5842 W CARLTON WAY 90028

Certificate Information: 5842 W CARLTON WAY 90028

Application / Permit
16010-10000-04627
Plan Check / Job No.
B16LA15542
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 5 STORY 18 UNIT APARTMENT OVER 2 LEVELS OF BASEMENT GARAGE.
Permit Issued
Issued on 9/22/2017
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2016 APPLICANT
Assigned to Plan Check Engineer 10/27/2016 JOHN VASQUEZ
Corrections Issued 11/7/2016 JOHN VASQUEZ
Quality Review Completed 11/7/2016 JOHN VASQUEZ
Building Plans Picked Up 11/8/2016 APPLICANT
Disabled Access Plans Picked Up 2/2/2017 APPLICANT
Applicant returned to address corrections 2/22/2017 JOHN VASQUEZ
Applicant returned to address corrections 3/1/2017 JOHN VASQUEZ
Applicant returned to address corrections 3/7/2017 JOHN VASQUEZ
Applicant returned to address corrections 3/15/2017 JOHN VASQUEZ
Plan Check Approved 4/5/2017 JOHN VASQUEZ
Issued 9/22/2017 LADBS
TCO Issued (Expire Date: 06-13-2020) 12/16/2019 WINSTON DUNNING
TCO Issued (Expire Date: 12-15-2020) 6/18/2020 DAVID TSAU
TCO Issued (Expire Date: 06-27-2021) 12/29/2020 ERNESTO CORRAL
CofO in Progress 10/6/2021 DAVID BURKHEAD
Permit Finaled 10/7/2021 ERNESTO CORRAL
CofO Issued 10/7/2021 ERNESTO CORRAL
Permit Finaled 10/7/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 11/17/2016 AVALYN KAMACHI
Eng Process Fee Ord 176,300 Cleared 12/20/2016 IRENE CHIA
Sewer availability Cleared 12/20/2016 IRENE CHIA
Highway dedication Cleared 12/22/2016 AVALYN KAMACHI
Project located in CRA area Cleared 2/15/2017 JIM URQUHART
Project located in CRA area Cleared 2/15/2017 JIM URQUHART
ZA Case Cleared 2/16/2017 JESSE RAMOS
Driveway location Cleared 2/23/2017 COLLINS ALLAN
Internal circulation Cleared 2/23/2017 COLLINS ALLAN
Frnt yard landscape/Water mgmt Cleared 2/24/2017 JESSE RAMOS
Opn space landscape/Water mgmt Cleared 2/24/2017 JESSE RAMOS
DAS Clearance Cleared 3/14/2017 CHOI YAN
Hydrant and Access approval Cleared 3/15/2017 ROBERT DUFF
Green Code Cleared 3/21/2017 JOHN VASQUEZ
DCP conditions approval Cleared 3/24/2017 MARITES CUNANAN
Housing density bonus Cleared 3/24/2017 MARITES CUNANAN
Low Impact Development Cleared 3/24/2017 SAM NAVID
Roof/Waste drainage to street Cleared 3/24/2017 LINDA MARGARET
Stormwater Pollution Mitigatn Cleared 3/24/2017 SAM NAVID
Permit Cleared 3/29/2017 RAVIL MANAPOV
Work Adjacent to Public Way Cleared 3/29/2017 RAVIL MANAPOV
"Q" conditions Cleared 3/30/2017 ULISES GONZALEZ
Building over 3-story or 36-ft Cleared 3/30/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/30/2017 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 3/30/2017 DOMINIQUE MEDINA
Miscellaneous Cleared 3/30/2017 ULISES GONZALEZ
Hold Cleared 10/4/2021 JASON SHEETS

Contact Information

Architect Soler, Jeffrey Robert; Lic. No.: C30180 619 N KILKEA DRIVE      LOS ANGELES, CA 90048
Contractor Fassberg Construction Company; Lic. No.: 470049-B 17000 VENTURA BLVD #200      ENCINO, CA 91316
Contractor Gates Enterprises Inc; Lic. No.: 911062-C12 6 HUTTON CENTRE DRIVE #600      SANTA ANA, CA 92707
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SUSMP-Std. Urban Storm Water 12/1/2017 Partial Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 1/3/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Grading 1/17/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 1/25/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 2/1/2018 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 2/2/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/6/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/6/2018 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 2/7/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 2/8/2018 Conditional Approval TED RIES
Deputy Reinf. Masonry 2/9/2018 Conditional Approval TED RIES
Footing/Foundation/Slab 2/12/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/15/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 2/15/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 2/20/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/21/2018 Partial Approval TED RIES
Footing/Foundation/Slab 2/27/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 4/9/2018 Partial Approval JEFF BYTHEWAY
Green Building Rough 4/20/2018 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Masonry Frame 4/20/2018 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 4/20/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 5/9/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 5/9/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 5/10/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/14/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 5/15/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/16/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 5/30/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 5/30/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 5/31/2018 Conditional Approval TED RIES
Deputy Shotcrete 6/4/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 6/5/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/6/2018 Partial Approval TED RIES
Deputy Shotcrete 6/8/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/12/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/13/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/13/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/13/2018 Approved JEFF BYTHEWAY
