926 N ORLANDO AVE 90069

Certificate Information: 926 N ORLANDO AVE 90069

Application / Permit
16010-10000-03224
Plan Check / Job No.
B16LA10947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRREGULAR ONE STORY SINGLE FAMILY DWELLING WITH BASEMENT.
Permit Issued
Issued on 4/4/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2016 APPLICANT
Assigned to Plan Check Engineer 9/1/2016 ROSHANAK VARJAVAND
Green Plans Picked Up 9/6/2016 APPLICANT
Corrections Issued 9/23/2016 ROSHANAK VARJAVAND
Quality Review Completed 9/29/2016 LARRY LEE
Building Plans Picked Up 9/30/2016 APPLICANT
Applicant returned to address corrections 11/16/2016 ROSHANAK VARJAVAND
Applicant returned to address corrections 1/13/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 1/27/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 1/30/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 3/14/2017 ROSHANAK VARJAVAND
Plan Check Approved 3/30/2017 ROSHANAK VARJAVAND
Issued 4/4/2017 LADBS
CofO in Progress 4/13/2026 JOSH MEISTER
Permit Finaled 4/13/2026 DEROLD HAUFF
CofO Issued 4/13/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 11/8/2016 DENNIS CHEW
ZI Cleared 11/8/2016 DENNIS CHEW
Address approval Cleared 11/14/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 11/14/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 11/14/2016 JOHN CONNEALLY
Permit Cleared 11/14/2016 RAVIL MANAPOV
Sewer availability Cleared 11/14/2016 RAVIL MANAPOV
Construction near power lines Cleared 12/13/2016 LUCIO FERRER
Low Impact Development Cleared 1/27/2017 SAM NAVID
Roof/Waste drainage to street Cleared 1/27/2017 RAVIL MANAPOV
Excavation more than 5-ft deep Cleared 1/30/2017 CALOSHA APPROVED
Construction within easement Cleared 2/1/2017 OSCAR CASTRO
Green Code Cleared 3/14/2017 JOHN KLARIN

Contact Information

Contractor Homeworx Incorporated; Lic. No.: 868030-B 1294 PIEDMONT DRIVE      UPLAND, CA 91784
Engineer Favretto, Nikica; Lic. No.: C83339 1477 FLORIBUNDA AVE APT 206      BURLINGAME, CA 94010
Engineer Garrison, Skye Mikaella; Lic. No.: C77689 PO BOX 15742      SAN LUIS OBISPO, CA 93406
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/21/2017 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/25/2017 Partial Approval LUIS BARRALES
Underground Mechanical 9/25/2017 Partial Approval LUIS BARRALES
ELECTRICAL-Rough 11/21/2017 Not Ready for Inspection LUIS BARRALES
PLUMBING-Rough 11/21/2017 Not Ready for Inspection LUIS BARRALES
Footing/Foundation/Slab 1/23/2018 Corrections Issued LUIS BARRALES
Excavation/Setback/Form/Re-Bar 1/24/2018 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 1/24/2018 Partial Inspection TIMOTHY O CONNER
Excavation/Setback/Form/Re-Bar 1/30/2018 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/2/2018 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 2/2/2018 Approved CRAIG VAUGHAN
Special/Order Compliance 2/2/2018 Partial Inspection TIMOTHY O CONNER
Structural Steel Frame 6/20/2018 Partial Approval RONALD COWAN
Deputy Drilled-In Anchors 8/17/2018 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 9/26/2018 Not Ready for Inspection BRIAN SULLIVAN
Masonry Wall/Backfill 9/28/2018 Partial Approval RONALD COWAN
Masonry Wall/Backfill 10/2/2018 Partial Inspection RONALD COWAN
Deputy Shotcrete 10/16/2018 Approved RONALD COWAN
Deputy Shotcrete 10/17/2018 Approved RAUL BARAJAS
Deputy Shotcrete 10/18/2018 Approved RONALD COWAN
BUILDING-Rough-Frame 11/19/2018 Not Ready for Inspection RONALD COWAN
Drywall Nailing 11/19/2018 Not Ready for Inspection RONALD COWAN
Final 11/19/2018 Not Ready for Inspection RONALD COWAN
Green Building Final 11/19/2018 Not Ready for Inspection RONALD COWAN
Green Building Rough 11/19/2018 Not Ready for Inspection RONALD COWAN
Reinforced Concrete Frame 11/19/2018 Not Ready for Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 11/19/2018 SGSOV Not Ready RONALD COWAN
Service/Power Release 11/19/2018 Not Ready for Inspection RONALD COWAN
Smoke Detectors 11/19/2018 Not Ready for Inspection RONALD COWAN
Verify Sprinkler Sign Off 11/19/2018 Not Ready for Inspection RONALD COWAN
Masonry Wall/Backfill 3/27/2019 Not Ready for Inspection RONALD MYRICK
Footing/Foundation/Slab 4/12/2019 Partial Approval JOSEPH MCGARRY
Green Building Rough 4/12/2019 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 4/12/2019 Not Ready for Inspection JOSEPH MCGARRY
Deputy Reinf. Concrete 5/3/2019 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/17/2019 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 5/17/2019 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 8/27/2019 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 9/19/2019 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 10/2/2019 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 6/17/2020 Conditional Approval CHRIS CHRISTENSEN
Deputy Wood Construction 6/25/2020 Conditional Approval CHRIS CHRISTENSEN
Deputy Wood Construction 8/7/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 6/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/2/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/16/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/16/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/16/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 6/21/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/21/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/30/2021 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 6/30/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 6/30/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 8/3/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/20/2021 Approved CHRIS CHRISTENSEN
Shower Pan 10/12/2021 Approved CHRIS CHRISTENSEN
Special/Order Compliance 3/4/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 3/23/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Final 7/20/2022 Corrections Issued ADAM ESCOTO
Footing/Foundation/Slab 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Green Building Final 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Reinforced Concrete Frame 7/20/2022 Not Ready for Inspection ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready ADAM ESCOTO
Service/Power Release 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Smoke Detectors 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Verify Sprinkler Sign Off 7/20/2022 Not Ready for Inspection ADAM ESCOTO
Gas Test 10/17/2022 Approved MICHAEL LEWIS
Sewer 10/17/2022 Approved MICHAEL LEWIS
Gas Test 10/18/2022 Corrections Issued MICHAEL LEWIS
Gas Test 10/27/2022 Corrections Issued MICHAEL LEWIS
Gas Test 11/2/2022 Approved MICHAEL LEWIS
HVAC-Final 1/11/2023 Approved MICHAEL LEWIS
PLUMBING-Final 1/27/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 2/7/2023 Approved MICHAEL LEWIS
Gas Test 2/10/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/22/2023 Approved MICHAEL LEWIS
Final 2/22/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 2/22/2023 Approved MICHAEL LEWIS
Green Building Final 2/22/2023 Approved MICHAEL LEWIS
Reinforced Concrete Frame 2/22/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 2/22/2023 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 2/22/2023 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 2/22/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/8/2023 Corrections Issued MICHAEL LEWIS
Enclosure/Fence 11/9/2023 Not Ready for Inspection LILIANA PORTILLO
Special/Order Compliance 4/25/2024 Partial Inspection AMIR NAZARIAN
Pre-Inspection 6/17/2024 Corrections Issued AMIR NAZARIAN
Special/Order Compliance 4/7/2025 Approved JOSE MACIAS
ELECTRICAL-Final 11/6/2025 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 11/12/2025 Approved JOSH MEISTER
Special/Order Compliance 2/13/2026 No Access for Inspection JOSH MEISTER
Final 2/25/2026 Corrections Issued JOSH MEISTER
Service/Power Release 2/25/2026 Not Ready for Inspection JOSH MEISTER
Smoke Detectors 2/25/2026 Approved JOSH MEISTER
Final 3/12/2026 Not Ready for Inspection JOSH MEISTER
Service/Power Release 3/12/2026 Not Ready for Inspection JOSH MEISTER
Final 4/13/2026 OK to Issue CofO JOSH MEISTER
Service/Power Release 4/13/2026 Approved JOSH MEISTER