2210 S GLENDON AVE 90064

Certificate Information: 2210 S GLENDON AVE 90064

Application / Permit
16010-10000-03513
Plan Check / Job No.
B16LA12099
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TYPE VB, 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE & BASEMENT STORAGE.
Permit Issued
Issued on 1/25/2017
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2016 APPLICANT
Assigned to Plan Check Engineer 9/1/2016 PRANITA SHAH
Green Plans Picked Up 9/22/2016 APPLICANT
Corrections Issued 9/29/2016 PRANITA SHAH
Quality Review Completed 10/3/2016 KESETE HAREGOT
Building Plans Picked Up 10/3/2016 APPLICANT
Applicant returned to address corrections 11/17/2016 PRANITA SHAH
Plan Check Approved 12/21/2016 PRANITA SHAH
Issued 1/25/2017 LADBS
CofO in Progress 5/26/2020 VINCENT COTTON
Permit Finaled 6/18/2020 RONALD MYRICK
CofO Issued 6/18/2020 RONALD MYRICK
Permit Finaled 6/18/2020 RONALD MYRICK

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/24/2016 ROBERT DUFF
Specific Plan Cleared 10/24/2016 COLLINS ALLAN
ZA Case Cleared 10/24/2016 ERIC CLAROS
ZI Cleared 10/24/2016 ERIC CLAROS
Green Code Cleared 11/1/2016 JONATHAN QUACH
Low Impact Development Cleared 11/8/2016 RYAN HUDSON
Eng Process Fee Ord 176,300 Cleared 12/7/2016 SEVAK ISAKHAYAN
Sewer availability Cleared 12/7/2016 SEVAK ISAKHAYAN
Roof/Waste drainage to street Cleared 12/8/2016 BRIAN KELLY

Contact Information

Architect Levitt, Arnold Stephen; Lic. No.: C10984 2224 GLENDON AVE      LOS ANGELES, CA 90064
Contractor Keating Bill Property Improvement; Lic. No.: 541407-B 7478 DEN ROCK AVE      LOS ANGELES, CA 90045

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/16/2017 Partial Approval ROBERT VORHIS
Pre-Inspection 11/7/2017 Corrections Issued MICHAEL PELHAM
Pre-Inspection 12/5/2017 Partial Inspection MICHAEL PELHAM
Deputy Reinf. Concrete 12/6/2017 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 12/28/2017 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/11/2018 Partial Approval MICHAEL PELHAM
METHANE-Barrier 1/11/2018 Not Ready for Inspection MICHAEL PELHAM
METHANE-Subgrade 1/11/2018 Not Ready for Inspection MICHAEL PELHAM
PLUMBING-Rough 5/21/2018 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/6/2018 Conditional Approval MICHAEL PELHAM
METHANE-Barrier 6/6/2018 Approved MICHAEL PELHAM
METHANE-Subgrade 6/6/2018 Approved MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 7/25/2018 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/25/2018 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/25/2018 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/23/2018 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 10/12/2018 Approved ANTHONY MCDOWALL
PLUMBING-Rough 12/20/2018 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 1/14/2019 Partial Approval ANTHONY MCDOWALL
HVAC-Rough 1/25/2019 Approved ANTHONY MCDOWALL
Pre-Inspection 1/25/2019 Partial Inspection MICHAEL TEMPLE
Shower Pan 2/7/2019 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/27/2019 Partial Approval EVAN COOPER
Wood Frame 2/27/2019 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 3/6/2019 Approved EVAN COOPER
BUILDING-Rough-Frame 3/11/2019 Approved RONALD WEBER
Green Building Rough 3/11/2019 Approved RONALD WEBER
METHANE-Rough 3/11/2019 Approved RONALD WEBER
Verify Sprinkler Sign Off 3/11/2019 Approved RONALD WEBER
Wood Frame 3/11/2019 Approved RONALD WEBER
Insulation 3/14/2019 Approved EVAN COOPER
Interior/Exterior Lathing 3/14/2019 Approved EVAN COOPER
Drywall Nailing 3/29/2019 Approved EVAN COOPER
Interior/Exterior Lathing 7/17/2019 Approved KEVIN BEAULIEU
Sewer 10/16/2019 Approved KEVIN BEAULIEU
ELECTRICAL-Final 3/26/2020 Approved OGANES TARAKHCHYAN
HVAC-Final 3/26/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 3/26/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/1/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/1/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 4/1/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/1/2020 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 4/1/2020 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/1/2020 Approved OGANES TARAKHCHYAN
Final 4/23/2020 Corrections Issued KENNETH NAGLE
Final 5/5/2020 Conditional Approval KENNETH NAGLE
Green Building Final 5/5/2020 Approved KENNETH NAGLE