Green Building Rough 6/14/2018 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 6/14/2018 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 6/14/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/15/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/15/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/18/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/18/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/18/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/19/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/19/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/19/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/20/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/20/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/26/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/26/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/27/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/27/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/27/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 6/28/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/28/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/6/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/6/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 7/10/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/10/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/10/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 7/11/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/11/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/11/2018 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 7/11/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 7/24/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 8/1/2018 Conditional Approval TED RIES
Footing/Foundation/Slab 8/2/2018 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 10/3/2018 Partial Approval JAMES POWERS
Deputy Wood Construction 10/4/2018 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 10/5/2018 Approved JEFF BYTHEWAY
Wood Frame 10/9/2018 Partial Approval TED RIES
Deputy Wood Construction 10/16/2018 Approved JEFF BYTHEWAY
Wood Frame 10/16/2018 Partial Inspection JEFF BYTHEWAY
Deputy Wood Construction 10/17/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 10/18/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 10/19/2018 Approved JEFF BYTHEWAY
Wood Frame 10/30/2018 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 10/31/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/1/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/2/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/6/2018 Approved JEFF BYTHEWAY
Structural Steel Frame 11/6/2018 Corrections Issued JEFF BYTHEWAY
Deputy Wood Construction 11/7/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/8/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/9/2018 Approved JEFF BYTHEWAY
Wood Frame 11/13/2018 Partial Inspection JEFF BYTHEWAY
Wood Frame 11/19/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Steel/Welding 11/26/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/26/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/27/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/28/2018 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 11/30/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/30/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/3/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/4/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/4/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/5/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/6/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/6/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/7/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/7/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/10/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/11/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/11/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/12/2018 Approved TED RIES
Deputy Wood Construction 12/12/2018 Approved TED RIES
Deputy Steel/Welding 12/13/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/13/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/14/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/14/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/17/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/17/2018 Approved JEFF BYTHEWAY
Wood Frame 12/17/2018 Partial Inspection JEFF BYTHEWAY
Deputy Steel/Welding 12/18/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/18/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/19/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/19/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/20/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/20/2018 Approved JEFF BYTHEWAY
Wood Frame 12/20/2018 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 12/21/2018 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/21/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/27/2018 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/28/2018 Approved TED RIES
Deputy Steel/Welding 12/31/2018 Approved TED RIES
Deputy Steel/Welding 1/2/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/2/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/3/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/3/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/4/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/4/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/7/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/8/2019 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/8/2019 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 1/9/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/10/2019 Conditional Approval TED RIES
Wood Frame 1/10/2019 Partial Approval LARRY ARNICK
Deputy Steel/Welding 1/16/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/17/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/18/2019 Approved JEFF BYTHEWAY
Wood Frame 1/24/2019 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 1/28/2019 Approved JEFF BYTHEWAY
Wood Frame 1/28/2019 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 1/29/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 1/30/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/30/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/30/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/6/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/7/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/8/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/11/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/12/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/13/2019 Approved JEFF BYTHEWAY
Pre-Inspection 2/13/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/14/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/15/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/21/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/22/2019 Conditional Approval TED RIES
