Sewer
|
5/9/2018
|
Not Ready for Inspection
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2018
|
Not Ready for Inspection
|
RICHARD STEINBACH
|
|
Footing/Foundation/Slab
|
8/16/2018
|
Not Ready for Inspection
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
8/24/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
Footing/Foundation/Slab
|
8/24/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
PLUMBING-Rough
|
10/10/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
Pre-Inspection
|
11/9/2018
|
Partial Inspection
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
11/14/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/7/2019
|
Corrections Issued
|
RICHARD STEINBACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/12/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
4/15/2019
|
Partial Approval
|
MICHAEL TEMPLE
|
|
Special/Order Compliance
|
4/15/2019
|
Corrections Issued
|
MICHAEL TEMPLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Deputy Steel/Welding
|
5/21/2019
|
Conditional Approval
|
TIM CHRISTENSEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/15/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
7/29/2019
|
Conditional Approval
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
8/2/2019
|
Conditional Approval
|
MICHAEL TEMPLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2019
|
Partial Inspection
|
DANNY TOLENTINO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/4/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/18/2020
|
Partial Approval
|
ROBERT SHELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/2/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
PLUMBING-Rough
|
4/2/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Insulation
|
4/14/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Special/Order Compliance
|
4/24/2020
|
Corrections Issued
|
KENNETH NAGLE
|
|
Special/Order Compliance
|
4/28/2020
|
Approved
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
4/30/2020
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Special/Order Compliance
|
7/7/2020
|
Partial Inspection
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Insulation
|
7/8/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Wood Frame
|
7/8/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
7/29/2020
|
Partial Approval
|
JOHN KIDWELL
|
|
Green Building Rough
|
7/29/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
7/29/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
ELECTRICAL-Rough
|
11/6/2020
|
Approved
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
11/6/2020
|
Approved
|
JOHN KIDWELL
|
|
Shower Pan
|
11/9/2020
|
Approved
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
11/18/2020
|
Approved
|
JOHN KIDWELL
|
|
Green Building Rough
|
11/18/2020
|
Approved
|
JOHN KIDWELL
|
|
HVAC-Rough
|
11/18/2020
|
Approved
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
11/18/2020
|
Approved
|
JOHN KIDWELL
|
|
Drywall Nailing
|
12/10/2020
|
Approved
|
DAVID HEINE
|
|
Insulation
|
12/10/2020
|
Approved
|
DAVID HEINE
|
|
Special/Order Compliance
|
3/12/2021
|
Corrections Issued
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
4/5/2021
|
Partial Approval
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
4/22/2021
|
Partial Approval
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
5/20/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Special/Order Compliance
|
10/25/2021
|
Corrections Issued
|
JOHN KIDWELL
|
|
Deputy Shotcrete
|
10/26/2021
|
Partial Approval
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
4/29/2022
|
No Access for Inspection
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
5/5/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
5/5/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
5/27/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
6/1/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Gas Test
|
12/12/2022
|
Approved
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
1/27/2023
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
ELECTRICAL-Final
|
2/2/2023
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
PLUMBING-Final
|
2/2/2023
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
HVAC-Final
|
2/27/2023
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
HVAC-Final
|
3/16/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
ELECTRICAL-Final
|
6/7/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
PLUMBING-Final
|
6/7/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
Pool/Spa Cover
|
6/7/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
Service/Power Release
|
6/26/2023
|
Approved
|
KENNETH NAGLE
|
|
Final
|
11/8/2023
|
OK to Issue CofO
|
ARAM AVEDISIAN
|
|
Footing/Foundation/Slab
|
11/8/2023
|
Approved
|
ARAM AVEDISIAN
|
|
Green Building Final
|
11/8/2023
|
Approved
|
ARAM AVEDISIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
11/8/2023
|
SGSOV Approved
|
ARAM AVEDISIAN
|
|
Smoke Detectors
|
11/8/2023
|
Approved
|
ARAM AVEDISIAN
|
|
Structural Steel Frame
|
11/8/2023
|
Approved
|
ARAM AVEDISIAN
|