Pre-Inspection
|
6/10/2022
|
Not Ready for Inspection
|
PETER FOLLING
|
|
Piling/Pier/Caisson
|
6/26/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Piling/Pier/Caisson
|
7/18/2024
|
Corrections Issued
|
HENRY KIM
|
|
Deputy Grading
|
7/23/2024
|
No Access for Inspection
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
8/9/2024
|
Conditional Approval
|
JOHN HAYES
|
|
Piling/Pier/Caisson
|
8/9/2024
|
Partial Inspection
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
8/15/2024
|
Conditional Approval
|
HENRY KIM
|
|
Piling/Pier/Caisson
|
8/15/2024
|
Partial Inspection
|
JOHN KIDWELL
|
|
Deputy Reinf. Concrete
|
5/28/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Shotcrete
|
6/27/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Drilled-In Anchors
|
6/30/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
7/1/2025
|
Approved
|
JOHN HAYES
|
|
Green Building Rough
|
7/1/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
7/1/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
7/1/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Deputy Shotcrete
|
7/3/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
7/8/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Sewer
|
7/22/2025
|
Partial Approval
|
JOHN HAYES
|
|
Underground Mechanical
|
7/22/2025
|
Partial Approval
|
JOHN HAYES
|
|
Deputy Shotcrete
|
7/31/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2025
|
Partial Approval
|
JOHN HAYES
|
|
Green Building Rough
|
8/1/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
8/1/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
8/1/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Deputy Shotcrete
|
8/6/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Sewer
|
8/8/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Underground Mechanical
|
8/8/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
8/13/2025
|
Partial Approval
|
JOHN HAYES
|
|
Green Building Rough
|
8/13/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
8/13/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
8/13/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
8/14/2025
|
Conditional Approval
|
HENRY KIM
|
|
Deputy Shotcrete
|
8/26/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
8/28/2025
|
Corrections Issued
|
JOHN HAYES
|
|
Deputy Shotcrete
|
8/29/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
9/2/2025
|
Partial Approval
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
9/10/2025
|
Approved
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
9/10/2025
|
Partial Approval
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
9/12/2025
|
Partial Approval
|
SEAN WIRCH
|
|
Deputy Reinf. Concrete
|
10/6/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Green Building Rough
|
10/6/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
10/6/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
10/6/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Deputy Shotcrete
|
10/7/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Shotcrete
|
10/8/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Deputy Reinf. Concrete
|
10/23/2025
|
Approved
|
JOHN HAYES
|
|
Green Building Rough
|
10/23/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
10/23/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
10/23/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Deputy Shotcrete
|
10/27/2025
|
Conditional Approval
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/10/2025
|
Partial Approval
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2025
|
Approved
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
12/15/2025
|
Partial Approval
|
JOHN HAYES
|
|
Green Building Rough
|
12/15/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Reinforced Concrete Frame
|
12/15/2025
|
Partial Approval
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
12/15/2025
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2026
|
Partial Approval
|
JOHN HAYES
|
|
PLUMBING-Rough
|
2/6/2026
|
Partial Approval
|
SEAN WIRCH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/27/2026
|
Partial Approval
|
SEAN WIRCH
|
|
HVAC-Rough
|
3/13/2026
|
Corrections Issued
|
JOHN HAYES
|
|
PLUMBING-Rough
|
3/19/2026
|
Corrections Issued
|
JOHN HAYES
|
|
PLUMBING-Rough
|
3/24/2026
|
Approved
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
3/31/2026
|
Approved
|
JOHN HAYES
|
|
HVAC-Rough
|
3/31/2026
|
Corrections Issued
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/7/2026
|
Partial Approval
|
JOHN HAYES
|
|
HVAC-Rough
|
4/10/2026
|
Approved
|
JOHN HAYES
|
|
BUILDING-Rough-Frame
|
4/16/2026
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Green Building Rough
|
4/16/2026
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
4/16/2026
|
Approved
|
JOHN HAYES
|
|
BUILDING-Rough-Frame
|
4/29/2026
|
Approved
|
SEAN WIRCH
|
|
Green Building Rough
|
4/29/2026
|
Approved
|
SEAN WIRCH
|
|
Insulation
|
5/4/2026
|
Approved
|
JOHN HAYES
|
|
Interior/Exterior Lathing
|
5/4/2026
|
Partial Approval
|
JOHN HAYES
|
|
Drywall Nailing
|
5/15/2026
|
Approved
|
JOHN HAYES
|
|
Shower Pan
|
5/15/2026
|
Approved
|
JOHN HAYES
|
|
Interior/Exterior Lathing
|
6/2/2026
|
Approved
|
HENRY KIM
|