Deputy Wood Construction 2/25/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/26/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/27/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/28/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/1/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/12/2019 Approved TED RIES
Deputy Wood Construction 3/12/2019 Approved TED RIES
Deputy Reinf. Concrete 3/13/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/13/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/14/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/14/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/15/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/15/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 3/18/2019 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 3/18/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/1/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/2/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/3/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/4/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/5/2019 Approved TED RIES
Deputy Wood Construction 4/9/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 4/10/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 4/11/2019 Approved JEFF BYTHEWAY
Insulation 4/17/2019 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 4/18/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/23/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/24/2019 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/26/2019 Partial Approval JEFF BYTHEWAY
Green Building Rough 4/26/2019 Not Ready for Inspection JEFF BYTHEWAY
Deputy Steel/Welding 5/2/2019 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Partial Approval JEFF BYTHEWAY
Wood Frame 5/7/2019 Partial Approval JEFF BYTHEWAY
Insulation 5/8/2019 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 5/9/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/13/2019 Approved JEFF BYTHEWAY
Insulation 5/14/2019 Partial Inspection JEFF BYTHEWAY
Insulation 5/15/2019 Not Ready for Inspection JEFF BYTHEWAY
Insulation 5/16/2019 Partial Approval JEFF BYTHEWAY
Insulation 5/17/2019 Partial Approval JEFF BYTHEWAY
Insulation 5/21/2019 Approved HAMID PISHEHVAR
Green Building Rough 5/24/2019 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 5/28/2019 Partial Approval JEFF BYTHEWAY
Wood Frame 5/29/2019 Partial Approval JEFF BYTHEWAY
Insulation 5/30/2019 Not Ready for Inspection TED RIES
Insulation 5/31/2019 Partial Approval TED RIES
Drywall Nailing 6/5/2019 Not Ready for Inspection JEFF BYTHEWAY
Insulation 6/6/2019 Not Ready for Inspection JEFF BYTHEWAY
Insulation 6/11/2019 Partial Approval JEFF BYTHEWAY
Insulation 6/18/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 6/20/2019 Not Ready for Inspection JEFF BYTHEWAY
Insulation 6/24/2019 Partial Approval JEFF BYTHEWAY
Insulation 6/25/2019 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 6/28/2019 Partial Approval JEFF BYTHEWAY
Insulation 7/2/2019 Not Ready for Inspection JEFF BYTHEWAY
Insulation 7/5/2019 Partial Inspection JEFF BYTHEWAY
Insulation 7/10/2019 Partial Approval JEFF BYTHEWAY
Insulation 7/18/2019 Corrections Issued JEFF BYTHEWAY
Insulation 7/23/2019 Not Ready for Inspection JEFF BYTHEWAY
Green Building Rough 7/26/2019 Approved JEFF BYTHEWAY
Insulation 7/30/2019 Partial Inspection DANIEL MC AULIFFE
Insulation 7/31/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 8/1/2019 Partial Inspection DANIEL MC AULIFFE
Insulation 8/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 8/14/2019 Partial Inspection JEFF BYTHEWAY
Insulation 8/29/2019 Partial Inspection JEFF BYTHEWAY
Pre-Inspection 8/29/2019 Approved JEFF BYTHEWAY
Drywall Nailing 9/4/2019 Partial Approval JEFF BYTHEWAY
Insulation 9/25/2019 Partial Inspection JEFF BYTHEWAY
Special/Order Compliance 10/25/2019 Approved JEFF BYTHEWAY
Insulation 10/30/2019 Partial Inspection JEFF BYTHEWAY
Final 11/7/2019 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 11/7/2019 Approved JEFF BYTHEWAY
Green Building Final 11/7/2019 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 11/7/2019 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 11/7/2019 Approved JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 11/7/2019 SGSOV Approved JEFF BYTHEWAY
SUSMP-Std. Urban Storm Water 11/7/2019 Approved JEFF BYTHEWAY
Smoke Detectors 11/7/2019 Not Ready for Inspection JEFF BYTHEWAY
Special/Order Compliance 11/7/2019 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 11/7/2019 Approved JEFF BYTHEWAY
Final 11/15/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 11/15/2019 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 11/15/2019 Not Ready for Inspection DAVID BURKHEAD
Final 11/21/2019 Partial Inspection DAVID BURKHEAD
Green Building Final 11/21/2019 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 11/21/2019 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 11/25/2019 Approved DAVID BURKHEAD
Final 11/27/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 11/27/2019 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 11/27/2019 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 12/2/2019 Partial Approval DAVID BURKHEAD
Special/Order Compliance 12/4/2019 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 12/5/2019 Not Ready for Inspection DAVID BURKHEAD
Final 12/6/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 12/6/2019 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 12/6/2019 Partial Approval DAVID BURKHEAD
Special/Order Compliance 12/9/2019 Partial Approval DAVID BURKHEAD
Final 5/22/2020 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 5/22/2020 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 5/22/2020 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 5/29/2020 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 11/25/2020 Approved DAVID BURKHEAD
Special/Order Compliance 6/3/2021 Approved DAVID BURKHEAD
Final 10/6/2021 OK to Issue CofO DAVID BURKHEAD
Green Building Final 10/6/2021 Approved DAVID BURKHEAD
Smoke Detectors 10/6/2021 Approved DAVID BURKHEAD