4807 W ELMWOOD AVE 1-13 90004
Certificate Information: 4807 W ELMWOOD AVE 1-13 90004
- Application / Permit
- 16010-10000-04103
- Plan Check / Job No.
- B16LA13986
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 4-story, Type IIIA, 13-Unit apartment building over one level, Type IIIA, basement parking garage. The project utilizes 35% density bonus restricting 1 very low come units, 11% of the 9 base units 12.22A.25.
- Permit Issued
- Issued on 3/16/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2016 | APPLICANT |
| Disabled Access Plans Picked Up | 9/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2016 | KESETE HAREGOT |
| Corrections Issued | 10/12/2016 | KESETE HAREGOT |
| Quality Review Completed | 10/24/2016 | MINYE PAK |
| Building Plans Picked Up | 10/26/2016 | APPLICANT |
| Green Plans Picked Up | 10/26/2016 | APPLICANT |
| Applicant returned to address corrections | 12/21/2016 | KESETE HAREGOT |
| Plan Check Approved | 3/15/2018 | KESETE HAREGOT |
| Issued | 3/16/2018 | LADBS |
| TCO Issued (Expire Date: 02-08-2022) | 8/12/2021 | DAVID TSAU |
| CofO in Progress | 9/3/2021 | DANIEL MC AULIFFE |
| Permit Finaled | 9/3/2021 | TERRY HERR |
| CofO Issued | 9/3/2021 | TERRY HERR |
| Permit Finaled | 9/3/2021 | TERRY HERR |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2017 | ROCHELLE DUNGCA |
| Permit | Cleared | 2/3/2017 | ROCHELLE DUNGCA |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2017 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 2/16/2017 | ROBERT DUFF |
| Sewer availability | Cleared | 4/21/2017 | JAMES MORALEZ |
| Frnt yard landscape/Water mgmt | Cleared | 5/5/2017 | EDBER MACEDO |
| Opn space landscape/Water mgmt | Cleared | 5/5/2017 | EDBER MACEDO |
| Green Code | Cleared | 6/27/2017 | NEGAR NEJAD |
| Fire Marshall Fire Life Safety | Cleared | 8/17/2017 | OSCAR SALGADO JR |
| DAS Clearance | Cleared | 8/25/2017 | WAI LAU |
| Housing density bonus | Cleared | 8/29/2017 | RICHARD TRUONG |
| Low Impact Development | Cleared | 12/22/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/22/2017 | ROCHELLE DUNGCA |
| Work Adjacent to Public Way | Cleared | 2/2/2018 | BOK GOH |
| Building over 3-story or 36-ft | Cleared | 3/15/2018 | CALOSHA APPROVED |
Contact Information
| Architect | Robert, Christian J M; Lic. No.: C34175 | 4200 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Contractor | Ceilbright Services Inc; Lic. No.: 957706-B | 250 S BEVERLY DRIVE BEVERLY HILLS, CA 90212 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2018 | Not Ready for Inspection | TED RIES |
| Footing/Foundation/Slab | 7/20/2018 | Partial Approval | TED RIES |
| Excavation/Setback/Form/Re-Bar | 9/20/2018 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 11/6/2018 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 11/20/2018 | Partial Inspection | TED RIES |
| Footing/Foundation/Slab | 11/27/2018 | Partial Approval | TED RIES |
| Masonry Wall/Backfill | 12/11/2018 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 12/20/2018 | Partial Approval | TED RIES |
| Structural Steel Frame | 12/28/2018 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 1/25/2019 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 2/20/2019 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 3/18/2019 | Partial Approval | TED RIES |
| Green Building Rough | 5/1/2019 | Not Ready for Inspection | TED RIES |
| Reinforced Masonry Frame | 5/1/2019 | Partial Approval | TED RIES |
| Verify Sprinkler Sign Off | 5/1/2019 | Not Ready for Inspection | TED RIES |
| Green Building Rough | 5/9/2019 | Partial Approval | TED RIES |
| Reinforced Masonry Frame | 5/9/2019 | Partial Approval | TED RIES |
| Verify Sprinkler Sign Off | 5/9/2019 | Not Ready for Inspection | TED RIES |
| Green Building Rough | 5/24/2019 | Not Ready for Inspection | TED RIES |
| Reinforced Masonry Frame | 5/24/2019 | Partial Approval | TED RIES |
| Verify Sprinkler Sign Off | 5/24/2019 | Not Ready for Inspection | TED RIES |
| Footing/Foundation/Slab | 6/24/2019 | Partial Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 7/16/2019 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2019 | Partial Approval | JEFF BYTHEWAY |
| Wood Frame | 8/27/2019 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 8/28/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2019 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2019 | Partial Approval | DANIEL MC AULIFFE |
| Reinforced Masonry Frame | 10/4/2019 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2019 | Partial Approval | DANIEL MC AULIFFE |
| Masonry Wall/Backfill | 10/28/2019 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 1/3/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 1/28/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 2/3/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 2/10/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 2/12/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 2/18/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Wood Construction | 2/28/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Wood Frame | 3/2/2020 | Corrections Issued | DANIEL MC AULIFFE |
| Wood Frame | 3/4/2020 | Partial Approval | DANIEL MC AULIFFE |
| Excavation/Setback/Form/Re-Bar | 3/12/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 3/12/2020 | Corrections Issued | DANIEL MC AULIFFE |
| Wood Frame | 3/18/2020 | Partial Approval | DANIEL MC AULIFFE |
| Excavation/Setback/Form/Re-Bar | 4/28/2020 | Partial Approval | DANIEL MC AULIFFE |
| Light Gage Steel Frame | 5/4/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Drywall Nailing | 5/6/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 5/13/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 5/20/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Excavation/Setback/Form/Re-Bar | 5/28/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 6/1/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Wood Frame | 6/5/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 6/9/2020 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 6/15/2020 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 6/19/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 6/23/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 6/25/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 7/8/2020 | Partial Approval | DANIEL MC AULIFFE |
| Structural Steel Frame | 7/8/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 7/21/2020 | Partial Approval | DANIEL MC AULIFFE |
| Light Gage Steel Frame | 8/24/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Light Gage Steel Frame | 9/1/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Light Gage Steel Frame | 9/3/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 9/9/2020 | Approved | DANIEL MC AULIFFE |
| Special/Order Compliance | 10/26/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Structural Steel Frame | 11/24/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Structural Steel Frame | 12/7/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Structural Steel Frame | 12/18/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 1/19/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| Green Building Final | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| Green Building Rough | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| Reinforced Masonry Frame | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 1/19/2021 | Approved | DANIEL MC AULIFFE |
| Final | 2/16/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Final | 4/12/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Final | 7/13/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Final | 8/13/2021 | No Access for Inspection | DAVID BURKHEAD |
| Final | 8/25/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Final | 9/2/2021 | Conditional Approval | DANIEL MC AULIFFE |