Deputy Reinf. Concrete
|
12/16/2019
|
Approved
|
BRAD BESCOS
|
|
Deputy Reinf. Concrete
|
3/26/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
5/18/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Sewer
|
7/28/2020
|
Partial Approval
|
ARTHUR SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/7/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
PLUMBING-Rough
|
8/24/2020
|
Partial Approval
|
ARTHUR SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
2/10/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
PLUMBING-Rough
|
2/10/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Protected Tree Letter
|
2/10/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
2/24/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Protected Tree Letter
|
2/24/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
2/26/2021
|
Conditional Approval
|
THOMAS LOGRASSO
|
|
Deputy Reinf. Concrete
|
3/1/2021
|
Conditional Approval
|
THOMAS LOGRASSO
|
|
Footing/Foundation/Slab
|
3/17/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Protected Tree Letter
|
3/17/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
3/26/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
3/26/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
3/26/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
3/31/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Shotcrete
|
3/31/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
4/6/2021
|
Corrections Issued
|
HAMIK HARTOUNIAN
|
|
Protected Tree Letter
|
4/6/2021
|
Approved
|
HAMIK HARTOUNIAN
|
|
Footing/Foundation/Slab
|
4/14/2021
|
Partial Approval
|
HAMIK HARTOUNIAN
|
|
PLUMBING-Rough
|
4/21/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
5/7/2021
|
No Access for Inspection
|
ELMER BLAND
|
|
Pool Piping
|
6/9/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
6/10/2021
|
Conditional Approval
|
THOMAS LOGRASSO
|
|
Deputy Reinf. Concrete
|
6/14/2021
|
Conditional Approval
|
WILLIAM WREN
|
|
Deputy Shotcrete
|
6/14/2021
|
Conditional Approval
|
WILLIAM WREN
|
|
Deputy Shotcrete
|
6/15/2021
|
Approved
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
6/15/2021
|
Partial Inspection
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
6/15/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
6/15/2021
|
Conditional Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
6/15/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Excavation/Setback/Form/Re-Bar
|
6/22/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
PLUMBING-Rough
|
6/22/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
6/22/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
6/28/2021
|
Approved
|
RONALD KIDWELL
|
|
Green Building Rough
|
7/2/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
7/2/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
7/2/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
7/22/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
7/23/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
8/5/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
8/5/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Special/Order Compliance
|
8/5/2021
|
Corrections Issued
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
8/5/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
8/23/2021
|
Conditional Approval
|
CHARLES BOGHOSKHAN
|
|
Green Building Rough
|
10/12/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
10/12/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
10/12/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Rough-Elec/Plmb/HVAC
|
10/19/2021
|
Partial Approval
|
CHRIS CHRISTENSEN
|
|
Deputy Reinf. Concrete
|
11/4/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
11/4/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Pre-Gunite
|
11/4/2021
|
Approved
|
JOSEPH MCGARRY
|
|
Reinforced Concrete Frame
|
11/4/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
11/4/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Pre-Gunite
|
11/5/2021
|
Approved
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
11/8/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
11/22/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
11/23/2021
|
Conditional Approval
|
CHRIS CHRISTENSEN
|
|
Deputy Steel/Welding
|
11/24/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
11/29/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
11/29/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
11/30/2021
|
Approved
|
JOSEPH MCGARRY
|
|
Excavation/Setback/Form/Re-Bar
|
11/30/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/1/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/2/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/3/2021
|
Conditional Approval
|
ADAM ESCOTO
|
|
Deputy Steel/Welding
|
12/6/2021
|
Corrections Issued
|
LILIANA PORTILLO
|
|
Deputy Steel/Welding
|
12/7/2021
|
Approved
|
ARTHUR SARGSYAN
|
|
Deputy Steel/Welding
|
12/13/2021
|
Conditional Approval
|
CRAIG DAVIS
|
|
Deputy Steel/Welding
|
12/16/2021
|
Approved
|
ARTHUR SARGSYAN
|
|
Deputy Steel/Welding
|
12/17/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/21/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/22/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/23/2021
|
No Access for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/27/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
12/28/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
1/12/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
1/25/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
1/27/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
1/28/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
2/2/2022
|
Approved
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
2/3/2022
|
Approved
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
2/4/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
BUILDING-Rough-Frame
|
2/11/2022
|
Partial Approval
|
CRAIG DAVIS
|
|
Green Building Rough
|
2/11/2022
|
Not Ready for Inspection
|
CRAIG DAVIS
|
|
Structural Steel Frame
|
2/11/2022
|
Partial Inspection
|
CRAIG DAVIS
|
|
Verify Sprinkler Sign Off
|
2/11/2022
|
Not Ready for Inspection
|
CRAIG DAVIS
|
|
Deputy Reinf. Concrete
|
2/17/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
3/31/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
5/5/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
5/9/2022
|
No Access for Inspection
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
5/9/2022
