649 S WALL ST 90014

Certificate Information: 649 S WALL ST 90014

Application / Permit
16010-10000-03925
Plan Check / Job No.
B16LA13467
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Core and Shell first two floors only (Commercial Use). 5 Leves Type IIIA 55 Units affordable housing residential and medical office over 2 levels type IA Podium medical office and parking. (205' x 63')
Permit Issued
Issued on 12/15/2017
Issuing Office
Metro
Current Status
CofO Issued on 8/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2016 APPLICANT
Green Plans Picked Up 1/19/2017 APPLICANT
Assigned to Plan Check Engineer 1/26/2017 SALVADOR QUINTANILLA
Corrections Issued 2/24/2017 SALVADOR QUINTANILLA
Quality Review Completed 3/1/2017 BINH PHAN
Building Plans Picked Up 3/1/2017 APPLICANT
Applicant returned to address corrections 5/3/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/17/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/24/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/2/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/12/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/15/2017 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/14/2017 SALVADOR QUINTANILLA
Plan Check Approved 12/15/2017 SALVADOR QUINTANILLA
Issued 12/15/2017 LADBS
TCO Issued (Expire Date: 06-22-2021) 12/24/2020 ERNESTO CORRAL
TCO Issued (Expire Date: 12-08-2021) 6/11/2021 ERNESTO CORRAL
CofO in Progress 8/24/2021 ERNESTO CORRAL
Permit Finaled 8/24/2021 ERNESTO CORRAL
CofO Issued 8/24/2021 ERNESTO CORRAL
Permit Finaled 8/24/2021 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/4/2017 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 6/27/2017 MARKOS PEREZ-BRAN
Address approval Cleared 7/6/2017 ROCHELLE DUNGCA
Permit Cleared 7/6/2017 ROCHELLE DUNGCA
DAS Clearance Cleared 8/30/2017 SALVADOR QUINTANILLA
"D" conditions Cleared 9/28/2017 DENNIS CHEW
"Q" conditions Cleared 9/28/2017 DENNIS CHEW
Site Plan review Cleared 9/28/2017 DENNIS CHEW
Sewer availability Cleared 10/4/2017 NAZILA NOORIFAR
Miscellaneous Cleared 10/26/2017 STEVEN WECHSLER
Highway dedication Cleared 11/1/2017 ALFREDO JARA
Encroachment in public way Cleared 11/7/2017 JACOB BIGLER
Project located in CRA area Cleared 11/7/2017 JIM URQUHART
Miscellaneous Cleared 11/9/2017 DANIEL SKOLNICK
Opn space landscape/Water mgmt Cleared 11/9/2017 DANIEL SKOLNICK
Building over 3-story or 36-ft Cleared 11/13/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/13/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/13/2017 CALOSHA APPROVED
Miscellaneous Cleared 11/14/2017 DANIEL SKOLNICK
Green Code Cleared 11/21/2017 MICKEY YAMASHITA
Stormwater Pollution Mitigatn Cleared 11/21/2017 MITESH PATEL
Fire Marshall Fire Life Safety Cleared 11/22/2017 OSCAR SALGADO JR
Roof/Waste drainage to street Cleared 12/11/2017 ZEMAMU GEBREWOLD
Housing density bonus Cleared 12/12/2017 RICHARD TRUONG
Work Adjacent to Public Way Cleared 12/13/2017 NAZILA NOORIFAR

Contact Information

Contractor Snyder Langston Residential Llc; Lic. No.: 1021447-B 17962 COWAN      IRVINE, CA 92614
Engineer Thomas, Jelisa Margaret; Lic. No.: C74946 336 E VERDIGO AVE 107      BURBANK, CA 91502
Engineer Yeh, Ming-Yang; Lic. No.: S2587 131 WEST GREEN ST      PASADENA, CA 911059886
Geologist Kirkgard, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 4/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/24/2018 Conditional Approval NICK DANERI
Deputy Other (see comments) 4/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/25/2018 Conditional Approval NICK DANERI
Deputy Other (see comments) 4/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/26/2018 Conditional Approval NICK DANERI
Deputy Other (see comments) 4/27/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/27/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/30/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/1/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/2/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/3/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/4/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 5/4/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/16/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/17/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/18/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/21/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/22/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/23/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 5/23/2018 Partial Approval NICK DANERI
Pre-Inspection 5/23/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/24/2018 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 5/24/2018 Partial Approval NICK DANERI
Pre-Inspection 5/24/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 5/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/29/2018 Conditional Approval ERNESTO CORRAL
Pre-Inspection 5/29/2018 Approved ERNESTO CORRAL
Reinforced Concrete Frame 5/29/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 5/29/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/30/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 5/30/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/31/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/1/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/4/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/18/2018 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/18/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/21/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/22/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/25/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/25/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/27/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/28/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/29/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 6/29/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/2/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/2/2018 Conditional Approval NICK DANERI
