215 W 14TH ST 90015

Certificate Information: 215 W 14TH ST 90015

Application / Permit
16010-10000-04283
Plan Check / Job No.
B16LA14735
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 7 STORY MIXED USE BUILDING. 6 STORY RESIDENTIAL OVER 1 STORY RETAIL, OFFICE, PARKING, OVER 2 LEVELS SUBTERRANEAN PARKING.
Permit Issued
Issued on 10/8/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2016 APPLICANT
Assigned to Plan Check Engineer 11/17/2016 LARRY LEE
Corrections Issued 11/22/2016 LARRY LEE
Quality Review Completed 11/22/2016 PETER KIM
Building Plans Picked Up 12/7/2016 APPLICANT
Applicant returned to address corrections 8/3/2017 LARRY LEE
Applicant returned to address corrections 9/26/2017 LARRY LEE
Applicant returned to address corrections 4/15/2019 LARRY LEE
Plan Check Approved 10/3/2019 LARRY LEE
Issued 10/8/2019 LADBS
TCO Issued (Expire Date: 10-14-2023) 4/17/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 08-31-2024) 3/4/2024 RAFAEL ESPINOZA
CofO in Progress 9/13/2024 NICK DANERI
CofO Issued 9/13/2024 ERNESTO CORRAL
Permit Finaled 9/13/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/26/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/26/2019 JEANIE LAM
Low Impact Development Cleared 5/10/2019 MARTIN FRAGOSO
Driveway location Cleared 5/23/2019 MOHAMMAD HASAN
Project located in CRA area Cleared 7/18/2019 JIM URQUHART
Roof/Waste drainage to street Cleared 7/19/2019 ELENA LOPEZ
Building over 3-story or 36-ft Cleared 7/22/2019 CALOSHA APPROVED
Tract Map conditions Cleared 7/22/2019 ANNA VAN
ZA Case Cleared 7/22/2019 ANNA VAN
Work Adjacent to Public Way Cleared 7/26/2019 ROSA SILVA
Methane Ordinance Cleared 7/29/2019 WILLIAM JOHNS
Hydrant and Access approval Cleared 8/1/2019 GILBERT URREA
Miscellaneous Cleared 8/1/2019 ANNA VAN
Excavation more than 5-ft deep Cleared 8/2/2019 CALOSHA APPROVED
Sewer availability Cleared 8/7/2019 ADRIAN SANCHEZ
DAS Clearance Cleared 8/12/2019 LARRY LEE
"D" conditions Cleared 8/19/2019 ANNA VAN
Green Code Cleared 8/19/2019 DONALD CRICHLOW
Opn space landscape/Water mgmt Cleared 8/19/2019 ANNA VAN
Site Plan review Cleared 8/19/2019 ANNA VAN
ZA Case Cleared 8/19/2019 ANNA VAN
Highway dedication Cleared 8/22/2019 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 9/24/2019 OSCAR SALGADO JR
Permit Cleared 10/2/2019 VICTOR MENDOZA

Contact Information

Architect , ; Lic. No.: C36092       ,
Contractor Shangri - La Construction L P; Lic. No.: 926436-B 550 S HOPE STREET SUITE 510      LOS ANGELES, CA 90071
Engineer Ghodsi, Afshin; Lic. No.: S3248 888 S. FIGUEROA ST.   18TH FLOOR    LOS ANGELES, CA 90017
Engineer Tofani, Glenn David; Lic. No.: GE2496 77 BUNSEN      IRVINE, CA 92618

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/11/2019 Corrections Issued LESLIE TRUJILLO
Grading Pre-Inspection 10/17/2019 Approved JAMES POWERS
Deputy Reinf. Concrete 12/17/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/17/2019 Corrections Issued LESLIE TRUJILLO
METHANE-Barrier 12/17/2019 Not Ready for Inspection LESLIE TRUJILLO
METHANE-Subgrade 12/17/2019 Not Ready for Inspection LESLIE TRUJILLO
Green Building Rough 12/20/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 12/20/2019 Corrections Issued LESLIE TRUJILLO
Reinforced Concrete Frame 12/20/2019 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/27/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 12/27/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/13/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/13/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/13/2020 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 1/13/2020 Corrections Issued LESLIE TRUJILLO
Deputy Reinf. Concrete 1/14/2020 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/14/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/21/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/21/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 1/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/23/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 1/27/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 1/27/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/27/2020 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/28/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/28/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/29/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/4/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/4/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/4/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/4/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/4/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/5/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/5/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/5/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 2/5/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/6/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/6/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/6/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/6/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/7/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/7/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/7/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 2/7/2020 Not Ready for Inspection LESLIE TRUJILLO
Deputy Shotcrete 2/10/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/10/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/10/2020 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/12/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/12/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/12/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/12/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/13/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 2/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/19/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/19/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/19/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 2/19/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/20/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/20/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/20/2020 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/21/2020 