1401 W EAGLE VISTA DR 90041
Certificate Information: 1401 W EAGLE VISTA DR 90041
- Application / Permit
- 16010-10000-03805
- Plan Check / Job No.
- B16LA12974
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND ROOF DECK AS PART OF A SMALL LOT SUBDIVISION PURSUANT TO VTT-73362-SL. A CERTIFICATE OF OCCUPANCY SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
- Permit Issued
- Issued on 10/18/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2016 | RICARDO SUPAN |
| Corrections Issued | 10/19/2016 | RICARDO SUPAN |
| Green Plans Picked Up | 11/1/2016 | APPLICANT |
| Quality Review Completed | 11/2/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 11/10/2016 | APPLICANT |
| Applicant returned to address corrections | 5/22/2017 | RICARDO SUPAN |
| Applicant returned to address corrections | 5/23/2017 | RICARDO SUPAN |
| Applicant returned to address corrections | 6/6/2017 | RICARDO SUPAN |
| Plan Check Approved | 10/3/2017 | RICARDO SUPAN |
| Issued | 10/18/2017 | LADBS |
| CofO in Progress | 12/6/2021 | SCOTT FINNILA |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
| CofO Issued | 12/18/2021 | DEROLD HAUFF |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2016 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2016 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 12/8/2016 | ROBERT DUFF |
| Highway dedication | Cleared | 1/24/2017 | ROCHELLE DUNGCA |
| Sewer availability | Cleared | 1/31/2017 | ROCHELLE DUNGCA |
| ZA Case | Cleared | 2/7/2017 | FIPE LEILUA |
| ZA Case | Cleared | 2/7/2017 | FIPE LEILUA |
| Frnt yard landscape/Water mgmt | Cleared | 2/21/2017 | JOHN DACEY |
| Private street | Cleared | 2/21/2017 | MARC WOERSCHING |
| Tract Map conditions | Cleared | 2/21/2017 | JOHN DACEY |
| Disturb/Remove Protected Trees | Cleared | 3/7/2017 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 6/6/2017 | RICARDO SUPAN |
| Grading Pre-Inspection | Cleared | 6/6/2017 | RICARDO SUPAN |
| Low Impact Development | Cleared | 8/8/2017 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 9/22/2017 | SOPHEA EK |
| Permit | Cleared | 9/22/2017 | SOPHEA EK |
| Roof/Waste drainage to street | Cleared | 9/22/2017 | SOPHEA EK |
| Green Code | Cleared | 10/2/2017 | JOHN KLARIN |
| Building over 3-story or 36-ft | Cleared | 10/3/2017 | CALOSHA APPROVED |
Contact Information
| Architect | Lee, Wan; Lic. No.: C30792 | 530 MOLINO STREET SUITE 220 LOS ANGELES, CA 90013 |
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | 7320 FIRESTONE BLVD #208 DOWNEY, CA 90241 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Lai, Yoon; Lic. No.: C60565 | 1216 S GARFIELD AVENUE, 200 ALHAMBRA, CA 91801 |
| Engineer | Lai, Yoon; Lic. No.: L8886 | 1216 S GARFIELD AVE 200 ALHAMBRA, CA 91801 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/4/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 8/23/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/18/2018 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/20/2018 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/24/2018 | Conditional Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/13/2018 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/15/2018 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2019 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 5/2/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 5/3/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2019 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/18/2019 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 11/18/2019 | Not Ready for Inspection | SCOTT FINNILA |
| MERV13>=Rough | 11/18/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 11/18/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2019 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/10/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/16/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 1/16/2020 | Corrections Issued | SCOTT FINNILA |
| MERV13>=Rough | 1/16/2020 | Approved | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 1/16/2020 | Corrections Issued | SCOTT FINNILA |
| Verify Rec and Parks Fee Memo | 1/16/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 1/16/2020 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/23/2020 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 1/23/2020 | Partial Inspection | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 1/23/2020 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 1/23/2020 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/16/2020 | Approved | SCOTT FINNILA |
| Green Building Rough | 3/23/2020 | Corrections Issued | SCOTT FINNILA |
| Verify Rec and Parks Fee Memo | 3/23/2020 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/23/2020 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/26/2020 | Conditional Approval | SCOTT FINNILA |
| HVAC-Rough | 3/26/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 3/26/2020 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 3/31/2020 | No Access for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 3/31/2020 | No Access for Inspection | SCOTT FINNILA |
| Wood Frame | 3/31/2020 | No Access for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/20/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 4/20/2020 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 4/20/2020 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 4/20/2020 | Partial Inspection | SCOTT FINNILA |
| Verify Rec and Parks Fee Memo | 4/20/2020 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/28/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Rough | 4/28/2020 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/5/2020 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 5/5/2020 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/8/2020 | Partial Approval | SCOTT FINNILA |
| Insulation | 5/8/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/14/2020 | Approved | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 5/14/2020 | Approved | SCOTT FINNILA |
| Insulation | 6/8/2020 | Approved | SCOTT FINNILA |
| Drywall Nailing | 6/26/2020 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 7/14/2020 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/20/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| Sewer | 10/9/2020 | Corrections Issued | SCOTT FINNILA |
| Sewer | 10/14/2020 | Corrections Issued | SCOTT FINNILA |
| Sewer | 10/16/2020 | No Access for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 10/19/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 10/19/2020 | Not Ready for Inspection | JAMES JENSEN |
| Pre-Inspection | 3/3/2021 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 3/3/2021 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 3/9/2021 | Partial Approval | SCOTT FINNILA |
| Gas Test | 3/10/2021 | Off-Hour Fees Due | |
| Underground Mechanical | 3/10/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/8/2021 | Corrections Issued | SCOTT FINNILA |
| Reinforced Concrete Frame | 4/21/2021 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 8/2/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/2/2021 | Approved | SCOTT FINNILA |
| Green Building Final | 8/2/2021 | Approved | SCOTT FINNILA |
| MERV13>=Final | 8/2/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 8/2/2021 | Partial Inspection | SCOTT FINNILA |
| Smoke Detectors | 8/2/2021 | Approved | SCOTT FINNILA |
| Structural Steel Frame | 8/2/2021 | Approved | SCOTT FINNILA |
| Final | 8/6/2021 | Partial Approval | SCOTT FINNILA |
| Service/Power Release | 8/6/2021 | Not Ready for Inspection | SCOTT FINNILA |
| Service/Power Release | 8/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/6/2021 | Approved | SCOTT FINNILA |
| Final | 12/6/2021 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 12/6/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/6/2021 | Approved | SCOTT FINNILA |