3229 W ROWENA AVE 90027

Certificate Information: 3229 W ROWENA AVE 90027

Application / Permit
16010-10000-03308
Plan Check / Job No.
B16LA11364
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY, TYPE VB, SINGLE FAMILY DWELLING WITH ROOF DECK & ATTACHED 2-CAR GARAGE. LOT 4. FULLY SPRINKLERED WITH NFPA-13R (SEE COMMENTS) "SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO./PRELIMINARY PARCEL MAP NO. VTT-73754-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED."
Permit Issued
Issued on 5/24/2018
Issuing Office
Metro
Current Status
CofO Issued on 12/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2016 APPLICANT
Assigned to Plan Check Engineer 9/8/2016 PRANITA SHAH
Green Plans Picked Up 10/3/2016 APPLICANT
Corrections Issued 11/1/2016 PRANITA SHAH
Quality Review Completed 11/2/2016 KESETE HAREGOT
Applicant returned to address corrections 4/9/2018 PRANITA SHAH
Applicant returned to address corrections 4/25/2018 PRANITA SHAH
Plan Check Approved 5/10/2018 PRANITA SHAH
Issued 5/24/2018 LADBS
CofO in Progress 12/24/2020 SCOTT FINNILA
Permit Finaled 12/24/2020 DEROLD HAUFF
CofO Issued 12/24/2020 DEROLD HAUFF
Permit Finaled 12/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2016 ADRIAN SANCHEZ
Address approval Cleared 12/13/2016 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 12/14/2016 JOHN CONNEALLY
Sewer availability Cleared 6/27/2017 ROCHELLE DUNGCA
ZA Case Cleared 7/26/2017 NOAH MCCOY
Low Impact Development Cleared 2/22/2018 RYAN HUDSON
Miscellaneous Cleared 3/8/2018 ARMENIA AGUILAR
Roof/Waste drainage to street Cleared 3/8/2018 ARMENIA AGUILAR
Green Code Cleared 3/19/2018 DONALD CRICHLOW
Tract Map conditions Cleared 4/6/2018 JESSE RAMOS

Contact Information

Architect Lee, Wan; Lic. No.: C30792 530 MOLINO STREET SUITE 220      LOS ANGELES, CA 90013
Contractor Owner-Builder       ,
Engineer De, Rama Reynaldo Tinamisan; Lic. No.: C29108 21335 THOMAS DRIVE      CARSON, CA 90745

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/16/2018 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/20/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/6/2018 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 9/7/2018 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/25/2018 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/9/2018 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/29/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 10/31/2018 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/31/2018 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/19/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/19/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 12/21/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 12/27/2018 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/10/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/22/2019 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/24/2019 Conditional Approval SCOTT FINNILA
Drywall Nailing 1/24/2019 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/28/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/31/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 2/12/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/30/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/31/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Gas Test 5/31/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/31/2019 Partial Approval ALEJANDRO DE ARTOLA
Sewer 5/31/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/4/2019 Approved SCOTT FINNILA
PLUMBING-Rough 6/4/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 6/19/2019 Partial Approval SCOTT FINNILA
Insulation 7/2/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/17/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/17/2019 Approved SCOTT FINNILA
HVAC-Rough 8/1/2019 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 8/8/2019 Partial Approval SCOTT FINNILA
HVAC-Rough 8/8/2019 Approved SCOTT FINNILA
Green Building Rough 8/19/2019 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 8/19/2019 Partial Approval SCOTT FINNILA
Green Building Rough 8/22/2019 Approved SCOTT FINNILA
Shower Pan 8/22/2019 Not Ready for Inspection SCOTT FINNILA
Shower Pan 8/26/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/5/2019 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/30/2019 Approved SCOTT FINNILA
Insulation 9/30/2019 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 9/30/2019 Approved SCOTT FINNILA
Drywall Nailing 10/23/2019 Approved SCOTT FINNILA
Gas Test 10/23/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 10/23/2019 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 10/30/2019 Partial Inspection SCOTT FINNILA
Interior/Exterior Lathing 11/26/2019 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 1/30/2020 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 11/12/2020 Corrections Issued SCOTT FINNILA
Service/Power Release 11/12/2020 Corrections Issued SCOTT FINNILA
Gas Test 11/19/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 12/15/2020 Partial Inspection SCOTT FINNILA
HVAC-Final 12/15/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 12/23/2020 Approved SCOTT FINNILA
Final 12/23/2020 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 12/23/2020 Approved SCOTT FINNILA
Green Building Final 12/23/2020 Approved SCOTT FINNILA
HVAC-Final 12/23/2020 Approved SCOTT FINNILA
PLUMBING-Final 12/23/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 12/23/2020 Approved SCOTT FINNILA
Smoke Detectors 12/23/2020 Approved SCOTT FINNILA
Final 12/24/2020 OK to Issue CofO SCOTT FINNILA