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/21/2020 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 2/24/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 2/24/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 2/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/25/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 2/25/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 2/25/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/25/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/25/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 2/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 2/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 2/26/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 2/26/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Shotcrete 2/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 2/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 3/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 3/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/4/2020 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 3/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 3/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/4/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 3/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/5/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 3/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 3/23/2020 Partial Approval LESLIE TRUJILLO
Green Building Rough 3/23/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 3/23/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 3/23/2020 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 3/23/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/23/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 3/23/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 4/3/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 4/3/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/3/2020 Partial Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 4/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/9/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 4/15/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 4/15/2020 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/15/2020 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 4/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/16/2020 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 4/16/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/16/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/16/2020 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 4/16/2020 Approved LESLIE TRUJILLO
Pre-Inspection 4/16/2020 Approved LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/22/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/22/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/22/2020 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 4/23/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 4/23/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 4/23/2020 Approved LESLIE TRUJILLO
Reinforced Concrete Frame 4/23/2020 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 4/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/24/2020 Conditional Approval RONALD PACHECO
Reinforced Concrete Frame 4/24/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 5/12/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/12/2020 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/12/2020 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 5/13/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/14/2020 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 5/18/2020 Conditional Approval NICK DANERI
Green Building Rough 5/20/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/20/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/20/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 5/21/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 5/21/2020 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Not Ready for Inspection NICK DANERI
Green Building Rough 5/27/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/27/2020 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection NICK DANERI
Green Building Rough 6/4/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/4/2020 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/4/2020 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 6/5/2020 Not Ready for Inspection NICK DANERI
Green Building Rough 6/9/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/9/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/9/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/10/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/15/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/17/2020 Conditional Approval NICK DANERI
Green Building Rough 6/17/2020 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/17/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/18/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/19/2020 Conditional Approval NICK DANERI
Green Building Rough 6/24/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 6/24/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/24/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/25/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 6/26/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/10/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/10/2020 Partial Approval NICK DANERI
Green Building Rough 7/13/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/13/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/13/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/14/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/17/2020 Conditional Approval NICK DANERI
Green Building Rough 7/17/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/17/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/17/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/20/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 7/20/2020 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 7/21/2020 Conditional Approval NICK DANERI
Green Building Rough 7/22/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/22/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/22/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/24/2020 Conditional Approval NICK DANERI