Pre-Inspection 7/2/2018 Partial Approval NICK DANERI
Reinforced Concrete Frame 7/2/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/2/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/3/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/3/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/5/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/5/2018 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 7/6/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 7/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/10/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/10/2018 Partial Approval NICK DANERI
Pre-Inspection 7/10/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/16/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/16/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/17/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/17/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/17/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/18/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/18/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/18/2018 Partial Approval NICK DANERI
Pre-Inspection 7/18/2018 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 7/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/20/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 7/23/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/24/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 7/24/2018 Partial Approval NICK DANERI
Pre-Inspection 7/24/2018 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 7/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/27/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/30/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 7/31/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 7/31/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/1/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/2/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 8/2/2018 Partial Approval NICK DANERI
Deputy Reinf. Masonry 8/3/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/8/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 8/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/9/2018 Conditional Approval NICK DANERI
Masonry Wall/Backfill 8/9/2018 Partial Approval NICK DANERI
Pre-Inspection 8/9/2018 Partial Approval NICK DANERI
Deputy Reinf. Masonry 8/10/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/21/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/21/2018 Partial Approval NICK DANERI
Pre-Inspection 8/21/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/22/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/27/2018 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/27/2018 Partial Approval NICK DANERI
Pre-Inspection 8/27/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/28/2018 Conditional Approval NICK DANERI
Special/Order Compliance 8/29/2018 Partial Inspection NICK DANERI
Special/Order Compliance 8/30/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 9/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 9/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 9/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/17/2018 Conditional Approval NICK DANERI
Pre-Inspection 9/17/2018 Partial Approval NICK DANERI
Reinforced Concrete Frame 9/17/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/17/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 9/18/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/20/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/20/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/21/2018 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 9/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/25/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/25/2018 Partial Approval NICK DANERI
Pre-Inspection 9/25/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/27/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/28/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/1/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/1/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 10/2/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/3/2018 Conditional Approval NICK DANERI
Pre-Inspection 10/3/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 10/4/2018 Conditional Approval NICK DANERI
Pre-Inspection 10/4/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 10/5/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/16/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/17/2018 Conditional Approval NICK DANERI
Pre-Inspection 10/17/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 10/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/22/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/22/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/23/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/26/2018 Conditional Approval NICK DANERI
Pre-Inspection 10/26/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/29/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/30/2018 Conditional Approval NICK DANERI
Pre-Inspection 10/30/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/31/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/1/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/2/2018 Conditional Approval NICK DANERI
Pre-Inspection 11/2/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/6/2018 Conditional Approval NICK DANERI
Pre-Inspection 11/6/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/8/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/16/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/21/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/27/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/28/2018 Conditional Approval NICK DANERI
