318 1/2 N ROBINSON ST 90026

Certificate Information: 318 1/2 N ROBINSON ST 90026

Application / Permit
16010-10000-03087
Plan Check / Job No.
B16LA10342
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO. 73982. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 4/17/2017
Issuing Office
Metro
Current Status
CofO Issued on 4/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2016 APPLICANT
Assigned to Plan Check Engineer 7/28/2016 TEODORO DIAZ RODRIGUEZ
Corrections Issued 8/2/2016 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 8/3/2016 KESETE HAREGOT
Building Plans Picked Up 8/5/2016 APPLICANT
Green Plans Picked Up 8/10/2016 APPLICANT
Plan Check Approved 3/23/2017 TEODORO DIAZ RODRIGUEZ
Issued 4/17/2017 LADBS
Permit Closed-Status Void 10/31/2017 SCOTT FINNILA
Re-Activate Permit 2/13/2018 SCOTT FINNILA
CofO in Progress 4/19/2023 ALIZAH MAYAGOITIA
Permit Finaled 4/23/2023 DEROLD HAUFF
Permit Finaled 4/23/2023 DEROLD HAUFF
CofO Issued 4/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/29/2016 RAVIL MANAPOV
Green Code Cleared 12/9/2016 JONATHAN QUACH
Green Code Cleared 12/9/2016 TEODORO DIAZ RODRIGUEZ
Address approval Cleared 1/23/2017 RAVIL MANAPOV
Sewer availability Cleared 1/23/2017 RAVIL MANAPOV
Highway dedication Cleared 1/25/2017 JACOB BIGLER
Miscellaneous Cleared 1/26/2017 ARMENIA AGUILAR
Permit Cleared 1/26/2017 ARMENIA AGUILAR
Roof/Waste drainage to street Cleared 1/26/2017 ARMENIA AGUILAR
Low Impact Development Cleared 3/9/2017 SAM NAVID
Frnt yard landscape/Water mgmt Cleared 3/16/2017 DAISY BENICIA
Hydrant and Access approval Cleared 3/16/2017 JOHN CONNEALLY
Tract Map conditions Cleared 3/16/2017 DAISY BENICIA
Building over 3-story or 36-ft Cleared 3/23/2017 CALOSHA APPROVED
GPI Written Notices Cleared 3/23/2017 TEODORO DIAZ RODRIGUEZ
Grading Pre-Inspection Cleared 3/23/2017 TEODORO DIAZ RODRIGUEZ

Contact Information

Architect Bien-Willner, Carina A; Lic. No.: C33114 2160 CENTURY PARK EAST # 210 N      LOS ANGELES, CA 90067
Engineer Nguyen, Tuan Minh; Lic. No.: S5883 503 E FRANKLIN AVE 2      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2017 Partial Approval SCOTT FINNILA
METHANE-Barrier 9/11/2017 Partial Approval SCOTT FINNILA
METHANE-Subgrade 9/11/2017 Partial Approval SCOTT FINNILA
PLUMBING-Rough 10/19/2017 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 10/31/2017 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 2/22/2018 Conditional Approval MICHAEL FAUNCE
Drywall Nailing 3/21/2018 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/21/2018 Partial Approval ENRIQUE MIRELES
Green Building Rough 3/21/2018 Partial Approval ENRIQUE MIRELES
Drywall Nailing 4/3/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/3/2018 Partial Approval SCOTT FINNILA
Green Building Rough 4/3/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 4/9/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/20/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 4/30/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/30/2018 Partial Approval SCOTT FINNILA
Green Building Rough 4/30/2018 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 5/2/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/18/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/30/2018 Conditional Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 6/1/2018 Conditional Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 6/22/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/27/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/27/2018 Partial Approval SCOTT FINNILA
METHANE-Barrier 6/27/2018 Partial Approval SCOTT FINNILA
METHANE-Subgrade 6/27/2018 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/24/2018 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 7/25/2018 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/27/2018 Partial Approval SCOTT FINNILA
Gas Test 8/30/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/7/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/12/2018 Partial Inspection MICHAEL FAUNCE
Deputy Wood Construction 1/4/2019 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/4/2019 Partial Approval ALEJANDRO DE ARTOLA
Insulation 2/20/2019 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 2/20/2019 Partial Inspection SCOTT FINNILA
Shower Pan 3/8/2019 Corrections Issued SCOTT FINNILA
Shower Pan 3/12/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/28/2019 Conditional Approval SCOTT FINNILA
Green Building Rough 3/28/2019 Approved SCOTT FINNILA
METHANE-Rough 3/28/2019 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 3/28/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 4/9/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/11/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 4/17/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/17/2019 Approved SCOTT FINNILA
PLUMBING-Rough 5/16/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 3/16/2020 Conditional Approval SCOTT FINNILA
Underground Mechanical 7/7/2020 Partial Approval SCOTT FINNILA
Service/Power Release 8/13/2020 Partial Inspection DONALD CRICHLOW
Green Building Final 10/25/2021 Corrections Issued DONALD CRICHLOW
ELECTRICAL-Final 8/1/2022 Approved SCOTT FINNILA
HVAC-Final 8/1/2022 Approved SCOTT FINNILA
Gas Test 8/11/2022 Approved STUART CHAPMAN
Green Building Final 8/11/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 8/11/2022 Approved STUART CHAPMAN
Service/Power Release 12/8/2022 Approved SCOTT FINNILA
Final 1/31/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/31/2023 Approved ALIZAH MAYAGOITIA
Green Building Final 1/31/2023 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 1/31/2023 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 1/31/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 1/31/2023 Approved ALIZAH MAYAGOITIA
Final 4/18/2023 OK to Issue CofO ALIZAH MAYAGOITIA