Green Building Rough 7/24/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/24/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/24/2020 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 7/27/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 7/27/2020 Partial Approval NICK DANERI
Deputy Shotcrete 7/28/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 7/29/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/5/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/5/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 8/5/2020 Partial Approval NICK DANERI
Deputy Reinf. Masonry 8/6/2020 Conditional Approval NICK DANERI
Green Building Rough 8/6/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/6/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/6/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/10/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 8/10/2020 Partial Approval NICK DANERI
Deputy Reinf. Masonry 8/11/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/14/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/17/2020 Conditional Approval NICK DANERI
Green Building Rough 8/18/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/18/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/18/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/21/2020 Conditional Approval NICK DANERI
Green Building Rough 8/25/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/25/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/25/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/27/2020 Conditional Approval NICK DANERI
Green Building Rough 8/27/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/27/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/27/2020 Not Ready for Inspection NICK DANERI
Green Building Rough 8/31/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/31/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/31/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 9/1/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/2/2020 Partial Approval NICK DANERI
Special/Order Compliance 9/2/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/3/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/14/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 9/14/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/16/2020 Conditional Approval NICK DANERI
Green Building Rough 9/22/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/22/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/22/2020 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 9/23/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 9/23/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/24/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 9/24/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 9/25/2020 Conditional Approval NICK DANERI
Green Building Rough 9/25/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/25/2020 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 9/25/2020 Not Ready for Inspection NICK DANERI
Green Building Rough 9/28/2020 Approved DANIEL COLLINS
Reinforced Concrete Frame 9/28/2020 Partial Approval DANIEL COLLINS
Verify Sprinkler Sign Off 9/28/2020 Not Ready for Inspection DANIEL COLLINS
Deputy Shotcrete 9/29/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 9/30/2020 Conditional Approval NICK DANERI
Masonry Wall/Backfill 9/30/2020 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 10/2/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/2/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/2/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/8/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/8/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/9/2020 Conditional Approval NICK DANERI
Reinforced Masonry Frame 10/22/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 10/22/2020 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 10/23/2020 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 11/4/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/5/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 11/13/2020 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/13/2020 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/16/2020 Partial Approval NICK DANERI
Wood Frame 11/19/2020 Partial Approval NICK DANERI
Deputy Wood Construction 11/24/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/30/2020 Not Ready for Inspection NICK DANERI
Wood Frame 12/4/2020 Partial Approval NICK DANERI
Deputy Wood Construction 12/17/2020 Conditional Approval NICK DANERI
Wood Frame 12/17/2020 Partial Approval NICK DANERI
Deputy Wood Construction 12/22/2020 Conditional Approval NICK DANERI
Deputy Wood Construction 12/30/2020 Conditional Approval NICK DANERI
Wood Frame 12/31/2020 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 1/6/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 1/11/2021 Conditional Approval NICK DANERI
Wood Frame 1/14/2021 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 1/15/2021 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 1/19/2021 Conditional Approval NICK DANERI
Insulation 1/19/2021 Partial Approval NICK DANERI
Deputy Fireproofing 1/20/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 1/20/2021 Conditional Approval NICK DANERI
Deputy Fireproofing 1/21/2021 Conditional Approval NICK DANERI
Deputy Fireproofing 1/22/2021 Conditional Approval NICK DANERI
Deputy Fireproofing 1/25/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 1/25/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/26/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 2/1/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 2/4/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 2/8/2021 Conditional Approval NICK DANERI
Insulation 2/16/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 2/19/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 2/19/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/22/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 2/23/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/26/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/2/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 3/3/2021 Conditional Approval NICK DANERI
