6606 N VARIEL AVE 91303

Certificate Information: 6606 N VARIEL AVE 91303

Application / Permit
16010-10000-04179
Plan Check / Job No.
B16LA14300
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 7 STORY, 277 UNIT APARTMENT BUILDING OVER 1 LEVEL OF BASEMENT PARKING. FOUR OF THE 277 UNITS ARE PROPOSED BE WORK-LIVE AS DE3SCRIBED IN THE WARNER CENTER SPECIFIC PLAN. STEEL STAIRS AND RAILS ARE DEFERRED
Permit Issued
Issued on 9/13/2017
Issuing Office
Metro
Current Status
CofO Issued on 9/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2016 APPLICANT
Assigned to Plan Check Engineer 10/27/2016 JOE VO
Corrections Issued 11/7/2016 RICARDO TRES
Quality Review Completed 11/8/2016 CHAD DOI
Building Plans Picked Up 11/30/2016 APPLICANT
Applicant returned to address corrections 5/23/2017 JOHN VASQUEZ
Applicant returned to address corrections 6/5/2017 JOHN VASQUEZ
Applicant returned to address corrections 6/12/2017 JOHN VASQUEZ
Applicant returned to address corrections 6/21/2017 JOHN VASQUEZ
Applicant returned to address corrections 6/26/2017 JOHN VASQUEZ
Applicant returned to address corrections 6/29/2017 JOHN VASQUEZ
Plan Check Approved 8/3/2017 JOHN VASQUEZ
Issued 9/13/2017 LADBS
TCO Issued (Expire Date: 02-23-2021) 8/27/2020 JEFFREY DURAN
TCO Issued (Expire Date: 08-29-2021) 3/2/2021 JEFFREY DURAN
TCO Issued (Expire Date: 02-27-2022) 8/31/2021 JEFFREY DURAN
CofO in Progress 9/22/2021 RICKEY JACKSON
Permit Finaled 9/22/2021 RICKEY JACKSON
CofO Issued 9/22/2021 RICKEY JACKSON
Permit Finaled 9/22/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 2/3/2017 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 2/3/2017 KENNETH PHAM
Hydrant and Access approval Cleared 2/3/2017 JOHN DALLAS
Permit Cleared 2/3/2017 KENNETH PHAM
Green Code Cleared 3/24/2017 SEAN DANG
Construction near power lines Cleared 6/6/2017 ERNEST FRESQUEZ
Bicycle Parking Cleared 6/27/2017 JAMES KHO
DAS Clearance Cleared 7/25/2017 RICARDO TRES
Driveway location Cleared 7/28/2017 VICENTE CORDERO
Internal circulation Cleared 7/28/2017 VICENTE CORDERO
Specific Plan Cleared 7/28/2017 RICARDO TRES
Building over 3-story or 36-ft Cleared 7/31/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/31/2017 CALOSHA APPROVED
Low Impact Development Cleared 7/31/2017 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 7/31/2017 RAVIL MANAPOV
Fire Marshall Fire Life Safety Cleared 8/2/2017 OSCAR SALGADO JR
Highway dedication Cleared 8/2/2017 EDUARDO PEDROZA
Sewer availability Cleared 8/2/2017 ROCHELLE DUNGCA
Work Adjacent to Public Way Cleared 8/2/2017 KENNETH PHAM
Frnt yard landscape/Water mgmt Cleared 8/3/2017 NORALI MARTINEZ
Opn space landscape/Water mgmt Cleared 8/3/2017 NORALI MARTINEZ
Site Plan review Cleared 8/3/2017 NORALI MARTINEZ
Specific Plan Cleared 8/3/2017 NORALI MARTINEZ
ZI Cleared 8/3/2017 NORALI MARTINEZ

Contact Information

Architect Silberstein, Neil Jacob; Lic. No.: C30410 17145 BALTAR STREET      VAN NUYS, CA 91406
Engineer Youssef, Nabih Fouad Guirg; Lic. No.: S2026 550 S HOPE ST SUITE 1700      LOS ANGELES, CA 90017

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/20/2017 Not Ready for Inspection JEFFREY DURAN
Piling/Pier/Caisson 10/16/2017 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 1/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/4/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/8/2018 No Access for Inspection JEFFREY DURAN
Deputy Steel/Welding 1/8/2018 No Access for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 1/9/2018 No Access for Inspection JEFFREY DURAN
Deputy Steel/Welding 1/9/2018 No Access for Inspection JEFFREY DURAN
SWPPP-Const. Storm Water 1/9/2018 Completed JEFFREY DURAN
Deputy Reinf. Concrete 1/10/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/11/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/16/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 1/16/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/17/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/17/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/18/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/19/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/22/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/24/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/25/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 1/25/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/29/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/30/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/31/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/1/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 2/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/5/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 2/5/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 2/6/2018 Approved JEFFREY DURAN
Deputy Shotcrete 2/6/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 2/7/2018 Approved JEFFREY DURAN
Deputy Shotcrete 2/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/9/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 2/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 2/14/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 2/15/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/16/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/20/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/21/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 2/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/23/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 2/26/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 2/27/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 2/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/28/2018 Approved JEFFREY DURAN
Deputy Shotcrete 2/28/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 2/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/1/2018 Approved JEFFREY DURAN
Deputy Shotcrete 3/1/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/2/2018 No Access for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/13/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/14/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 3/15/2018 Approved JEFFREY DURAN
Deputy Shotcrete 3/15/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/16/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/19/2018 Approved JEFFREY DURAN
