12414 W EXPOSITION BLVD 90064

Certificate Information: 12414 W EXPOSITION BLVD 90064

Application / Permit
16010-10000-03990
Plan Check / Job No.
B16LA13694
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
New 3-story Type IIIB office builidng (Core & Shell only) over a 2-story Type IA parking garage.
Permit Issued
Issued on 6/22/2017
Issuing Office
Metro
Current Status
CofO Issued on 10/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2016 APPLICANT
Assigned to Plan Check Engineer 9/22/2016 EUGENE BARBEAU
Corrections Issued 9/26/2016 EUGENE BARBEAU
Quality Review Completed 10/11/2016 BILL STUTSMAN
Building Plans Picked Up 10/13/2016 APPLICANT
Applicant returned to address corrections 4/12/2017 EUGENE BARBEAU
Applicant returned to address corrections 6/8/2017 EUGENE BARBEAU
Plan Check Approved 6/16/2017 EUGENE BARBEAU
Issued 6/22/2017 LADBS
TCO Issued (Expire Date: 12-14-2020) 6/17/2020 HENRY BAGHDASSARIAN
CofO in Progress 10/23/2020 HENRY BAGHDASSARIAN
Permit Finaled 10/23/2020 HENRY BAGHDASSARIAN
CofO Issued 10/23/2020 HENRY BAGHDASSARIAN
Permit Finaled 10/23/2020 HENRY BAGHDASSARIAN

Permit Application Clearance Information

CPC Cleared 12/7/2016 EDBER MACEDO
Site Plan review Cleared 12/7/2016 EDBER MACEDO
Address approval Cleared 1/23/2017 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 1/23/2017 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/9/2017 ROBERT DUFF
Internal circulation Cleared 2/15/2017 PEDRO AYALA
Specific Plan Cleared 2/15/2017 PEDRO AYALA
Highway dedication Cleared 3/6/2017 ANDREW SLUSSER
Permit Cleared 3/6/2017 ANDREW SLUSSER
Low Impact Development Cleared 5/11/2017 SAM NAVID
Roof/Waste drainage to street Cleared 5/11/2017 CARLA VALLADARES
Sewer availability Cleared 5/11/2017 CARLA VALLADARES
Building over 3-story or 36-ft Cleared 5/15/2017 CALOSHA APPROVED
DAS Clearance Cleared 5/30/2017 EUGENE BARBEAU
Fire Marshall Fire Life Safety Cleared 6/15/2017 ANDREW KO
Green Code Cleared 6/20/2017 DONALD CRICHLOW

Contact Information

Contractor Essey Construction Company Inc; Lic. No.: 566045-B 10801 NATIONAL BOULEVARD #345      LOS ANGELES, CA 90064