Drywall Nailing 3/4/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 3/5/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/10/2021 Conditional Approval NICK DANERI
Insulation 3/11/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 3/12/2021 Conditional Approval NICK DANERI
Drywall Nailing 3/17/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 3/19/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 3/19/2021 Conditional Approval NICK DANERI
Insulation 3/19/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 3/22/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 3/22/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/23/2021 Conditional Approval NICK DANERI
Drywall Nailing 3/24/2021 Partial Approval NICK DANERI
Deputy Wood Construction 3/25/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/26/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/26/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/30/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/30/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 4/1/2021 Conditional Approval NICK DANERI
Insulation 4/1/2021 Partial Approval NICK DANERI
Insulation 4/5/2021 Partial Approval NICK DANERI
Deputy Wood Construction 4/6/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/7/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/9/2021 Conditional Approval NICK DANERI
Drywall Nailing 4/19/2021 Partial Approval NICK DANERI
Insulation 4/19/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 4/22/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 4/22/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/23/2021 Conditional Approval NICK DANERI
Insulation 4/23/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 4/26/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/27/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 4/27/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 4/29/2021 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 4/30/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 4/30/2021 Conditional Approval NICK DANERI
Drywall Nailing 5/4/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 5/10/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/12/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/13/2021 Conditional Approval NICK DANERI
Insulation 5/14/2021 Partial Inspection DAVID BURKHEAD
Deputy Steel/Welding 5/17/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 5/17/2021 Conditional Approval NICK DANERI
Insulation 5/18/2021 Corrections Issued NICK DANERI
Deputy Steel/Welding 5/20/2021 Conditional Approval NICK DANERI
Insulation 5/20/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 5/21/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/24/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 5/24/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/25/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/26/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/27/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 5/27/2021 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/28/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/1/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/2/2021 Conditional Approval NICK DANERI
Drywall Nailing 6/2/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 6/3/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 6/3/2021 Conditional Approval NICK DANERI
Insulation 6/3/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 6/4/2021 Conditional Approval NICK DANERI
Insulation 6/9/2021 Partial Approval NICK DANERI
Deputy Fireproofing 6/15/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 6/15/2021 Partial Approval DANIEL COLLINS
Deputy Wood Construction 6/16/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/21/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 6/23/2021 Not Ready for Inspection KATY RAMIREZ
Deputy Steel/Welding 6/28/2021 Conditional Approval KATY RAMIREZ
Insulation 6/28/2021 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 6/29/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 6/29/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 7/1/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 7/8/2021 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Not Ready for Inspection KATY RAMIREZ
Deputy Wood Construction 7/16/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 7/16/2021 No Access for Inspection KATY RAMIREZ
Deputy Wood Construction 7/20/2021 Partial Approval JAMES POWERS
Pre-Inspection 7/21/2021 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 7/23/2021 Partial Approval JONATHAN QUACH
Verify Sprinkler Sign Off 7/23/2021 Not Ready for Inspection JONATHAN QUACH
Insulation 7/27/2021 Partial Approval JONATHAN QUACH
Deputy Wood Construction 7/30/2021 Conditional Approval KATY RAMIREZ
Drywall Nailing 7/30/2021 Partial Approval KATY RAMIREZ
Insulation 8/6/2021 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 8/10/2021 Conditional Approval KATY RAMIREZ
Deputy Wood Construction 8/23/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 8/24/2021 Partial Approval KATY RAMIREZ
Insulation 8/31/2021 Partial Approval KATY RAMIREZ
Deputy Wood Construction 9/1/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 9/1/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 9/9/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/14/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/14/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Partial Inspection KATY RAMIREZ
Insulation 9/15/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 9/16/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 9/22/2021 Partial Approval KATY RAMIREZ
Insulation 9/22/2021 Partial Inspection KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/27/2021 Conditional Approval KATY RAMIREZ
Drywall Nailing 9/29/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 10/4/2021 Corrections Issued RUSSELL BONVOULOIR
Wood Frame 10/7/2021 Partial Approval DANIEL COLLINS
Wood Frame 10/8/2021 Conditional Approval DARRYL ARNOLD
Insulation 10/13/2021 Off-Hour Fees Due
Insulation 10/13/2021 Partial Approval RAFAEL ESPINOZA
Insulation 10/14/2021 Partial Approval KATY RAMIREZ
Wood Frame 10/18/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/20/2021 Conditional Approval KATY RAMIREZ
Drywall Nailing 10/27/2021 Partial Inspection KATY RAMIREZ
