2210 S GLENDON AVE 90064
Certificate Information: 2210 S GLENDON AVE 90064
- Application / Permit
- 16010-10000-03513
- Plan Check / Job No.
- B16LA12099
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TYPE VB, 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE & BASEMENT STORAGE.
- Permit Issued
- Issued on 1/25/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2016 | PRANITA SHAH |
| Green Plans Picked Up | 9/22/2016 | APPLICANT |
| Corrections Issued | 9/29/2016 | PRANITA SHAH |
| Quality Review Completed | 10/3/2016 | KESETE HAREGOT |
| Building Plans Picked Up | 10/3/2016 | APPLICANT |
| Applicant returned to address corrections | 11/17/2016 | PRANITA SHAH |
| Plan Check Approved | 12/21/2016 | PRANITA SHAH |
| Issued | 1/25/2017 | LADBS |
| CofO in Progress | 5/26/2020 | VINCENT COTTON |
| Permit Finaled | 6/18/2020 | RONALD MYRICK |
| CofO Issued | 6/18/2020 | RONALD MYRICK |
| Permit Finaled | 6/18/2020 | RONALD MYRICK |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/24/2016 | ROBERT DUFF |
| Specific Plan | Cleared | 10/24/2016 | COLLINS ALLAN |
| ZA Case | Cleared | 10/24/2016 | ERIC CLAROS |
| ZI | Cleared | 10/24/2016 | ERIC CLAROS |
| Green Code | Cleared | 11/1/2016 | JONATHAN QUACH |
| Low Impact Development | Cleared | 11/8/2016 | RYAN HUDSON |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2016 | SEVAK ISAKHAYAN |
| Sewer availability | Cleared | 12/7/2016 | SEVAK ISAKHAYAN |
| Roof/Waste drainage to street | Cleared | 12/8/2016 | BRIAN KELLY |
Contact Information
| Architect | Levitt, Arnold Stephen; Lic. No.: C10984 | 2224 GLENDON AVE LOS ANGELES, CA 90064 |
| Contractor | Keating Bill Property Improvement; Lic. No.: 541407-B | 7478 DEN ROCK AVE LOS ANGELES, CA 90045 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/16/2017 | Partial Approval | ROBERT VORHIS |
| Pre-Inspection | 11/7/2017 | Corrections Issued | MICHAEL PELHAM |
| Pre-Inspection | 12/5/2017 | Partial Inspection | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 12/6/2017 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/28/2017 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/11/2018 | Partial Approval | MICHAEL PELHAM |
| METHANE-Barrier | 1/11/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| METHANE-Subgrade | 1/11/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 5/21/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/6/2018 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Barrier | 6/6/2018 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 6/6/2018 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/25/2018 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/25/2018 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2018 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2018 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 12/20/2018 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/14/2019 | Partial Approval | ANTHONY MCDOWALL |
| HVAC-Rough | 1/25/2019 | Approved | ANTHONY MCDOWALL |
| Pre-Inspection | 1/25/2019 | Partial Inspection | MICHAEL TEMPLE |
| Shower Pan | 2/7/2019 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2019 | Partial Approval | EVAN COOPER |
| Wood Frame | 2/27/2019 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 3/6/2019 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/11/2019 | Approved | RONALD WEBER |
| Green Building Rough | 3/11/2019 | Approved | RONALD WEBER |
| METHANE-Rough | 3/11/2019 | Approved | RONALD WEBER |
| Verify Sprinkler Sign Off | 3/11/2019 | Approved | RONALD WEBER |
| Wood Frame | 3/11/2019 | Approved | RONALD WEBER |
| Insulation | 3/14/2019 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/14/2019 | Approved | EVAN COOPER |
| Drywall Nailing | 3/29/2019 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/17/2019 | Approved | KEVIN BEAULIEU |
| Sewer | 10/16/2019 | Approved | KEVIN BEAULIEU |
| ELECTRICAL-Final | 3/26/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 3/26/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/26/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/1/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 4/1/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/1/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 4/1/2020 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/1/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 4/23/2020 | Corrections Issued | KENNETH NAGLE |
| Final | 5/5/2020 | Conditional Approval | KENNETH NAGLE |
| Green Building Final | 5/5/2020 | Approved | KENNETH NAGLE |