10819 N GRAY FOX CT 91326
Certificate Information: 10819 N GRAY FOX CT 91326
- Application / Permit
- 16010-10000-04022
- Plan Check / Job No.
- B16LA13754
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD PER STD PLAN #644. lot 20
- Permit Issued
- Issued on 11/21/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2016 | ERIC CABRERA |
| Green Plans Picked Up | 9/22/2016 | APPLICANT |
| Corrections Issued | 9/27/2016 | ERIC CABRERA |
| Quality Review Completed | 10/13/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 10/14/2016 | APPLICANT |
| Plan Check Approved | 11/16/2016 | ERIC CABRERA |
| Issued | 11/21/2016 | LADBS |
| CofO in Progress | 1/20/2022 | SEAN WIRCH |
| Permit Finaled | 1/20/2022 | MICHAEL SMITH |
| CofO Issued | 1/20/2022 | MICHAEL SMITH |
| Permit Finaled | 1/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/20/2016 | ANNA VIDAL |
| "T" removal | Cleared | 10/20/2016 | ANNA VIDAL |
| CPC | Cleared | 10/20/2016 | ANNA VIDAL |
| Tract Map conditions | Cleared | 10/20/2016 | ANNA VIDAL |
| Tract Map conditions | Cleared | 10/20/2016 | ANNA VIDAL |
| ZA Case | Cleared | 10/20/2016 | ANNA VIDAL |
| ZA Case | Cleared | 10/20/2016 | ANNA VIDAL |
| ZA Case | Cleared | 10/20/2016 | ANNA VIDAL |
| ZA Case | Cleared | 10/20/2016 | ANNA VIDAL |
| Address approval | Cleared | 10/25/2016 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 10/25/2016 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 10/25/2016 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Miscellaneous | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Permit | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Sewer availability | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Work Adjacent to Public Way | Cleared | 10/25/2016 | ROBERT SAMONTE |
| Hydrant and Access approval | Cleared | 10/26/2016 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/1/2016 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 11/2/2016 | RICHARD SOUTHERLAND |
| Green Code | Cleared | 11/8/2016 | DONALD CRICHLOW |
| Excavation more than 5-ft deep | Cleared | 11/16/2016 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 11/21/2016 | ERIC CABRERA |
| Grading Pre-Inspection | Cleared | 11/21/2016 | ERIC CABRERA |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Braatz, Tara Elizabeth; Lic. No.: C79028 | 38 RED BUD ALISO VIEJO, CA 92656 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/12/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 4/7/2021 | Approved | SEAN WIRCH |
| Sewer | 5/5/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | SEAN WIRCH |
| Deputy Reinf. Concrete | 8/13/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 8/31/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 9/1/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 9/1/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 9/24/2021 | Not Ready for Inspection | SEAN WIRCH |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 9/24/2021 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 9/24/2021 | Not Ready for Inspection | SEAN WIRCH |
| Underground Mechanical | 10/6/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 10/14/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 10/14/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 10/14/2021 | Partial Approval | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 10/14/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 11/3/2021 | Partial Approval | JOSEPH SAGEN |
| Gas Test | 11/8/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Gas Test | 11/16/2021 | Approved | HENRY KIM |
| Service/Power Release | 12/8/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Approved | HENRY KIM |
| ELECTRICAL-Final | 1/7/2022 | Approved | SEAN WIRCH |
| HVAC-Final | 1/7/2022 | Approved | SEAN WIRCH |
| Final | 1/14/2022 | Partial Approval | SEAN WIRCH |
| Green Building Final | 1/14/2022 | Approved | SEAN WIRCH |
| PLUMBING-Final | 1/14/2022 | Approved | SEAN WIRCH |
| Smoke Detectors | 1/14/2022 | Approved | SEAN WIRCH |
| Final | 1/21/2022 | OK to Issue CofO | SEAN WIRCH |