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/1/2017 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 9/19/2017 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 9/21/2017 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 9/27/2017 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/3/2017 Partial Approval JONATHAN ALLEN
Excavation/Setback/Form/Re-Bar 10/23/2017 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 10/23/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/24/2017 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/24/2017 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/25/2017 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/25/2017 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/26/2017 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 10/26/2017 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 10/26/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/27/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/1/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/2/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/3/2017 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/3/2017 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/3/2017 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/7/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/8/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/9/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/14/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/15/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/16/2017 Conditional Approval DANIEL MC AULIFFE
Green Building Rough 11/16/2017 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 11/16/2017 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 11/16/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/17/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/20/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/21/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/22/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/27/2017 Conditional Approval DANIEL MC AULIFFE
Green Building Rough 11/27/2017 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 11/27/2017 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 11/27/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/28/2017 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 11/28/2017 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/29/2017 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/29/2017 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/30/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/1/2017 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 12/1/2017 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 12/5/2017 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/5/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/6/2017 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 12/6/2017 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/7/2017 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/8/2017 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 12/11/2017 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/11/2017 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/13/2017 Approved JONATHAN ALLEN
Footing/Foundation/Slab 12/13/2017 Partial Approval JONATHAN ALLEN
Excavation/Setback/Form/Re-Bar 12/18/2017 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/27/2017 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 12/27/2017 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 12/27/2017 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/27/2017 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 12/29/2017 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 1/3/2018 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 1/3/2018 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 1/8/2018 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 1/8/2018 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 1/10/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 1/16/2018 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 1/16/2018 Not Ready for Inspection DANIEL MC AULIFFE
Special/Order Compliance 1/22/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 1/23/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 1/23/2018 Not Ready for Inspection DANIEL MC AULIFFE
Pre-Inspection 1/24/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/26/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/29/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/30/2018 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 1/30/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/31/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 1/31/2018 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 1/31/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/1/2018 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 2/1/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/2/2018 Approved MILLARD ARDOIN
T-Bar Ceiling 2/2/2018 Not Ready for Inspection MILLARD ARDOIN
Deputy Reinf. Concrete 2/9/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 2/9/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 2/9/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 2/14/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 2/20/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/22/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 3/8/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/9/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 3/14/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/19/2018 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 3/19/2018 Not Ready for Inspection DANIEL MC AULIFFE
Special/Order Compliance 3/19/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/20/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 3/20/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/21/2018 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 3/21/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/22/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/23/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 3/23/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/27/2018 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 3/27/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/28/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 4/2/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 4/4/2018 Partial Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/18/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/19/2018 Conditional Approval JONATHAN ALLEN
Deputy Steel/Welding 4/20/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/23/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/24/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 4/24/2018 Partial Approval DANIEL MC AULIFFE
Structural Steel Frame 4/24/2018 Partial Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/25/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/26/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/27/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/30/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/1/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/2/2018 Approved DANIEL MC AULIFFE
Deputy Steel/Welding 5/3/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/4/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/7/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/8/2018 Approved DANIEL MC AULIFFE
Deputy Steel/Welding 5/9/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/10/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/10/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/11/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 5/11/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/14/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/15/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/16/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/21/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 5/21/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/22/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/24/2018 Conditional Approval DANIEL MC AULIFFE
Wood Frame 5/24/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 5/25/2018 Partial Approval DANIEL MC AULIFFE
Wood Frame 5/29/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 6/4/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 6/5/2018 Partial Approval DANIEL MC AULIFFE
Wood Frame 6/7/2018 Partial Approval DANIEL MC AULIFFE
Wood Frame 6/15/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/25/2018 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 6/25/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/26/2018 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 6/27/2018 Approved DANIEL MC AULIFFE