Pre-Inspection 11/28/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/29/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/30/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/3/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/3/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/4/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/10/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/13/2018 Conditional Approval NICK DANERI
Pre-Inspection 12/13/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 12/20/2018 Conditional Approval NICK DANERI
Deputy Wood Construction 12/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 12/21/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/21/2018 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/21/2018 Not Ready for Inspection JAMES POWERS
Wood Frame 12/21/2018 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/26/2018 Conditional Approval NICK DANERI
Deputy Wood Construction 12/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 12/27/2018 Conditional Approval NICK DANERI
Reinforced Masonry Frame 12/27/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/27/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 12/28/2018 Conditional Approval NICK DANERI
Deputy Wood Construction 12/28/2018 Conditional Approval NICK DANERI
Deputy Wood Construction 12/31/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 1/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 1/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/7/2019 Conditional Approval NICK DANERI
Deputy Wood Construction 1/7/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/8/2019 Conditional Approval NICK DANERI
Deputy Wood Construction 1/8/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/9/2019 Conditional Approval NICK DANERI
Deputy Wood Construction 1/9/2019 Conditional Approval NICK DANERI
Masonry Wall/Backfill 1/9/2019 Partial Approval NICK DANERI
Pre-Inspection 1/9/2019 Partial Approval NICK DANERI
Deputy Reinf. Masonry 1/10/2019 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/11/2019 Conditional Approval NICK DANERI
Pre-Inspection 1/23/2019 Partial Inspection NICK DANERI
Special/Order Compliance 1/24/2019 Partial Inspection NICK DANERI
Deputy Wood Construction 1/29/2019 Conditional Approval NICK DANERI
Deputy Wood Construction 2/8/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 2/8/2019 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/19/2019 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/21/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 2/22/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 2/25/2019 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 2/25/2019 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/1/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 3/14/2019 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/14/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 3/15/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/26/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/8/2019 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/8/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 4/9/2019 Conditional Approval NICK DANERI
Pre-Inspection 4/15/2019 Partial Approval NICK DANERI
Wall Anchors 4/15/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/1/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/1/2019 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/8/2019 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 5/14/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/15/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/22/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/28/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/29/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 5/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/30/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/30/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/30/2019 Not Ready for Inspection JAMES POWERS
Wall Anchors 5/30/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 5/30/2019 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 6/4/2019 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 6/5/2019 Not Ready for Inspection JAMES POWERS
Wall Anchors 6/5/2019 Partial Approval JAMES POWERS
Wood Frame 6/5/2019 Partial Approval JAMES POWERS
Insulation 6/7/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/10/2019 Not Ready for Inspection JAMES POWERS
Wall Anchors 6/10/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 6/10/2019 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/12/2019 Not Ready for Inspection JAMES POWERS
Wall Anchors 6/12/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 6/12/2019 Partial Approval JAMES POWERS
Drywall Nailing 6/14/2019 Partial Approval JAMES POWERS
Insulation 6/14/2019 Partial Approval JAMES POWERS
Drywall Nailing 6/18/2019 Partial Approval JAMES POWERS
Insulation 6/25/2019 Partial Approval JAMES POWERS
Insulation 6/27/2019 Partial Approval JAMES POWERS
Drywall Nailing 7/9/2019 Partial Approval JAMES POWERS
Insulation 7/9/2019 Partial Approval JAMES POWERS
Insulation 7/11/2019 Partial Approval JAMES POWERS
Insulation 7/26/2019 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/30/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 7/30/2019 Partial Approval JAMES POWERS
Insulation 8/1/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/2/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/5/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/6/2019 Partial Approval JAMES POWERS
Insulation 8/7/2019 Partial Approval JAMES POWERS
Insulation 8/14/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/14/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 8/14/2019 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 8/16/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/19/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/20/2019 Partial Approval JAMES POWERS
