2124 N LAKE SHORE AVE 90039
Certificate Information: 2124 N LAKE SHORE AVE 90039
- Application / Permit
- 16010-10000-04181
- Plan Check / Job No.
- B16LA14312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW RESIDENCE 2 STORY WITH ATTACHED 2 CAR GARAGE. 1 OF 3
- Permit Issued
- Issued on 3/15/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2016 | LUKE GONZALES |
| Corrections Issued | 11/4/2016 | LUKE GONZALES |
| Quality Review Completed | 11/4/2016 | LARRY LEE |
| Building Plans Picked Up | 12/2/2016 | APPLICANT |
| Green Plans Picked Up | 12/2/2016 | APPLICANT |
| Applicant returned to address corrections | 5/3/2017 | LUKE GONZALES |
| Applicant returned to address corrections | 6/8/2017 | LUKE GONZALES |
| Applicant returned to address corrections | 11/27/2017 | LUKE GONZALES |
| Plan Check Approved | 1/4/2018 | LUKE GONZALES |
| Issued | 3/15/2018 | LADBS |
| CofO in Progress | 8/22/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/18/2017 | JOHN CONNEALLY |
| Address approval | Cleared | 5/2/2017 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2017 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2017 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/2/2017 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2017 | CELINA MORENO |
| Green Code | Cleared | 5/2/2017 | NEGAR NEJAD |
| Low Impact Development | Cleared | 5/2/2017 | MARTIN FRAGOSO |
| Permit | Cleared | 5/2/2017 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/2/2017 | CELINA MORENO |
| Sewer availability | Cleared | 5/23/2017 | CARLA VALLADARES |
| Excavation more than 5-ft deep | Cleared | 6/8/2017 | CALOSHA APPROVED |
Contact Information
| Engineer | Hamilton, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Geologist | Van, Meter James L.; Lic. No.: EG2031 | 7702 CAPISTRANO AVE WEST HILLS, CA 91304 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/23/2019 | Conditional Approval | DAVID CHAN |
| Underground Mechanical | 5/30/2019 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 6/6/2019 | Approved | DAVID CHAN |
| PLUMBING-Rough | 6/6/2019 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2019 | Corrections Issued | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2020 | Corrections Issued | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2020 | Partial Approval | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2020 | Approved | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Approved | AJA COLLAY |
| ELECTRICAL-Rough | 3/17/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 3/17/2020 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/23/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/23/2020 | Approved | SCOTT FINNILA |
| Green Building Rough | 3/23/2020 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 3/23/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 3/23/2020 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/23/2020 | Approved | SCOTT FINNILA |
| Green Building Rough | 4/6/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 4/10/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 4/20/2020 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 4/29/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/1/2020 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/1/2020 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/1/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/1/2020 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/2/2020 | Approved | THOMAS LOGRASSO |
| Shower Pan | 6/2/2020 | Corrections Issued | THOMAS LOGRASSO |
| Shower Pan | 6/9/2020 | Approved | THOMAS LOGRASSO |
| Gas Test | 5/5/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 8/4/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 6/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Special/Order Compliance | 5/22/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/9/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/9/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 8/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/9/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 8/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 8/11/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 8/11/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/21/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |