Excavation/Setback/Form/Re-Bar
|
9/12/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
9/26/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Wood Construction
|
11/19/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
3/28/2019
|
Partial Inspection
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/2/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/10/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
4/10/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
4/17/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
5/7/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
5/15/2019
|
Approved
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
6/12/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/18/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
Drywall Nailing
|
7/22/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Underground Mechanical
|
8/6/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
8/26/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/26/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Green Building Rough
|
8/26/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/24/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Gas Test
|
10/23/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Underground Mechanical
|
10/23/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Wood Frame
|
11/19/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
11/26/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Sewer
|
11/26/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
HVAC-Rough
|
1/30/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
1/30/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
1/30/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
2/12/2020
|
Approved
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
2/12/2020
|
Approved
|
SCOTT FINNILA
|
|
Wood Frame
|
2/12/2020
|
Approved
|
SCOTT FINNILA
|
|
Insulation
|
2/24/2020
|
Approved
|
SCOTT FINNILA
|
|
Drywall Nailing
|
3/3/2020
|
Approved
|
SCOTT FINNILA
|
|
Green Building Rough
|
3/3/2020
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
3/3/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
5/12/2020
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
6/15/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Gas Test
|
11/12/2020
|
Corrections Issued
|
SCOTT FINNILA
|
|
Gas Test
|
11/19/2020
|
Approved
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
4/22/2021
|
Approved
|
SCOTT FINNILA
|
|
Final
|
4/22/2021
|
OK to Issue CofO
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
4/22/2021
|
Approved
|
SCOTT FINNILA
|
|
Green Building Final
|
4/22/2021
|
Approved
|
SCOTT FINNILA
|
|
SGSOV-Seismic Gas S/O Valve
|
4/22/2021
|
SGSOV Approved
|
SCOTT FINNILA
|
|
Service/Power Release
|
4/22/2021
|
Approved
|
SCOTT FINNILA
|
|
Smoke Detectors
|
4/22/2021
|
Approved
|
SCOTT FINNILA
|