6327 W PRIMROSE AVE 90068

Certificate Information: 6327 W PRIMROSE AVE 90068

Application / Permit
16010-10000-04772
Plan Check / Job No.
B16LA16020
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SMALL LOT SUBDIVISION PURSUANT TO PARCEL MAP AA-2011-3250-PMLA-SL. PARCEL A: NEW SINGLE FAMILY DWELLING W/ ATTACHED GARAGE. A CERTIFICATE OF OCCUPANCY SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 12/16/2020
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2016 APPLICANT
Green Plans Picked Up 11/3/2016 APPLICANT
Assigned to Plan Check Engineer 11/9/2016 CAROLYNN NEPOMUCENO
Corrections Issued 12/2/2016 CAROLYNN NEPOMUCENO
Quality Review Completed 12/8/2016 ALLEN MANALANSAN
Applicant returned to address corrections 4/7/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 9/15/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 9/26/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 10/3/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 10/19/2017 CAROLYNN NEPOMUCENO
Plan Check Approved 11/30/2020 ZAW HAN
Issued 12/16/2020 APPLICANT
Building Plans Picked Up 12/17/2020 APPLICANT
CofO in Progress 2/7/2023 ALIZAH MAYAGOITIA
Permit Finaled 2/16/2023 DEROLD HAUFF
CofO Issued 2/16/2023 DEROLD HAUFF
Permit Finaled 2/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/23/2017 FATIMA GUERRA
Sewer availability Cleared 8/23/2017 FATIMA GUERRA
Eng Process Fee Ord 176,300 Cleared 8/29/2017 RAVIL MANAPOV
Hydrant and Access approval Cleared 9/19/2017 JOHN CONNEALLY
BHO/Hillside ordinance Cleared 9/22/2017 LINDA MARGARET
BHO/Hillside ordinance Cleared 9/22/2017 LINDA MARGARET
Highway dedication Cleared 9/22/2017 LINDA MARGARET
Miscellaneous Cleared 9/22/2017 LINDA MARGARET
Miscellaneous Cleared 9/22/2017 LINDA MARGARET
Permit Cleared 9/22/2017 LINDA MARGARET
Roof/Waste drainage to street Cleared 9/22/2017 LINDA MARGARET
BHO/Hillside ordinance Cleared 10/3/2017 NAZILA NOORIFAR
Green Code Cleared 6/5/2020 MICKEY YAMASHITA
Frnt yard landscape/Water mgmt Cleared 6/30/2020 JOE LUCKEY
Tract Map conditions Cleared 6/30/2020 JOE LUCKEY
ZA Case Cleared 6/30/2020 JOE LUCKEY
Low Impact Development Cleared 9/2/2020 IDA MEISAMI-FARD
Excavation more than 5-ft deep Cleared 11/30/2020 CALOSHA APPROVED
GPI Written Notices Cleared 11/30/2020 CAROLYNN NAPOMUCENO
Grading Pre-Inspection Cleared 11/30/2020 CAROLYNN NAPOMUCENO

Contact Information

Architect Texter, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE #295      WOODLAND HILLS, CA 91364
Engineer Lewis, Stephen H; Lic. No.: C70304 169 S BALDWIN AVE      SIERRA MADRE, CA 91024
Engineer Soma_Jr., Philip George; Lic. No.: C46231 17572 BECKWALL LANE      HUNTINGTON BEACH, CA 92649

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/19/2021 Partial Inspection SCOTT FINNILA
Underground Mechanical 6/16/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/25/2021 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 6/25/2021 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 7/12/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 7/20/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 8/3/2021 Partial Approval SCOTT FINNILA
Green Building Rough 8/3/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 8/17/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 9/17/2021 Partial Inspection SCOTT FINNILA
Drywall Nailing 10/1/2021 Partial Approval SCOTT FINNILA
Green Building Rough 10/1/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 10/5/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Partial Approval CRAIG DAVIS
Drywall Nailing 12/16/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 12/16/2021 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 12/17/2021 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 12/17/2021 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 12/22/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Approval STUART CHAPMAN
HVAC-Rough 2/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/22/2022 Conditional Approval SCOTT FINNILA
HVAC-Rough 2/24/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 2/25/2022 Corrections Issued SCOTT FINNILA
HVAC-Rough 3/3/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 3/9/2022 Approved SCOTT FINNILA
Insulation 3/9/2022 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 3/9/2022 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 3/16/2022 Partial Approval SCOTT FINNILA
HVAC-Rough 3/21/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 4/15/2022 Approved SCOTT FINNILA
Green Building Rough 4/15/2022 Approved SCOTT FINNILA
PLUMBING-Rough 4/15/2022 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 4/15/2022 Approved SCOTT FINNILA
Insulation 4/25/2022 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 4/29/2022 Partial Approval SCOTT FINNILA
Drywall Nailing 5/9/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/9/2022 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 6/21/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 7/29/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 8/3/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 10/3/2022 Partial Approval SCOTT FINNILA
HVAC-Final 11/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 11/3/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/3/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/7/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 12/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 12/2/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/9/2022 Approved SCOTT FINNILA
Service/Power Release 12/9/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 12/12/2022 Partial Inspection SCOTT FINNILA
PLUMBING-Final 12/12/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Approved SCOTT FINNILA
Final 12/28/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/28/2022 Approved SCOTT FINNILA
Service/Power Release 1/23/2023 Approved ALIZAH MAYAGOITIA
Final 2/7/2023 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 2/7/2023 Approved ALIZAH MAYAGOITIA
Smoke Detectors 2/7/2023 Approved ALIZAH MAYAGOITIA