Insulation 8/26/2019 Partial Approval JAMES POWERS
Pre-Inspection 9/3/2019 OK to Expire Permit JAMES POWERS
Insulation 9/9/2019 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/9/2019 Partial Approval JAMES POWERS
Drywall Nailing 9/11/2019 Partial Approval JAMES POWERS
Drywall Nailing 9/13/2019 Partial Approval JAMES POWERS
Insulation 9/13/2019 Partial Approval JAMES POWERS
Insulation 9/19/2019 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/25/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/30/2019 Not Ready for Inspection JAMES POWERS
Insulation 9/30/2019 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/1/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 10/3/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/9/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/9/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/10/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/11/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/15/2019 Conditional Approval ERNESTO CORRAL
Pre-Inspection 10/18/2019 Partial Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 10/21/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/22/2019 Partial Approval JAMES POWERS
Pre-Inspection 10/22/2019 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/23/2019 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/29/2019 Partial Approval JAMES POWERS
Drywall Nailing 11/1/2019 Partial Approval JAMES POWERS
Insulation 11/6/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 11/12/2019 Partial Approval JAMES POWERS
Insulation 11/26/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 12/2/2019 Partial Approval DANIEL MC AULIFFE
Pre-Inspection 12/2/2019 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 12/10/2019 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/17/2019 Partial Approval JAMES POWERS
T-Bar Ceiling 12/23/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/24/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/30/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 1/2/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/7/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/8/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/9/2020 Not Ready for Inspection JAMES POWERS
Wall Anchors 1/9/2020 Partial Approval JAMES POWERS
Wood Frame 1/9/2020 Partial Approval JAMES POWERS
Insulation 1/22/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/29/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/29/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/30/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/30/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/31/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/31/2020 Partial Approval JAMES POWERS
Drywall Nailing 2/21/2020 Partial Approval JAMES POWERS
Pre-Inspection 2/21/2020 Not Ready for Inspection JAMES POWERS
Pre-Inspection 2/25/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/25/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 2/25/2020 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 2/28/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/4/2020 Partial Approval JAMES POWERS
Drywall Nailing 3/4/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/4/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/6/2020 Partial Approval JAMES POWERS
Pre-Inspection 3/6/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/6/2020 Approved JAMES POWERS
Wood Frame 3/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/17/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/18/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/19/2020 Partial Approval JAMES POWERS
Drywall Nailing 3/19/2020 Partial Approval JAMES POWERS
Drywall Nailing 3/20/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/23/2020 Partial Approval JAMES POWERS
Drywall Nailing 3/24/2020 Partial Approval JAMES POWERS
Wood Frame 3/24/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/26/2020 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 4/1/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/1/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/10/2020 Partial Approval JAMES POWERS
Structural Steel Frame 4/16/2020 Approved JAMES POWERS
Wood Frame 4/16/2020 Approved JAMES POWERS
Deputy Reinf. Concrete 4/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/30/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/7/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 5/13/2020 Partial Approval NICK DANERI
Pre-Inspection 5/15/2020 Partial Approval NICK DANERI
Drywall Nailing 5/26/2020 Partial Approval NICK DANERI
Pre-Inspection 6/11/2020 Partial Approval NICK DANERI
Pre-Inspection 6/12/2020 Partial Approval NICK DANERI
Deputy Steel/Welding 6/17/2020 Conditional Approval NICK DANERI
Pre-Inspection 6/26/2020 Conditional Approval NICK DANERI
Deputy Steel/Welding 6/30/2020 Conditional Approval NICK DANERI
Pre-Inspection 8/11/2020 Partial Approval NICK DANERI
Pre-Inspection 8/18/2020 Conditional Approval NICK DANERI
T-Bar Ceiling 8/19/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/21/2020 Corrections Issued NICK DANERI
Pre-Inspection 8/24/2020 Partial Approval NICK DANERI
Special/Order Compliance 9/11/2020 Conditional Approval NICK DANERI
Special/Order Compliance 9/25/2020 Conditional Approval NICK DANERI
Pre-Inspection 10/27/2020 Partial Approval NICK DANERI
Special/Order Compliance 5/26/2021 Conditional Approval NICK DANERI
Drywall Nailing 8/24/2021 Approved ERNESTO CORRAL
Final 8/24/2021 OK to Issue CofO ERNESTO CORRAL
Footing/Foundation/Slab 8/24/2021 Approved ERNESTO CORRAL
Reinforced Concrete Frame 8/24/2021 Approved ERNESTO CORRAL
Reinforced Masonry Frame 8/24/2021 Approved ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 8/24/2021 Approved ERNESTO CORRAL