2598 N THAMES PL 90046

Certificate Information: 2598 N THAMES PL 90046

Application / Permit
16010-10000-04899
Plan Check / Job No.
B16LA16457
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 10/2/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2016 APPLICANT
Green Plans Picked Up 11/22/2016 APPLICANT
Assigned to Plan Check Engineer 12/1/2016 TEODORO DIAZ RODRIGUEZ
Corrections Issued 12/6/2016 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 12/7/2016 RICARDO TRES
Building Plans Picked Up 12/8/2016 APPLICANT
Applicant returned to address corrections 4/10/2018 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/17/2018 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 10/2/2019 TEODORO DIAZ RODRIGUEZ
Issued 10/2/2019 LADBS
CofO in Progress 12/3/2025 ROY SPAULDING
Permit Finaled 12/4/2025 DEROLD HAUFF
Permit Finaled 12/4/2025 DEROLD HAUFF
CofO Issued 12/4/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/7/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 2/7/2018 KAYLA PEJI
Sewer availability Cleared 2/8/2018 CARLA VALLADARES
Green Code Cleared 3/22/2018 MICKEY YAMASHITA
Low Impact Development Cleared 4/11/2018 SAM NAVID
BHO/Hillside ordinance Cleared 6/27/2018 DENNIS BRAGIN
Construction within easement Cleared 7/11/2018 RIDWAN HARDY
Excavation more than 5-ft deep Cleared 1/29/2019 CALOSHA APPROVED
GPI Written Notices Cleared 1/29/2019 TEODORO DIAZ RODRIGUEZ
Grading Pre-Inspection Cleared 1/29/2019 TEODORO DIAZ RODRIGUEZ
Disturb/Remove Protected Trees Cleared 8/21/2019 ADRIAN SANCHEZ
Specific Plan Cleared 8/23/2019 SARAH GOLDMAN
ZA Case Cleared 8/23/2019 SARAH GOLDMAN
Hydrant and Access approval Cleared 8/26/2019 ROBERT DUFF
Permit Cleared 9/24/2019 LINDA MARGARET
Roof/Waste drainage to street Cleared 9/24/2019 LINDA MARGARET
BHO/Hillside ordinance Cleared 9/25/2019 LINDA MARGARET
Encroachment in public way Cleared 9/25/2019 ELENA LOPEZ
Miscellaneous Cleared 10/1/2019 LINDA MARGARET

Contact Information

Contractor Owner-Builder       ,
Engineer Ochsner, Richard John; Lic. No.: C35218 14146 182 AVE NE      WOODINVILLE, WA 98072

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/28/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 11/9/2020 Partial Approval RAUL BARAJAS
Special/Order Compliance 12/29/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/8/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 2/8/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/4/2021 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/17/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/17/2021 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/8/2021 Partial Inspection RAUL BARAJAS
Green Building Rough 8/11/2021 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 8/11/2021 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 8/11/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 10/4/2021 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 10/4/2021 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 10/4/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 12/10/2021 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 8/26/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 9/14/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 12/16/2022 Partial Approval STUART CHAPMAN
Deputy Steel/Welding 4/4/2023 Approved STUART CHAPMAN
Piling/Pier/Caisson 4/20/2023 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/17/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 7/25/2023 Partial Approval STUART CHAPMAN
Deputy Steel/Welding 9/20/2023 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 9/21/2023 Conditional Approval STUART CHAPMAN
Deputy Steel/Welding 9/22/2023 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 10/10/2023 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 10/13/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 10/16/2023 Partial Approval STUART CHAPMAN
Green Building Rough 10/16/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 10/16/2023 Partial Approval STUART CHAPMAN
Reinforced Concrete Frame 10/16/2023 Partial Approval STUART CHAPMAN
Verify Sprinkler Sign Off 10/16/2023 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 12/11/2023 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 12/11/2023 Partial Approval ROY SPAULDING
Underground Mechanical 12/11/2023 Approved ROY SPAULDING
Green Building Rough 1/23/2024 Not Ready for Inspection STUART CHAPMAN
Reinforced Concrete Frame 1/23/2024 Partial Approval STUART CHAPMAN
Verify Sprinkler Sign Off 1/23/2024 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 2/27/2024 Partial Approval RAUL BARAJAS
Drywall Nailing 4/2/2024 Approved ROY SPAULDING
Green Building Rough 4/2/2024 Approved ROY SPAULDING
PLUMBING-Rough 4/26/2024 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 5/13/2024 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 5/13/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/17/2024 Partial Approval RAUL BARAJAS
HVAC-Rough 5/17/2024 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/23/2024 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 6/3/2024 Approved ALIZAH MAYAGOITIA
Insulation 6/3/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/27/2024 Approved RAUL BARAJAS
Shower Pan 10/21/2024 Approved JOSH MEISTER
ELECTRICAL-Final 4/22/2025 Not Ready for Inspection ROY SPAULDING
HVAC-Final 4/22/2025 Corrections Issued ROY SPAULDING
PLUMBING-Final 4/22/2025 Corrections Issued ROY SPAULDING
ELECTRICAL-Final 4/28/2025 Approved ROY SPAULDING
HVAC-Final 4/28/2025 Approved ROY SPAULDING
PLUMBING-Final 4/28/2025 Approved ROY SPAULDING
Final 10/22/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 10/22/2025 Approved ROY SPAULDING
Green Building Final 10/22/2025 Approved ROY SPAULDING
Reinforced Concrete Frame 10/22/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV No Gas ROY SPAULDING
Service/Power Release 10/22/2025 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 10/22/2025 Approved ROY SPAULDING
Structural Steel Frame 10/22/2025 Approved ROY SPAULDING
Verify Sprinkler Sign Off 10/22/2025 Approved ROY SPAULDING
Final 11/14/2025 Corrections Issued ROY SPAULDING
Service/Power Release 11/14/2025 Not Ready for Inspection ROY SPAULDING
Final 11/21/2025 Corrections Issued ROY SPAULDING
Service/Power Release 11/21/2025 Not Ready for Inspection ROY SPAULDING
Final 12/2/2025 OK to Issue CofO ROY SPAULDING
Service/Power Release 12/2/2025 Approved ROY SPAULDING