|
Conditional Approval
|
JOSEPH MCGARRY
|
|
Deputy Drilled-In Anchors
|
6/28/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
6/28/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Steel/Welding
|
6/30/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
7/29/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
8/22/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Other (see comments)
|
8/25/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
8/26/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Shotcrete
|
8/26/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Other (see comments)
|
9/13/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Excavation/Setback/Form/Re-Bar
|
9/13/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
9/15/2022
|
Conditional Approval
|
ALIZAH MAYAGOITIA
|
|
Special/Order Compliance
|
9/16/2022
|
Corrections Issued
|
JOSEPH MCGARRY
|
|
Deputy Wood Construction
|
11/3/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Wood Construction
|
11/18/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Wood Construction
|
11/28/2022
|
Conditional Approval
|
RICHARD DOCKUS
|
|
BUILDING-Rough-Frame
|
12/1/2022
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Deputy Wood Construction
|
12/1/2022
|
Approved
|
JOSEPH MCGARRY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/1/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
12/1/2022
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
12/1/2022
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Wood Frame
|
12/1/2022
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
2/13/2023
|
Not Ready for Inspection
|
HAMIK HARTOUNIAN
|
|
Structural Steel Frame
|
2/13/2023
|
Not Ready for Inspection
|
HAMIK HARTOUNIAN
|
|
Verify Sprinkler Sign Off
|
2/13/2023
|
Not Ready for Inspection
|
HAMIK HARTOUNIAN
|
|
Green Building Rough
|
2/23/2023
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Structural Steel Frame
|
2/23/2023
|
Conditional Approval
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
2/23/2023
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Pre-Inspection
|
3/28/2023
|
Corrections Issued
|
DONALD CRICHLOW
|
|
Pre-Inspection
|
8/8/2023
|
Corrections Issued
|
JOSEPH MCGARRY
|
|
Interior/Exterior Lathing
|
11/22/2023
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Pre-Inspection
|
11/28/2023
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Interior/Exterior Lathing
|
12/6/2023
|
Partial Approval
|
JOSEPH MCGARRY
|
|
PLUMBING-Rough
|
2/1/2024
|
Partial Approval
|
JEFFREY MEAD
|
|
PLUMBING-Rough
|
2/2/2024
|
Not Ready for Inspection
|
LILIANA PORTILLO
|
|
HVAC-Rough
|
2/8/2024
|
Conditional Approval
|
ALIZAH MAYAGOITIA
|
|
PLUMBING-Rough
|
2/23/2024
|
Partial Approval
|
BRENDAN MORELLI
|
|
ELECTRICAL-Rough
|
3/7/2024
|
Approved
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
4/17/2024
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2024
|
Partial Approval
|
JEFFREY MEAD
|
|
Gas Test
|
6/12/2024
|
Partial Approval
|
JEFFREY MEAD
|
|
Excavation/Setback/Form/Re-Bar
|
6/13/2024
|
Approved
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
6/13/2024
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
HVAC-Rough
|
6/17/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Drilled-In Anchors
|
6/18/2024
|
Conditional Approval
|
RICHARD DOCKUS
|
|
Deputy Drilled-In Anchors
|
6/21/2024
|
Approved
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
6/25/2024
|
Approved
|
RICHARD DOCKUS
|
|
Excavation/Setback/Form/Re-Bar
|
6/28/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
7/2/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
7/9/2024
|
Not Ready for Inspection
|
JEFFREY MEAD
|
|
Special/Order Compliance
|
7/9/2024
|
Corrections Issued
|
JOAQUIN GREENOUGH
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2024
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
BUILDING-Rough-Frame
|
7/30/2024
|
Not Ready for Inspection
|
JOAQUIN GREENOUGH
|
|
Footing/Foundation/Slab
|
7/30/2024
|
Corrections Issued
|
JOAQUIN GREENOUGH
|
|
Green Building Rough
|
7/30/2024
|
Approved
|
JOAQUIN GREENOUGH
|
|
Verify Sprinkler Sign Off
|
7/30/2024
|
Approved
|
JOAQUIN GREENOUGH
|
|
BUILDING-Rough-Frame
|
8/5/2024
|
Approved
|
JOAQUIN GREENOUGH
|
|
Sewer
|
9/18/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2025
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Interior/Exterior Lathing
|
1/22/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Shower Pan
|
4/7/2025
|
Partial Approval
|
ALEX COLIN
|
|
Drywall Nailing
|
4/10/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/18/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Shower Pan
|
4/18/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
4/23/2025
|
Conditional Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
4/25/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
4/30/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Piling/Pier/Caisson
|
5/1/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
5/5/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Drywall Nailing
|
5/5/2025
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Green Building Final
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Light Gage Steel Frame
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Reinforced Concrete Frame
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
SGSOV-Seismic Gas S/O Valve
|
5/5/2025
|
SGSOV Not Ready
|
ENRIQUE MIRELES
|
|
SUSMP-Std. Urban Storm Water
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Service/Power Release
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Smoke Detectors
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Structural Steel Frame
|
5/5/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Insulation
|
6/17/2025
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Final
|
7/17/2025
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
7/17/2025
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
10/15/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Special/Order Compliance
|
11/7/2025
|
No Access for Inspection
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
1/9/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
1/12/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
5/15/2026
|
Conditional Approval
|
ALEX COLIN
|
|
Excavation/Setback/Form/Re-Bar
|
5/15/2026
|
Approved
|
JEFFREY MEAD
|
|
Deputy Reinf. Concrete
|
5/19/2026
|
Approved
|
ENRIQUE MIRELES
|