2598 N THAMES PL 90046
Certificate Information: 2598 N THAMES PL 90046
- Application / Permit
- 16010-10000-04899
- Plan Check / Job No.
- B16LA16457
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 10/2/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2016 | APPLICANT |
| Green Plans Picked Up | 11/22/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2016 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 12/6/2016 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 12/7/2016 | RICARDO TRES |
| Building Plans Picked Up | 12/8/2016 | APPLICANT |
| Applicant returned to address corrections | 4/10/2018 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/17/2018 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 10/2/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 10/2/2019 | LADBS |
| CofO in Progress | 12/3/2025 | ROY SPAULDING |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
| CofO Issued | 12/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/7/2018 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 2/8/2018 | CARLA VALLADARES |
| Green Code | Cleared | 3/22/2018 | MICKEY YAMASHITA |
| Low Impact Development | Cleared | 4/11/2018 | SAM NAVID |
| BHO/Hillside ordinance | Cleared | 6/27/2018 | DENNIS BRAGIN |
| Construction within easement | Cleared | 7/11/2018 | RIDWAN HARDY |
| Excavation more than 5-ft deep | Cleared | 1/29/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/29/2019 | TEODORO DIAZ RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 1/29/2019 | TEODORO DIAZ RODRIGUEZ |
| Disturb/Remove Protected Trees | Cleared | 8/21/2019 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 8/23/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 8/23/2019 | SARAH GOLDMAN |
| Hydrant and Access approval | Cleared | 8/26/2019 | ROBERT DUFF |
| Permit | Cleared | 9/24/2019 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 9/24/2019 | LINDA MARGARET |
| BHO/Hillside ordinance | Cleared | 9/25/2019 | LINDA MARGARET |
| Encroachment in public way | Cleared | 9/25/2019 | ELENA LOPEZ |
| Miscellaneous | Cleared | 10/1/2019 | LINDA MARGARET |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ochsner, Richard John; Lic. No.: C35218 | 14146 182 AVE NE WOODINVILLE, WA 98072 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/9/2020 | Partial Approval | RAUL BARAJAS |
| Special/Order Compliance | 12/29/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/8/2021 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 2/8/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/17/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/8/2021 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 8/11/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 8/11/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 8/11/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 10/4/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 10/4/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 10/4/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/10/2021 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/26/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 12/16/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Steel/Welding | 4/4/2023 | Approved | STUART CHAPMAN |
| Piling/Pier/Caisson | 4/20/2023 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/17/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Steel/Welding | 9/20/2023 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 9/21/2023 | Conditional Approval | STUART CHAPMAN |
| Deputy Steel/Welding | 9/22/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 10/10/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 10/13/2023 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/16/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 10/16/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 10/16/2023 | Partial Approval | STUART CHAPMAN |
| Reinforced Concrete Frame | 10/16/2023 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/16/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/11/2023 | Partial Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 12/11/2023 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 12/11/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 1/23/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Reinforced Concrete Frame | 1/23/2024 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 1/23/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/27/2024 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 4/2/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 4/2/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 4/26/2024 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/13/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/13/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/17/2024 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 5/17/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/23/2024 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 6/3/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/27/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 10/21/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 4/22/2025 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Final | 4/22/2025 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Final | 4/22/2025 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Final | 4/28/2025 | Approved | ROY SPAULDING |
| HVAC-Final | 4/28/2025 | Approved | ROY SPAULDING |
| PLUMBING-Final | 4/28/2025 | Approved | ROY SPAULDING |
| Final | 10/22/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 10/22/2025 | Approved | ROY SPAULDING |
| Green Building Final | 10/22/2025 | Approved | ROY SPAULDING |
| Reinforced Concrete Frame | 10/22/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV No Gas | ROY SPAULDING |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 10/22/2025 | Approved | ROY SPAULDING |
| Structural Steel Frame | 10/22/2025 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 10/22/2025 | Approved | ROY SPAULDING |
| Final | 11/14/2025 | Corrections Issued | ROY SPAULDING |
| Service/Power Release | 11/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 11/21/2025 | Corrections Issued | ROY SPAULDING |
| Service/Power Release | 11/21/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 12/2/2025 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 12/2/2025 | Approved | ROY SPAULDING |