Deputy Shotcrete 3/20/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/21/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 3/21/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/22/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 3/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/23/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 3/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/27/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 3/27/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 3/28/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/28/2018 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 3/28/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 3/29/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/29/2018 Conditional Approval ROBERT COLE
Piling/Pier/Caisson 3/29/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 3/30/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/30/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 4/2/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/3/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/3/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 4/3/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/4/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/4/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/5/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/6/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/6/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 4/6/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 4/10/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 4/12/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 4/19/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/20/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 4/20/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/23/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/24/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/24/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 4/24/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/25/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/26/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/26/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 4/26/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/27/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/27/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 4/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/30/2018 Approved JEFFREY DURAN
Reinforced Concrete Frame 4/30/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 4/30/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 5/1/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/2/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/3/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/4/2018 Approved JEFFREY DURAN
Deputy Shotcrete 5/4/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 5/4/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/7/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/7/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/8/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/9/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/10/2018 Approved JEFFREY DURAN
Deputy Shotcrete 5/10/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 5/10/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/11/2018 Approved DANNY RODRIGUEZ
Deputy Shotcrete 5/11/2018 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 5/11/2018 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/16/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/18/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 5/18/2018 Conditional Approval JAMES STEPHENS
Footing/Foundation/Slab 5/18/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/21/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/21/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/22/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/22/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/23/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 5/23/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 5/23/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 5/24/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 5/24/2018 Conditional Approval CAMERON CHABAN
Piling/Pier/Caisson 5/24/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 5/25/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 5/25/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 5/25/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 5/30/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/30/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/31/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/31/2018 Conditional Approval JAMES STEPHENS
Footing/Foundation/Slab 5/31/2018 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/4/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/4/2018 Approved JEFFREY DURAN
Special/Order Compliance 6/4/2018 Approved JEFFREY DURAN
Wood Frame 6/4/2018 Corrections Issued JEFFREY DURAN
Deputy Reinf. Concrete 6/5/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 6/5/2018 Conditional Approval CAMERON CHABAN
Piling/Pier/Caisson 6/5/2018 Approved CAMERON CHABAN
Deputy Reinf. Concrete 6/6/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/7/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/7/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/8/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/11/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/11/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 6/11/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/12/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 6/12/2018 Conditional Approval CAMERON CHABAN
Piling/Pier/Caisson 6/12/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/13/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/14/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/14/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/15/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/15/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/18/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/18/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 6/18/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/19/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/19/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/20/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 6/20/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/21/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/21/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 6/21/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/22/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/25/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/26/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/27/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/27/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 6/27/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/28/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/29/2018 Approved JEFFREY DURAN
