8555 W HEDGES PL 90069
Certificate Information: 8555 W HEDGES PL 90069
- Application / Permit
- 16010-10000-04114
- Plan Check / Job No.
- B16LA14038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) Accessory Living Quarters
- Permit Issued
- Issued on 4/14/2017
- Issuing Office
- Metro
- Current Status
- Issued on 4/14/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/13/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2016 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/3/2016 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/6/2016 | LARRY LEE |
| Building Plans Picked Up | 10/6/2016 | APPLICANT |
| Green Plans Picked Up | 10/6/2016 | APPLICANT |
| Plan Check Approved | 4/13/2017 | VLADIMIR ARUTYUNYAN |
| Issued | 4/14/2017 | LADBS |
Permit Application Clearance Information
| ZA Case | Cleared | 12/22/2016 | FIPE LEILUA |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2017 | CARLA VALLADARES |
| Sewer availability | Cleared | 3/3/2017 | SEVAK ISAKHAYAN |
| Hydrant and Access approval | Cleared | 3/22/2017 | ROBERT DUFF |
| Green Code | Cleared | 3/28/2017 | JOHN KLARIN |
| Low Impact Development | Cleared | 4/12/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 4/12/2017 | ROCHELLE DUNGCA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fischer, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/12/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/25/2025 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 5/15/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Steel/Welding | 7/14/2025 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 7/15/2025 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 7/16/2025 | Partial Approval | ROY SPAULDING |
| Deputy Steel/Welding | 7/18/2025 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 10/7/2025 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 10/7/2025 | Not Ready for Inspection | ROY SPAULDING |