANIEL VARNUM
Wood Frame 8/2/2021 Conditional Approval CAMERON CHABAN
Insulation 8/3/2021 Partial Approval CAMERON CHABAN
Insulation 8/11/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 8/17/2021 Partial Inspection JONATHAN QUACH
Insulation 8/19/2021 Partial Inspection CAMERON CHABAN
Insulation 8/20/2021 Partial Approval CAMERON CHABAN
Interior/Exterior Lathing 8/24/2021 Conditional Approval CAMERON CHABAN
Pre-Inspection 8/24/2021 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 8/26/2021 Conditional Approval CAMERON CHABAN
Wood Frame 9/7/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 9/13/2021 Partial Approval CAMERON CHABAN
Wood Frame 9/30/2021 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/8/2021 Partial Inspection DANIEL VARNUM
Insulation 11/23/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 11/30/2021 Partial Approval CAMERON CHABAN
Wood Frame 11/30/2021 Conditional Approval CAMERON CHABAN
Drywall Nailing 2/23/2022 Partial Approval CAMERON CHABAN
Wood Frame 5/11/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 5/13/2022 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 6/14/2022 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 6/16/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 6/21/2022 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 7/15/2022 Partial Approval CAMERON CHABAN
Grading Pre-Inspection 10/20/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 10/26/2022 Partial Inspection CAMERON CHABAN
Light Gage Steel Frame 10/26/2022 Partial Inspection CAMERON CHABAN
Light Gage Steel Frame 12/1/2022 Not Ready for Inspection CAMERON CHABAN
Light Gage Steel Frame 12/27/2022 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 1/6/2023 Corrections Issued DANIEL VARNUM
Special/Order Compliance 1/11/2023 Partial Inspection CAMERON CHABAN
Special/Order Compliance 1/11/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 1/18/2023 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 1/18/2023 Not Ready for Inspection CAMERON CHABAN
Special/Order Compliance 1/25/2023 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 1/27/2023 Partial Approval CAMERON CHABAN
Special/Order Compliance 1/27/2023 Partial Inspection CAMERON CHABAN
Drywall Nailing 2/15/2023 Partial Inspection BRIAN KELLY
Drywall Nailing 2/21/2023 Approved DANIEL VARNUM
Special/Order Compliance 2/21/2023 Not Ready for Inspection DANIEL VARNUM
Final 5/15/2023 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/15/2023 Conditional Approval CAMERON CHABAN
Green Building Final 5/15/2023 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 5/15/2023 Conditional Approval CAMERON CHABAN
Reinforced Masonry Frame 5/15/2023 Conditional Approval CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 5/15/2023 Not Ready for Inspection CAMERON CHABAN
Special/Order Compliance 5/15/2023 Conditional Approval CAMERON CHABAN
Wood Frame 5/15/2023 Approved CAMERON CHABAN
Smoke Detectors 7/27/2023 Partial Inspection CAMERON CHABAN
Green Building Final 9/15/2023 Not Ready for Inspection STEVEN LEVITT
Special/Order Compliance 9/15/2023 Not Ready for Inspection STEVEN LEVITT
Special/Order Compliance 9/19/2023 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 9/25/2023 Approved CAMERON CHABAN
Special/Order Compliance 10/17/2023 Approved CAMERON CHABAN
Final 11/16/2023 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 11/16/2023 Approved CAMERON CHABAN
Green Building Final 11/16/2023 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 11/16/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 11/16/2023 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved CAMERON CHABAN
Smoke Detectors 11/16/2023 Approved CAMERON CHABAN
Final 12/8/2023 Not Ready for Inspection CAMERON CHABAN
Green Building Final 12/8/2023 Not Ready for Inspection CAMERON CHABAN
Final 1/22/2024 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 1/22/2024 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 1/23/2024 Corrections Issued DEANDRE HOFFMAN
Final 2/9/2024 Not Ready for Inspection JEFFREY DURAN
Green Building Final 2/9/2024 Not Ready for Inspection JEFFREY DURAN
Final 2/12/2024 Partial Inspection DEANDRE HOFFMAN
Green Building Final 2/12/2024 Approved DEANDRE HOFFMAN
Final 2/20/2024 OK to Issue CofO DEANDRE HOFFMAN