Deputy Shotcrete 6/29/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 6/29/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/2/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 7/2/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 7/3/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/5/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/9/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/9/2018 Conditional Approval JEFFREY DURAN
Piling/Pier/Caisson 7/10/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/18/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/19/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 7/19/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 7/20/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 7/20/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/24/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/25/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 7/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/27/2018 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 7/27/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 7/30/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 7/30/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 7/31/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 7/31/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/1/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/1/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/2/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/3/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 8/3/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 8/3/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/7/2018 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/7/2018 Conditional Approval CAMERON CHABAN
Piling/Pier/Caisson 8/7/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/8/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/9/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/10/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 8/10/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/13/2018 Approved JEFFREY DURAN
Deputy Shotcrete 8/13/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 8/13/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/14/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/14/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/15/2018 Approved JEFFREY DURAN
Deputy Shotcrete 8/15/2018 Approved JEFFREY DURAN
Piling/Pier/Caisson 8/15/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/16/2018 Approved JEFFREY DURAN
Deputy Shotcrete 8/16/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 8/16/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/17/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/21/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/23/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 8/23/2018 Conditional Approval JAMES STEPHENS
Floor/Roof Diaphrgm/Shear Wall 8/23/2018 Corrections Issued CAMERON CHABAN
Deputy Reinf. Concrete 8/24/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/29/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/30/2018 Approved JEFFREY DURAN
Deputy Wood Construction 8/30/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 8/30/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/31/2018 Conditional Approval JEFFREY DURAN
Piling/Pier/Caisson 9/4/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 9/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/6/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/7/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/10/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/10/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/11/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/11/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/12/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/13/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/18/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 9/18/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 9/18/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/18/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2018 Partial Inspection JEFFREY DURAN
Deputy Drilled-In Anchors 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/20/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/20/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/20/2018 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 9/20/2018 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 9/20/2018 Conditional Approval JEFFREY DURAN
Verify Sprinkler Sign Off 9/20/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Drilled-In Anchors 9/24/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 9/24/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 9/24/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/24/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/25/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/26/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/26/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/26/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/27/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/27/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/28/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 9/28/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/28/2018 Approved JEFFREY DURAN
Wood Frame 9/28/2018 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 10/1/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/1/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/2/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 10/3/2018 Conditional Approval ROBERT COLE
Wood Frame 10/3/2018 Partial Inspection ROBERT COLE
Deputy Wood Construction 10/4/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/9/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/10/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/10/2018 Approved JEFFREY DURAN
