4235 N CORONA DR 90032

Certificate Information: 4235 N CORONA DR 90032

Application / Permit
16010-10000-04685
Plan Check / Job No.
B16LA15746
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY HILLSIDE AREA (ZONING CODE) SFD WITH BASEMENT GARAGE
Permit Issued
Issued on 10/12/2018
Issuing Office
Metro
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2016 APPLICANT
Green Plans Picked Up 11/17/2016 APPLICANT
Assigned to Plan Check Engineer 11/22/2016 BIDYUT RATH
Corrections Issued 12/5/2016 BIDYUT RATH
Quality Review Completed 12/7/2016 LARRY LEE
Building Plans Picked Up 12/12/2016 APPLICANT
Applicant returned to address corrections 3/9/2017 BIDYUT RATH
Applicant returned to address corrections 6/26/2018 BIDYUT RATH
Applicant returned to address corrections 7/18/2018 BIDYUT RATH
Applicant returned to address corrections 7/23/2018 BIDYUT RATH
Applicant returned to address corrections 9/11/2018 BIDYUT RATH
Plan Check Approved 10/11/2018 BIDYUT RATH
Issued 10/12/2018 LADBS
CofO in Progress 1/26/2024 AMY COLIN
Permit Finaled 1/30/2024 DEROLD HAUFF
CofO Issued 1/30/2024 DEROLD HAUFF
Permit Finaled 1/30/2024 DEROLD HAUFF

Permit Application Clearance Information

"D" conditions Cleared 12/29/2016 MARY RICHARDSON
"Q" conditions Cleared 12/29/2016 MARY RICHARDSON
ZI Cleared 12/29/2016 MARY RICHARDSON
ZI Cleared 12/29/2016 MARY RICHARDSON
Green Code Cleared 3/1/2017 BIDYUT RATH
Grading Pre-Inspection Cleared 3/9/2017 BIDYUT RATH
Disturb/Remove Protected Trees Cleared 3/31/2017 LUIS TORRES
Green Code Cleared 7/18/2018 BIDYUT RATH
Address approval Cleared 7/24/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 7/24/2018 GEORGE SUCHAND
Miscellaneous Cleared 7/24/2018 GEORGE SUCHAND
Permit Cleared 7/24/2018 MICHAEL CASTILLO
Low Impact Development Cleared 7/30/2018 ANDRES COVARRUBIAS
BHO/Hillside ordinance Cleared 8/6/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/6/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/6/2018 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/6/2018 ADRIAN SANCHEZ
Sewer availability Cleared 8/6/2018 ADRIAN SANCHEZ
"D" conditions Cleared 8/15/2018 NICOLE SANCHEZ
"Q" conditions Cleared 8/15/2018 NICOLE SANCHEZ
ZI Cleared 8/15/2018 NICOLE SANCHEZ
BHO/Hillside ordinance Cleared 9/25/2018 STEVE MELGAR

Contact Information

Contractor C E M Construction Corporation; Lic. No.: 951234-B 8207 BROOKGREEN ROAD      DOWNEY, CA 90240
Engineer , ; Lic. No.: C86223 1840 S GAFFEY STREET   382    SAN PEDRO, CA 90731
Engineer Carrillo, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Geologist , ; Lic. No.: EG1314 501 VALIDO ROAD      ARCADIA, CA 91007

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/18/2021 Approved COREY HUPP
Footing/Foundation/Slab 7/1/2021 Corrections Issued COREY HUPP
Special/Order Compliance 7/1/2021 Approved COREY HUPP
Footing/Foundation/Slab 7/30/2021 Partial Approval COREY HUPP
Footing/Foundation/Slab 8/30/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 9/2/2021 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/4/2021 Off-Hour Fees Due
Green Building Rough 9/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Reinforced Concrete Frame 9/7/2021 Partial Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 9/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Reinf. Concrete 9/9/2021 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 9/16/2021 Partial Approval COREY HUPP
Masonry Wall/Backfill 10/20/2021 Partial Inspection COREY HUPP
Footing/Foundation/Slab 1/6/2022 Partial Approval RUBEN SALAS
PLUMBING-Rough 1/12/2022 Approved COREY HUPP
Footing/Foundation/Slab 1/24/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 1/24/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 2/2/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 2/3/2022 Conditional Approval MICHAEL LEWIS
Special/Order Compliance 2/3/2022 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 2/23/2022 Corrections Issued COREY HUPP
Footing/Foundation/Slab 3/2/2022 Approved COREY HUPP
Deputy Reinf. Concrete 3/4/2022 Conditional Approval COREY HUPP
PLUMBING-Rough 3/23/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Corrections Issued AMY COLIN
Special/Order Compliance 7/15/2022 Corrections Issued AMY COLIN
Special/Order Compliance 7/15/2022 Partial Inspection AMY COLIN
Special/Order Compliance 9/29/2022 Partial Inspection AMY COLIN
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Corrections Issued AMY COLIN
Green Building Rough 10/25/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 10/25/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 11/1/2022 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 11/1/2022 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Not Ready for Inspection AMY COLIN
Green Building Rough 11/1/2022 Not Ready for Inspection AMY COLIN
HVAC-Rough 11/1/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 11/1/2022 Corrections Issued AMY COLIN
Rough-Elec/Plmb/HVAC 11/1/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 11/1/2022 Not Ready for Inspection AMY COLIN
Wood Frame 11/1/2022 Corrections Issued AMY COLIN
ELECTRICAL-Rough 11/18/2022 Approved AMY COLIN
Gas Test 11/18/2022 Approved AMY COLIN
HVAC-Rough 11/18/2022 Approved AMY COLIN
PLUMBING-Rough 11/18/2022 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 11/18/2022 Approved AMY COLIN
BUILDING-Rough-Frame 11/23/2022 Partial Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Corrections Issued AMY COLIN
Green Building Rough 11/23/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 11/23/2022 Corrections Issued AMY COLIN
Deputy Wood Construction 11/30/2022 Conditional Approval AMY COLIN
Deputy Wood Construction 12/1/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Approved AMY COLIN
Wood Frame 12/1/2022 Approved AMY COLIN
Special/Order Compliance 1/10/2023 Approved AMY COLIN
BUILDING-Rough-Frame 2/15/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 2/15/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/7/2023 Not Ready for Inspection AMY COLIN
Service/Power Release 8/26/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/17/2023 Approved ROY SPAULDING
Final 11/17/2023 Corrections Issued ROY SPAULDING
Green Building Final 11/17/2023 Not Ready for Inspection ROY SPAULDING
Green Building Rough 11/17/2023 Approved ROY SPAULDING
Reinforced Concrete Frame 11/17/2023 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV No Gas ROY SPAULDING
Service/Power Release 11/17/2023 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 11/17/2023 Approved ROY SPAULDING
Drywall Nailing 11/28/2023 Approved AMY COLIN
ELECTRICAL-Final 11/28/2023 Corrections Issued AMY COLIN
Final 11/28/2023 Corrections Issued AMY COLIN
Green Building Final 11/28/2023 Approved AMY COLIN
HVAC-Final 11/28/2023 Approved AMY COLIN
PLUMBING-Final 11/28/2023 Corrections Issued AMY COLIN
Service/Power Release 11/28/2023 Not Ready for Inspection AMY COLIN
Final 1/12/2024 Partial Approval AMY COLIN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved AMY COLIN
Service/Power Release 1/12/2024 Approved AMY COLIN
Final 1/26/2024 OK to Issue CofO AMY COLIN