Deputy Reinf. Concrete
|
2/14/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
4/30/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
4/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Masonry Frame
|
4/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Verify Sprinkler Sign Off
|
4/30/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
5/15/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/18/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
5/19/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/20/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
5/22/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
5/26/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
5/28/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
6/4/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
6/5/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/8/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
6/9/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/10/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
6/11/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/12/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/16/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
6/16/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
6/19/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
6/24/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
6/25/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/25/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
6/26/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
7/2/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
7/8/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/10/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Insulation
|
7/10/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
7/16/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
4/27/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
5/19/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/17/2021
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
9/13/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
9/17/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
10/5/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
10/12/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/14/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
11/1/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
11/3/2021
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
11/3/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
11/4/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
11/8/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
11/10/2021
|
Partial Approval
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
11/12/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
11/18/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
11/22/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
12/3/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
12/3/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
12/8/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
12/8/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
12/10/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
12/15/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
12/21/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
1/4/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
1/5/2022
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
1/12/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
1/12/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
1/18/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
1/25/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
2/3/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
2/23/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
2/28/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Grading Pre-Inspection
|
3/3/2022
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
3/15/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
3/17/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
3/23/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
3/25/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
3/29/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
3/30/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
3/30/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
4/11/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
4/15/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
4/18/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
4/18/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
5/2/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
5/2/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/6/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
5/12/2022
|
Conditional Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
5/13/2022
|
Partial Approval
|
TED RIES
|
|
Reinforced Masonry Frame
|
5/16/2022
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
6/1/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
6/6/2022
|
No Result Entered
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
6/6/2022
|
No Result Entered
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/6/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/7/2022
|
No Result Entered
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/7/2022
|
No Result Entered
|
DANIEL MC AULIFFE
|
|
Light Gage Steel Frame
|
6/15/2022
|
Partial Approval
|
TED RIES
|
|
Light Gage Steel Frame
|
6/29/2022
|
Partial Inspection
|
KATY RAMIREZ
|
|
Drywall Nailing
|
7/6/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
7/6/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/6/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/12/2022
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
7/12/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
7/13/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/14/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
7/26/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
8/3/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
8/3/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Light Gage Steel Frame
|
8/9/2022
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
8/19/2022
|
Partial Approval
|
TED RIES
|
|
Final
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
Footing/Foundation/Slab
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
Green Building Final
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
Reinforced Concrete Frame
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
Reinforced Masonry Frame
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
9/20/2022
|
SGSOV Not Ready
|
TED RIES
|
|
Smoke Detectors
|
9/20/2022
|
No Access for Inspection
|
TED RIES
|
|
Final
|
9/26/2022
|
Corrections Issued
|
TED RIES
|
|
Footing/Foundation/Slab
|
9/26/2022
|
Partial Inspection
|
TED RIES
|
|
Green Building Final
|
9/26/2022
|
Conditional Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
9/26/2022
|
Partial Inspection
|
TED RIES
|
|
Reinforced Masonry Frame
|
9/26/2022
|
Partial Inspection
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
9/26/2022
|
SGSOV Not Ready
|
TED RIES
|
|
Smoke Detectors
|
9/26/2022
|
Conditional Approval
|
TED RIES
|
|
Final
|
9/29/2022
|
Not Ready for Inspection
|
TED RIES
|
|
Footing/Foundation/Slab
|
9/29/2022
|
Partial Approval
|
TED RIES
|
|
Green Building Final
|
9/29/2022
|
Conditional Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
9/29/2022
|
Partial Approval
|
TED RIES
|
|
Reinforced Masonry Frame
|
9/29/2022
|
Partial Approval
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
9/29/2022
|
SGSOV Not Ready
|
TED RIES
|
|
Smoke Detectors
|
9/29/2022
|
Approved
|
TED RIES
|
|
Insulation
|
10/17/2022
|
Partial Approval
|
TED RIES
|
|
Light Gage Steel Frame
|
10/17/2022
|
Partial Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
10/20/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Green Building Final
|
10/20/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
10/20/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
10/20/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
10/20/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
SGSOV-Seismic Gas S/O Valve
|
10/20/2022
|
SGSOV Not Ready
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
10/24/2022
|
Partial Inspection
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
10/31/2022
|
Approved
|
TED RIES
|
|
Final
|
11/1/2022
|
Not Ready for Inspection
|
TED RIES
|
|
Footing/Foundation/Slab
|
11/1/2022
|
Partial Inspection
|
TED RIES
|
|
Green Building Final
|
11/1/2022
|
Conditional Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
11/1/2022
|
Partial Inspection
|
TED RIES
|
|
Reinforced Masonry Frame
|
11/1/2022
|
Partial Inspection
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
11/1/2022
|
SGSOV Not Ready
|
TED RIES
|
|
Final
|
11/9/2022
|
Partial Inspection
|
TED RIES
|
|
Footing/Foundation/Slab
|
11/9/2022
|
Partial Inspection
|
TED RIES
|
|
Green Building Final
|
11/9/2022
|
Partial Inspection
|
TED RIES
|
|
Reinforced Concrete Frame
|
11/9/2022
|
Partial Inspection
|
TED RIES
|
|
Reinforced Masonry Frame
|
11/9/2022
|
Partial Inspection
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
11/9/2022
|
SGSOV Not Ready
|
TED RIES
|
|
Pre-Inspection
|
11/16/2022
|
Partial Approval
|
TED RIES
|
|
Pre-Inspection
|
11/23/2022
|
Partial Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
11/28/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
7/18/2023
|
Approved
|
TED RIES
|
|
Special/Order Compliance
|
1/16/2024
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
2/6/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
2/6/2024
|
Approved
|
DAVID BURKHEAD
|
|
Green Building Final
|
2/6/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
2/6/2024
|
Approved
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
2/6/2024
|
Approved
|
DAVID BURKHEAD
|
|
SGSOV-Seismic Gas S/O Valve
|
2/6/2024
|
SGSOV Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
2/12/2024
|
Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
2/12/2024
|
Partial Inspection
|
JEROME BLACKWOOD
|
|
Special/Order Compliance
|
7/23/2024
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
1/15/2025
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
7/8/2025
|
Approved
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
1/6/2026
|
Approved
|
JOEY BUCHANAN
|