Wood Frame 10/10/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/11/2018 Approved JEFFREY DURAN
Deputy Wood Construction 10/11/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2018 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 10/11/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 10/11/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 10/12/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/12/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/16/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/17/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 10/18/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/19/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/19/2018 Approved JEFFREY DURAN
Wood Frame 10/19/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/22/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/23/2018 Approved JEFFREY DURAN
Deputy Wood Construction 10/23/2018 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 10/23/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/24/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/24/2018 Conditional Approval JEFFREY DURAN
Special/Order Compliance 10/24/2018 Corrections Issued JEFFREY DURAN
Deputy Reinf. Masonry 10/25/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/26/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/26/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/29/2018 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 10/29/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 10/29/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 10/30/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/30/2018 Partial Approval ROBERT COLE
Masonry Wall/Backfill 10/30/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/1/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 11/5/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/6/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/8/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/8/2018 Approved JEFFREY DURAN
Drywall Nailing 11/8/2018 Conditional Approval JEFFREY DURAN
Structural Steel Frame 11/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/9/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/9/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/13/2018 Approved JEFFREY DURAN
Drywall Nailing 11/13/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 11/14/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/15/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/16/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/20/2018 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2018 Not Ready for Inspection CAMERON CHABAN
Deputy Wood Construction 11/21/2018 Conditional Approval ROBERT COLE
Deputy Wood Construction 11/27/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 11/28/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/29/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/30/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/3/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/4/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/6/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/10/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/11/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/12/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/13/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 12/14/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 12/17/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/18/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/19/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/20/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/24/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/24/2018 Partial Inspection JEFFREY DURAN
Footing/Foundation/Slab 12/24/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/26/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/27/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/28/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/31/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/2/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/2/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/3/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/7/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/8/2019 Approved JEFFREY DURAN
Deputy Wood Construction 1/9/2019 Approved JEFFREY DURAN
Wood Frame 1/9/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/10/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/11/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/23/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/24/2019 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 1/24/2019 Partial Approval ROBERT COLE
Deputy Wood Construction 1/28/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 1/28/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/29/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/30/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 1/31/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 1/31/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/1/2019 Approved JEFFREY DURAN
Wall Anchors 2/1/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/5/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/6/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/7/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/7/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 2/8/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/8/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/11/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/12/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/12/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/13/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/14/2019 Approved JEFFREY DURAN