Wood Frame 10/29/2021 Partial Inspection KATY RAMIREZ
Drywall Nailing 11/4/2021 Partial Approval KATY RAMIREZ
Wood Frame 11/5/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 11/9/2021 Partial Approval KATY RAMIREZ
Insulation 11/9/2021 Partial Approval KATY RAMIREZ
Wood Frame 11/9/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 11/15/2021 Partial Approval KATY RAMIREZ
Insulation 11/15/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 11/15/2021 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 11/16/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 11/18/2021 Not Ready for Inspection KATY RAMIREZ
Insulation 11/18/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 11/22/2021 Not Ready for Inspection KATY RAMIREZ
Insulation 11/22/2021 Not Ready for Inspection KATY RAMIREZ
Wood Frame 11/24/2021 No Access for Inspection KATY RAMIREZ
Wood Frame 11/29/2021 Partial Approval JONATHAN QUACH
Insulation 12/2/2021 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 12/2/2021 Partial Approval KATY RAMIREZ
Wood Frame 12/2/2021 Partial Approval KATY RAMIREZ
Insulation 12/6/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 12/10/2021 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 12/10/2021 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 12/13/2021 No Access for Inspection KATY RAMIREZ
Interior/Exterior Lathing 12/14/2021 Partial Approval NICK DANERI
Wood Frame 12/14/2021 Corrections Issued NICK DANERI
Insulation 12/17/2021 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/22/2021 Conditional Approval NICK DANERI
Interior/Exterior Lathing 12/22/2021 Partial Approval NICK DANERI
Wood Frame 12/22/2021 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 12/23/2021 Not Ready for Inspection NICK DANERI
Wood Frame 12/23/2021 Partial Approval NICK DANERI
Insulation 12/28/2021 Partial Approval NICK DANERI
Insulation 1/7/2022 Partial Approval NICK DANERI
Wood Frame 1/7/2022 Partial Approval NICK DANERI
Drywall Nailing 1/11/2022 Partial Approval DAVID BURKHEAD
Insulation 1/11/2022 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/13/2022 Partial Approval JAMES POWERS
Insulation 1/14/2022 Partial Inspection RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 1/20/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/21/2022 Partial Approval TED RIES
Deputy Drilled-In Anchors 1/24/2022 Conditional Approval NICK DANERI
Drywall Nailing 2/2/2022 Partial Approval JAMES POWERS
Insulation 2/2/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/11/2022 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 2/24/2022 Conditional Approval NICK DANERI
Structural Steel Frame 3/11/2022 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 3/15/2022 Conditional Approval NICK DANERI
Insulation 3/31/2022 Partial Inspection NICK DANERI
Structural Steel Frame 3/31/2022 Partial Approval NICK DANERI
Insulation 4/11/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/13/2022 Conditional Approval NICK DANERI
Drywall Nailing 4/18/2022 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 4/22/2022 Conditional Approval NICK DANERI
Drywall Nailing 4/29/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/4/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/24/2022 Partial Approval NICK DANERI
Pre-Inspection 5/31/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/3/2022 Partial Approval NICK DANERI
Insulation 6/7/2022 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/23/2022 Partial Approval NICK DANERI
Drywall Nailing 7/22/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 8/12/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 8/15/2022 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 9/14/2022 Partial Approval NICK DANERI
Special/Order Compliance 10/28/2022 Not Ready for Inspection GREGORY POMISH
Insulation 10/31/2022 Partial Approval NICK DANERI
Pre-Inspection 11/10/2022 Partial Inspection NICK DANERI
Special/Order Compliance 11/15/2022 Partial Inspection NICK DANERI
Interior/Exterior Lathing 11/17/2022 Partial Approval NICK DANERI
Final 1/12/2023 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 1/12/2023 Approved NICK DANERI
Green Building Final 1/12/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 1/12/2023 Partial Inspection NICK DANERI
Reinforced Masonry Frame 1/12/2023 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Not Ready NICK DANERI
Smoke Detectors 1/12/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 1/12/2023 Not Ready for Inspection NICK DANERI
Final 1/25/2023 Not Ready for Inspection NICK DANERI
Green Building Final 1/25/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 1/25/2023 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 1/25/2023 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Not Ready NICK DANERI
Smoke Detectors 1/25/2023 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 1/25/2023 Partial Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Not Ready NICK DANERI
Final 2/6/2023 Partial Inspection DAVID BURKHEAD
Green Building Final 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 2/9/2023 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Not Ready NICK DANERI
Pre-Inspection 2/16/2023 Partial Approval NICK DANERI
Pre-Inspection 3/8/2023 Partial Approval NICK DANERI
Pre-Inspection 3/10/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/16/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 3/17/2023 Partial Inspection NICK DANERI
Pre-Inspection 3/22/2023 Partial Approval NICK DANERI
Pre-Inspection 4/3/2023 Partial Inspection NICK DANERI
Green Building Final 4/11/2023 Approved NICK DANERI
Pre-Inspection 4/11/2023 Partial Inspection NICK DANERI
Pre-Inspection 4/13/2023 Conditional Approval NICK DANERI
Pre-Inspection 4/25/2023 Partial Inspection NICK DANERI
Special/Order Compliance 9/19/2023 Conditional Approval NICK DANERI
Special/Order Compliance 8/6/2024 Conditional Approval NICK DANERI
Final 9/11/2024 Corrections Issued NICK DANERI
Reinforced Concrete Frame 9/11/2024 Approved NICK DANERI
Reinforced Masonry Frame 9/11/2024 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Approved NICK DANERI
Smoke Detectors 9/11/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 9/11/2024 Approved NICK DANERI
Final 9/13/2024 OK to Issue CofO NICK DANERI