4273 N ENSENADA DR 91364
Certificate Information: 4273 N ENSENADA DR 91364
- Application / Permit
- 16010-10000-03963
- Plan Check / Job No.
- B16LA13591
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING AND 1-LEVEL OF BASEMENT WITH ATTACHED GARAGE
- Permit Issued
- Issued on 3/13/2020
- Issuing Office
- Metro
- Current Status
- Issued on 3/13/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2016 | YOUNG KIM |
| Corrections Issued | 10/12/2016 | YOUNG KIM |
| Green Plans Picked Up | 10/24/2016 | APPLICANT |
| Building Plans Picked Up | 10/26/2016 | APPLICANT |
| Quality Review Completed | 11/22/2016 | WING SUEN |
| Applicant returned to address corrections | 6/22/2017 | YOUNG KIM |
| Applicant returned to address corrections | 12/11/2018 | YOUNG KIM |
| Applicant returned to address corrections | 1/30/2019 | YOUNG KIM |
| Applicant returned to address corrections | 5/31/2019 | YOUNG KIM |
| Applicant returned to address corrections | 9/12/2019 | YOUNG KIM |
| Applicant returned to address corrections | 9/18/2019 | YOUNG KIM |
| Applicant returned to address corrections | 3/6/2020 | YOUNG KIM |
| Plan Check Approved | 3/13/2020 | YOUNG KIM |
| Issued | 3/13/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 9/25/2018 | JOHN DALLAS |
| GPI Written Notices | Cleared | 12/11/2018 | YOUNG KIM |
| Grading Pre-Inspection | Cleared | 12/11/2018 | YOUNG KIM |
| Excavation more than 5-ft deep | Cleared | 1/30/2019 | CALOSHA APPROVED |
| Permit | Cleared | 2/20/2019 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 4/15/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/15/2019 | ELAINE LEI |
| Green Code | Cleared | 4/24/2019 | JOHN KLARIN |
| CPC | Cleared | 9/16/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 9/16/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 9/16/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 9/16/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 9/16/2019 | LATANYA ROUX |
| Specific Plan | Cleared | 9/16/2019 | LATANYA ROUX |
| Specific Plan | Cleared | 9/16/2019 | LATANYA ROUX |
| Sewer availability | Cleared | 3/11/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai, Luo B; Lic. No.: C80352 | 5244 HUCKLEBERRY OAK STREET SIMI VALLEY, CA 93063 |
| Engineer | Tuchscher, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Piling/Pier/Caisson | 6/26/2024 | Not Ready for Inspection | JOHN HAYES |
| Deputy Reinf. Concrete | 12/12/2024 | Conditional Approval | JOHN HAYES |
| Piling/Pier/Caisson | 12/18/2024 | Corrections Issued | JOHN HAYES |
| Deputy Reinf. Concrete | 12/19/2024 | Conditional Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/20/2024 | Partial Approval | JOHN COLEMAN |
| Deputy Reinf. Concrete | 12/24/2024 | Conditional Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Partial Approval | JOHN HAYES |
| Piling/Pier/Caisson | 12/24/2024 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 12/24/2024 | Approved | JOHN COLEMAN |
| Deputy Reinf. Concrete | 12/31/2024 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | JOHN HAYES |
| Reinforced Concrete Frame | 6/6/2025 | Partial Approval | SEAN WIRCH |
| Deputy Shotcrete | 6/13/2025 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 7/16/2025 | Partial Approval | JOHN KIDWELL |
| Reinforced Concrete Frame | 7/29/2025 | Partial Approval | SEAN WIRCH |
| Underground Mechanical | 8/11/2025 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | JOHN HAYES |
| Deputy Steel/Welding | 9/16/2025 | Conditional Approval | HENRY KIM |
| Deputy Reinf. Concrete | 10/23/2025 | Approved | JOHN HAYES |
| Green Building Rough | 10/23/2025 | Not Ready for Inspection | JOHN HAYES |
| Reinforced Concrete Frame | 10/23/2025 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 10/23/2025 | Not Ready for Inspection | JOHN HAYES |
| Deputy Shotcrete | 10/27/2025 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 1/26/2026 | Partial Approval | SEAN WIRCH |
| Deputy Shotcrete | 2/17/2026 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 3/3/2026 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 3/9/2026 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | JOHN HAYES |
| Wood Frame | 4/10/2026 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 5/11/2026 | Approved | JOHN HAYES |
| PLUMBING-Rough | 5/12/2026 | Approved | JOHN HAYES |
| Shower Pan | 5/15/2026 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 5/21/2026 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Partial Approval | JOHN HAYES |