Deputy Wood Construction 2/15/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/19/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/20/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/20/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/21/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/21/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/25/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/25/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/26/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/26/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 2/27/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 2/28/2019 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 3/4/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/5/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/6/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/7/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/8/2019 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 3/11/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/12/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/13/2019 Approved JEFFREY DURAN
Wood Frame 3/13/2019 Partial Inspection JEFFREY DURAN
Deputy Steel/Welding 3/14/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/14/2019 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/15/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 3/18/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2019 Partial Approval JEFFREY DURAN
Wood Frame 3/18/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 3/19/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/19/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 3/20/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/20/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 3/21/2019 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2019 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 3/22/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 3/27/2019 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2019 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 3/28/2019 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 3/29/2019 Conditional Approval ROBERT COLE
Wood Frame 3/29/2019 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/1/2019 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 4/2/2019 Approved JEFFREY DURAN
Deputy Wood Construction 4/2/2019 Conditional Approval JAMES STEPHENS
Floor/Roof Diaphrgm/Shear Wall 4/2/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 4/3/2019 Approved JEFFREY DURAN
Wood Frame 4/3/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 4/4/2019 Approved JEFFREY DURAN
Wood Frame 4/4/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 4/5/2019 Conditional Approval DANIEL VARNUM
Wood Frame 4/5/2019 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 4/8/2019 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2019 Conditional Approval CAMERON CHABAN
Wood Frame 4/8/2019 Not Ready for Inspection CAMERON CHABAN
Deputy Wood Construction 4/9/2019 Approved JEFFREY DURAN
Wood Frame 4/9/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 4/10/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2019 Partial Approval JEFFREY DURAN
Special/Order Compliance 4/11/2019 Corrections Issued JEFFREY DURAN
Wood Frame 4/11/2019 Partial Approval JEFFREY DURAN
Wall Anchors 4/12/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/15/2019 Conditional Approval CAMERON CHABAN
Wood Frame 4/15/2019 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/16/2019 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 4/16/2019 Conditional Approval CAMERON CHABAN
Wood Frame 4/16/2019 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 4/17/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/17/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/18/2019 Approved JEFFREY DURAN
Wood Frame 4/18/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 4/19/2019 Approved JEFFREY DURAN
Wood Frame 4/19/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/22/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/22/2019 Approved JEFFREY DURAN
Wood Frame 4/22/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/23/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/23/2019 Approved JEFFREY DURAN
Insulation 4/23/2019 Partial Approval JEFFREY DURAN
Wood Frame 4/23/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/24/2019 Approved JEFFREY DURAN
Deputy Wood Construction 4/24/2019 Conditional Approval JEFFREY DURAN
Wood Frame 4/24/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/25/2019 Approved JEFFREY DURAN
Deputy Steel/Welding 4/25/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/25/2019 Approved JEFFREY DURAN
Masonry Wall/Backfill 4/25/2019 Partial Approval JEFFREY DURAN
Wood Frame 4/25/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/26/2019 Approved JEFFREY DURAN
Deputy Wood Construction 4/26/2019 Approved JEFFREY DURAN
Wood Frame 4/26/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 4/29/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/29/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 4/29/2019 Not Ready for Inspection JEFFREY DURAN
Structural Steel Frame 4/29/2019 Corrections Issued JEFFREY DURAN
Wood Frame 4/29/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 4/30/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/30/2019 Approved JEFFREY DURAN
Insulation 4/30/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/1/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 5/1/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/1/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/2/2019 Approved JEFFREY DURAN
Wood Frame 5/2/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/3/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2019 Partial Approval JEFFREY DURAN
Insulation 5/3/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/6/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2019 Partial Approval JEFFREY DURAN
Insulation 5/6/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/6/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/7/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 5/7/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/7/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/8/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/8/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/9/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/9/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2019 Partial Approval JEFFREY DURAN
Insulation 5/10/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/10/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2019 Partial Approval JEFFREY DURAN
Insulation 5/13/2019 Partial Approval JEFFREY DURAN
Insulation 5/14/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/14/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/15/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/15/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/16/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2019 Partial Approval JEFFREY DURAN