Wood Frame 6/27/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/28/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/29/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/3/2018 Approved DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 7/3/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/5/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/6/2018 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 7/6/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/9/2018 Approved DANIEL MC AULIFFE
Masonry Wall/Backfill 7/9/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/10/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/11/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/12/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/13/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/16/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/17/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 7/17/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/18/2018 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 7/18/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/19/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 7/19/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/20/2018 Approved DANIEL MC AULIFFE
Deputy Steel/Welding 7/20/2018 Approved DANIEL MC AULIFFE
Masonry Wall/Backfill 7/20/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 7/20/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/23/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 7/23/2018 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 7/23/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/24/2018 Approved DANIEL MC AULIFFE
Deputy Steel/Welding 7/24/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/25/2018 Approved DERRICK SPENCER
Deputy Steel/Welding 7/25/2018 Approved DERRICK SPENCER
Deputy Reinf. Masonry 7/26/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 7/26/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 7/27/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 7/27/2018 Conditional Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 7/30/2018 Partial Approval DANIEL MC AULIFFE
Deputy Steel/Welding 8/1/2018 Approved DANIEL MC AULIFFE
Deputy Steel/Welding 8/2/2018 Approved DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 8/2/2018 Partial Approval DANIEL MC AULIFFE
Deputy Steel/Welding 8/3/2018 Approved DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 8/6/2018 Partial Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 8/7/2018 Partial Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 8/10/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Wood Construction 8/14/2018 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 8/20/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Wood Construction 8/20/2018 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 8/20/2018 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 8/21/2018 Conditional Approval DANIEL MC AULIFFE
Insulation 8/30/2018 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/7/2018 Partial Approval DANIEL MC AULIFFE
Insulation 9/7/2018 Not Ready for Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 9/11/2018 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 9/20/2018 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 9/21/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 10/3/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 10/4/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 10/12/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/15/2018 Approved DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 10/24/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 10/29/2018 Partial Inspection DANIEL MC AULIFFE
Insulation 10/29/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 10/29/2018 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 10/31/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/1/2018 Partial Approval DANIEL MC AULIFFE
Insulation 11/2/2018 Partial Approval DANIEL MC AULIFFE
Wood Frame 11/5/2018 Partial Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Not Ready for Inspection DANIEL MC AULIFFE
Interior/Exterior Lathing 11/15/2018 Partial Approval DANIEL MC AULIFFE
Interior/Exterior Lathing 11/19/2018 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/21/2018 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 11/26/2018 Partial Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Partial Approval DANIEL MC AULIFFE
Wood Frame 12/13/2018 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 1/15/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Drilled-In Anchors 1/16/2019 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 1/16/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 1/17/2019 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 2/4/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 2/22/2019 Not Ready for Inspection TONY HARTONO
Wood Frame 3/6/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 3/7/2019 Partial Inspection DANIEL MC AULIFFE
Structural Steel Frame 3/8/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Steel/Welding 3/12/2019 Conditional Approval DANIEL MC AULIFFE
Wood Frame 3/12/2019 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/19/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 3/27/2019 Partial Approval DANIEL MC AULIFFE
Insulation 4/1/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 4/1/2019 Partial Inspection DANIEL MC AULIFFE
Insulation 4/3/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 4/4/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 4/9/2019 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 4/12/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 4/16/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Wood Construction 4/17/2019 Approved DANIEL MC AULIFFE
Wood Frame 4/17/2019 Not Ready for Inspection DANIEL MC AULIFFE
Drywall Nailing 4/22/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 5/6/2019 Not Ready for Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 5/8/2019 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 5/8/2019 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/10/2019 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 5/13/2019 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 5/14/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 5/14/2019 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 6/4/2019 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Masonry Wall/Backfill 6/6/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 6/11/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 6/24/2019 Partial Inspection TED RIES
Drywall Nailing 6/27/2019 Partial Approval DERRICK SPENCER
Insulation 7/10/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 7/17/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/8/2019 Partial Approval DERRICK SPENCER
Drywall Nailing 8/15/2019 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 8/15/2019 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 8/15/2019 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 8/30/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/16/2019 Partial Approval DERRICK SPENCER
Final 10/18/2019 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 10/18/2019 Approved DERRICK SPENCER
Green Building Final 10/18/2019 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 10/18/2019 Approved DERRICK SPENCER
Reinforced Masonry Frame 10/18/2019 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 10/18/2019 SGSOV Approved DERRICK SPENCER
Smoke Detectors 10/18/2019 Approved DERRICK SPENCER
Structural Steel Frame 10/18/2019 Approved DERRICK SPENCER
Special/Order Compliance 10/21/2019 Approved DERRICK SPENCER
Interior/Exterior Lathing 11/1/2019 Approved DERRICK SPENCER
Drywall Nailing 11/13/2019 Partial Approval DERRICK SPENCER
Pre-Inspection 1/30/2020 Approved DERRICK SPENCER
Special/Order Compliance 2/27/2020 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 3/20/2020 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 3/23/2020 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 3/24/2020 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 3/25/2020 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 3/26/2020 Approved DERRICK SPENCER
Masonry Wall/Backfill 3/26/2020 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 3/27/2020 Approved DERRICK SPENCER
Light Gage Steel Frame 4/3/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/6/2020 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 4/14/2020 Approved DERRICK SPENCER
Special/Order Compliance 5/26/2020 Approved DERRICK SPENCER
Final 5/27/2020 Not Ready for Inspection DERRICK SPENCER
Green Building Final 5/27/2020 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 5/28/2020 Approved DERRICK SPENCER
Wall Anchors 5/29/2020 Approved DERRICK SPENCER
Final 6/8/2020 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/8/2020 Approved DERRICK SPENCER
Final 6/16/2020 Not Ready for Inspection DERRICK SPENCER
Final 7/31/2020 Not Ready for Inspection DERRICK SPENCER
Final 8/7/2020 Partial Approval DERRICK SPENCER