Insulation 5/16/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/16/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/17/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 5/20/2019 Approved JEFFREY DURAN
Wood Frame 5/20/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/21/2019 Approved JEFFREY DURAN
Insulation 5/21/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/21/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Drilled-In Anchors 5/22/2019 Approved JEFFREY DURAN
Insulation 5/22/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/22/2019 Partial Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/23/2019 Conditional Approval JEFFREY DURAN
Insulation 5/23/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/23/2019 Partial Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/24/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/24/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/28/2019 Approved JEFFREY DURAN
Insulation 5/28/2019 Partial Approval JEFFREY DURAN
Wood Frame 5/28/2019 Partial Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/29/2019 Approved JEFFREY DURAN
Deputy Wood Construction 5/29/2019 Approved JEFFREY DURAN
T-Bar Ceiling 5/29/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/30/2019 Approved JEFFREY DURAN
Drywall Nailing 5/30/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/31/2019 Approved JEFFREY DURAN
Wood Frame 5/31/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 6/3/2019 Approved JEFFREY DURAN
Drywall Nailing 6/3/2019 Partial Approval JEFFREY DURAN
Insulation 6/3/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/3/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 6/4/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 6/4/2019 Approved JEFFREY DURAN
Drywall Nailing 6/4/2019 Partial Approval JEFFREY DURAN
Insulation 6/4/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 6/5/2019 Partial Approval JEFFREY DURAN
Insulation 6/5/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/5/2019 Partial Approval JEFFREY DURAN
Insulation 6/6/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/6/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 6/7/2019 Conditional Approval ROBERT COLE
Deputy Wood Construction 6/7/2019 Conditional Approval ROBERT COLE
Insulation 6/7/2019 Partial Approval DANIEL VARNUM
Deputy Wood Construction 6/10/2019 Approved JEFFREY DURAN
Insulation 6/10/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/10/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 6/11/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 6/12/2019 Conditional Approval DANIEL VARNUM
Insulation 6/12/2019 Partial Approval DANIEL VARNUM
Wood Frame 6/12/2019 Partial Approval DANIEL VARNUM
Deputy Wood Construction 6/13/2019 Approved JEFFREY DURAN
Insulation 6/13/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/13/2019 Partial Approval JEFFREY DURAN
Insulation 6/14/2019 Partial Approval JEFFREY DURAN
Wood Frame 6/14/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 6/17/2019 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 6/17/2019 Partial Approval DANIEL VARNUM
Deputy Wood Construction 6/18/2019 Conditional Approval DANIEL VARNUM
Insulation 6/18/2019 Partial Approval DANIEL VARNUM
Wood Frame 6/18/2019 Partial Approval DANIEL VARNUM
Deputy Wood Construction 6/19/2019 Approved MILLARD ARDOIN
Drywall Nailing 6/19/2019 Partial Approval MILLARD ARDOIN
Deputy Wood Construction 6/21/2019 Conditional Approval DANIEL VARNUM
Insulation 6/21/2019 Order to Comply Issued DANIEL VARNUM
Wood Frame 6/21/2019 Partial Approval DANIEL VARNUM
Drywall Nailing 6/24/2019 Partial Approval ROBERT COLE
Insulation 6/25/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 6/26/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2019 Partial Approval JEFFREY DURAN
Insulation 6/27/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 6/28/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2019 Partial Approval JEFFREY DURAN
Insulation 7/1/2019 Partial Approval JEFFREY DURAN
Insulation 7/2/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/2/2019 Partial Approval JEFFREY DURAN
Insulation 7/5/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/5/2019 Conditional Approval JEFFREY DURAN
Insulation 7/8/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/8/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 7/10/2019 Conditional Approval DANNY RODRIGUEZ
Insulation 7/10/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/10/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 7/11/2019 Conditional Approval JEFFREY DURAN
Insulation 7/11/2019 Partial Approval ROBERT COLE
Deputy Wood Construction 7/12/2019 Conditional Approval JAMES STEPHENS
Insulation 7/12/2019 Partial Inspection DANIEL VARNUM
Deputy Wood Construction 7/15/2019 Approved JEFFREY DURAN
Drywall Nailing 7/15/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/15/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 7/16/2019 Approved JEFFREY DURAN
Drywall Nailing 7/16/2019 Partial Approval JEFFREY DURAN
Special/Order Compliance 7/16/2019 Corrections Issued JEFFREY DURAN
Drywall Nailing 7/17/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/18/2019 Conditional Approval JEFFREY DURAN
Insulation 7/19/2019 Not Ready for Inspection DANIEL VARNUM
Insulation 7/22/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/22/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 7/24/2019 Not Ready for Inspection MILLARD ARDOIN
Drywall Nailing 7/26/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 7/30/2019 Approved JEFFREY DURAN
Drywall Nailing 7/30/2019 Partial Approval JEFFREY DURAN
Wood Frame 7/30/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 7/31/2019 Approved JEFFREY DURAN
Wood Frame 7/31/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 8/1/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/2/2019 Conditional Approval JEFFREY DURAN
Wood Frame 8/2/2019 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 8/5/2019 Conditional Approval JEFFREY DURAN
Insulation 8/6/2019 Conditional Approval JEFFREY DURAN
Insulation 8/8/2019 Partial Approval JEFFREY DURAN
Wood Frame 8/8/2019 Partial Approval JEFFREY DURAN
Wood Frame 8/12/2019 Partial Approval JEFFREY DURAN
Insulation 8/13/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 8/13/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/15/2019 Conditional Approval DANIEL VARNUM
Insulation 8/15/2019 Partial Approval DANIEL VARNUM
Wood Frame 8/15/2019 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 8/16/2019 Approved MILLARD ARDOIN
Drywall Nailing 8/16/2019 Partial Approval DANIEL VARNUM
Interior/Exterior Lathing 8/19/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2019 Partial Approval JEFFREY DURAN
T-Bar Ceiling 8/22/2019 Partial Inspection JEFFREY DURAN
Wood Frame 8/27/2019 Partial Approval JEFFREY DURAN
Wood Frame 8/28/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/29/2019 Partial Approval JEFFREY DURAN
Insulation 8/29/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 8/30/2019 Partial Approval JEFFREY DURAN
T-Bar Ceiling 8/30/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/4/2019 Partial Inspection JEFFREY DURAN
Drywall Nailing 9/5/2019 Partial Approval DANIEL VARNUM
Wood Frame 9/5/2019 Approved DANIEL VARNUM
Interior/Exterior Lathing 9/6/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/9/2019 Partial Approval MILLARD ARDOIN
Wood Frame 9/9/2019 Partial Approval MILLARD ARDOIN
Drywall Nailing 9/10/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 9/10/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 9/10/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/11/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 9/11/2019 Partial Approval JEFFREY DURAN
Wood Frame 9/11/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/16/2019 Partial Approval JEFFREY DURAN
Insulation 9/16/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 9/16/2019 Partial Approval JEFFREY DURAN
Wood Frame 9/16/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/17/2019 Partial Approval JEFFREY DURAN
Green Building Rough 9/17/2019 Corrections Issued JEFFREY DURAN
Insulation 9/17/2019 Partial Approval JEFFREY DURAN
Insulation 9/18/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 9/18/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/19/2019 Partial Approval JEFFREY DURAN
Insulation 9/19/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 9/19/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 9/19/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/21/2019 Off-Hour Fees Due
Insulation 9/21/2019 Off-Hour Fees Due
Wood Frame 9/21/2019 Off-Hour Fees Due
Drywall Nailing 9/23/2019 Partial Approval JEFFREY DURAN
Insulation 9/23/2019 Partial Approval JEFFREY DURAN
Wood Frame 9/23/2019 Conditional Approval JEFFREY DURAN
Wood Frame 9/23/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/24/2019 Partial Approval JEFFREY DURAN
Insulation 9/24/2019 Partial Approval JEFFREY DURAN
Wood Frame 9/24/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/25/2019 Partial Approval JEFFREY DURAN
Insulation 9/25/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 9/25/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 9/25/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/26/2019 Partial Approval JEFFREY DURAN
Insulation 9/26/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 9/26/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 9/26/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/27/2019 Partial Approval JEFFREY DURAN
Insulation 9/27/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 9/27/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/30/2019 Partial Approval JAMES STEPHENS
Insulation 9/30/2019 Partial Approval JAMES STEPHENS
Interior/Exterior Lathing 9/30/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 10/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/1/2019 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 10/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 10/2/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 10/2/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 10/2/2019 Partial Approval JEFFREY DURAN
Wood Frame 10/2/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/3/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 10/3/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 10/3/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/4/2019 Partial Approval JEFFREY DURAN
Insulation 10/4/2019 Partial Approval JEFFREY DURAN
Wood Frame 10/4/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 10/7/2019 Partial Approval JEFFREY DURAN
Insulation 10/7/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 10/7/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 10/9/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/10/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 10/15/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 10/15/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 10/16/2019 Corrections Issued JEFFREY DURAN
Drywall Nailing 10/17/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 10/17/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/18/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 10/18/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 10/22/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/25/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/29/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 10/29/2019 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2019 Partial Approval JEFFREY DURAN
Wood Frame 10/30/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 11/4/2019 Partial Approval JEFFREY DURAN
Wood Frame 11/4/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 11/7/2019 Partial Approval JEFFREY DURAN
Wood Frame 11/7/2019 Partial Inspection JEFFREY DURAN
Insulation 11/14/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 11/14/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 11/14/2019 Conditional Approval JEFFREY DURAN
Wood Frame 11/14/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 11/20/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 11/25/2019 Partial Inspection DANIEL VARNUM
Light Gage Steel Frame 11/26/2019 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 11/27/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 12/4/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 12/4/2019 Partial Approval JEFFREY DURAN
Insulation 12/4/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 12/5/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 12/5/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 12/9/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 12/11/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 12/18/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 12/24/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 12/24/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 1/2/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 1/3/2020 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 1/10/2020 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 1/10/2020 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 1/14/2020 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 1/22/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 1/27/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 1/29/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 1/29/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 1/30/2020 Partial Approval JEFFREY DURAN
Wood Frame 1/30/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 2/3/2020 Partial Approval JEFFREY DURAN
Wood Frame 2/3/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 2/6/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 2/6/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/13/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 2/18/2020 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 2/18/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/18/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 2/20/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 2/24/2020 Not Ready for Inspection JEFFREY DURAN
Masonry Wall/Backfill 2/28/2020 Partial Approval JEFFREY DURAN
Special/Order Compliance 3/5/2020 Not Ready for Inspection JEFFREY DURAN
Deputy Steel/Welding 3/9/2020 Conditional Approval JAMES STEPHENS
Insulation 3/9/2020 Partial Approval JAMES STEPHENS
Drywall Nailing 3/12/2020 Corrections Issued JEFFREY DURAN
Drywall Nailing 3/18/2020 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 3/23/2020 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 3/23/2020 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 3/23/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 3/24/2020 Conditional Approval JEFFREY DURAN
Insulation 3/25/2020 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 3/25/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 3/26/2020 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval JEFFREY DURAN
Insulation 4/1/2020 Partial Inspection JEFFREY DURAN
Special/Order Compliance 4/1/2020 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 4/3/2020 Not Ready for Inspection ROBERT COLE
Interior/Exterior Lathing 4/7/2020 Partial Inspection JEFFREY FULTON
Insulation 4/9/2020 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 4/13/2020 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/15/2020 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 4/17/2020 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/20/2020 Conditional Approval ROBERT COLE
Drywall Nailing 4/22/2020 Partial Approval DANIEL VARNUM
Deputy Wood Construction 4/27/2020 Conditional Approval JEFFREY DURAN
Structural Steel Frame 4/28/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 5/1/2020 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 5/5/2020 Not Ready for Inspection DANIEL VARNUM
Deputy Drilled-In Anchors 5/7/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 5/14/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 5/19/2020 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/21/2020 Partial Inspection JEFFREY DURAN
Final 5/26/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 5/26/2020 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 5/26/2020 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 5/26/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 5/26/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 5/26/2020 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 5/26/2020 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 5/27/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/27/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/28/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/29/2020 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 6/2/2020 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 6/30/2020 Approved HAMID PISHEHVAR
Special/Order Compliance 7/6/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 7/7/2020 Partial Inspection JEFFREY FULTON
Final 7/10/2020 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 7/17/2020 Corrections Issued ROBERT DAVIS
Special/Order Compliance 7/23/2020 Order to Comply Issued ROBERT DAVIS
Special/Order Compliance 7/27/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 7/29/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 7/30/2020 Approved HAMID PISHEHVAR
Special/Order Compliance 8/3/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/6/2020 Partial Inspection ROBERT DAVIS
Special/Order Compliance 8/11/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/14/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/17/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/20/2020 Partial Inspection JEFFREY DURAN
Special/Order Compliance 8/21/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/22/2020 Conditional Approval JEFFREY DURAN
Special/Order Compliance 8/22/2020 Off-Hour Fees Due
Deputy Steel/Welding 8/24/2020 Conditional Approval ROBERT DAVIS
Special/Order Compliance 8/24/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 8/25/2020 Not Ready for Inspection HAMID PISHEHVAR
Final 8/26/2020 Corrections Issued JEFFREY DURAN
Footing/Foundation/Slab 8/26/2020 Approved JEFFREY DURAN
Reinforced Concrete Frame 8/26/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 8/26/2020 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Approved JEFFREY DURAN
Smoke Detectors 8/26/2020 Approved JEFFREY DURAN
Special/Order Compliance 8/26/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 8/26/2020 Partial Approval JEFFREY DURAN
Final 8/27/2020 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 8/27/2020 Approved JEFFREY DURAN
Reinforced Concrete Frame 8/28/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Masonry Frame 8/28/2020 Partial Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 8/28/2020 Conditional Approval JONATHAN QUACH
Special/Order Compliance 1/27/2021 Not Ready for Inspection JEFFREY DURAN
Final 5/26/2021 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 5/26/2021 Approved HAMID PISHEHVAR
Reinforced Masonry Frame 5/26/2021 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 5/26/2021 Approved HAMID PISHEHVAR
Special/Order Compliance 8/4/2021 Not Ready for Inspection JEFFREY DURAN
Final 9/21/2021 Not Ready for Inspection RICKEY JACKSON