8144 1/2 W GOULD AVE 90046

Certificate Information: 8144 1/2 W GOULD AVE 90046

Application / Permit
16010-10000-03064
Plan Check / Job No.
B16LA10290
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD and NEW ACCESSORY DWELLING UNIT
Permit Issued
Issued on 1/14/2021
Issuing Office
Current Status
CofO Issued on 7/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2016 APPLICANT
Assigned to Plan Check Engineer 8/4/2016 DEAN LEE
Corrections Issued 8/9/2016 DEAN LEE
Quality Review Completed 8/16/2016 BILL STUTSMAN
Applicant returned to address corrections 2/16/2017 DEAN LEE
Applicant returned to address corrections 9/8/2017 DEAN LEE
Applicant returned to address corrections 9/27/2017 DEAN LEE
Applicant returned to address corrections 10/17/2017 DEAN LEE
Applicant returned to address corrections 12/13/2017 DEAN LEE
Green Plans Picked Up 2/6/2018 APPLICANT
Applicant returned to address corrections 6/17/2019 DEAN LEE
Applicant returned to address corrections 5/13/2020 DEAN LEE
Applicant returned to address corrections 6/18/2020 DEAN LEE
Applicant returned to address corrections 6/26/2020 DEAN LEE
Applicant returned to address corrections 10/14/2020 DEAN LEE
Applicant returned to address corrections 10/20/2020 DEAN LEE
Applicant returned to address corrections 10/30/2020 DEAN LEE
Applicant returned to address corrections 11/20/2020 DEAN LEE
Applicant returned to address corrections 12/2/2020 DEAN LEE
Plan Check Approved 1/5/2021 DEAN LEE
Issued 1/14/2021 APPLICANT
Building Plans Picked Up 1/19/2021 APPLICANT
CofO in Progress 1/12/2024 RAUL BARAJAS
Permit Finaled 7/30/2024 RONALD MYRICK
CofO Issued 7/30/2024 RONALD MYRICK
Permit Finaled 7/30/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/15/2016 DEAN LEE
Address approval Cleared 8/16/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 8/16/2017 ROCHELLE DUNGCA
Hold Cleared 8/16/2017 TERESA MUI
Sewer availability Cleared 8/16/2017 ROCHELLE DUNGCA
Green Code Cleared 2/13/2018 ALDO UBAU
ZA Case Cleared 5/21/2019 ANNA VAN
BHO/Hillside ordinance Cleared 11/18/2019 LINDA MARGARET
BHO/Hillside ordinance Cleared 11/18/2019 LINDA MARGARET
BHO/Hillside ordinance Cleared 11/18/2019 LINDA MARGARET
BHO/Hillside ordinance Cleared 11/18/2019 LINDA MARGARET
CPC Cleared 11/18/2019 ANNA VIDAL
Distance to fire station Cleared 11/18/2019 JOHN CONNEALLY
Hydrant and Access approval Cleared 11/18/2019 JOHN CONNEALLY
Permit Cleared 11/18/2019 LINDA MARGARET
Roof/Waste drainage to street Cleared 11/18/2019 LINDA MARGARET
ZI Cleared 11/18/2019 ANNA VIDAL
ZI Cleared 11/18/2019 ANNA VIDAL
Encroachment in public way Cleared 11/19/2019 ELENA LOPEZ
Construction near power lines Cleared 12/10/2019 WALTER RAMIREZ
Construction within easement Cleared 12/10/2019 WALTER RAMIREZ
BHO/Hillside ordinance Cleared 12/11/2019 LINDA MARGARET
Miscellaneous Cleared 12/11/2019 LINDA MARGARET
Building over 3-story or 36-ft Cleared 12/18/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/18/2019 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 2/14/2020 ARMEN SARKISIAN
Distance to fire station Cleared 2/26/2020 JOHN CONNEALLY
Mechanical Car Lift Cleared 6/12/2020 ANDREW KO
Low Impact Development Cleared 9/16/2020 JORGE MEJIA LEMUS
Address approval Cleared 9/28/2020 RENZ SORIANO
Private street Cleared 10/27/2020 RICHARD REASER

Contact Information

Architect Massaro,, Jon Robert; Lic. No.: C23463 8335 WINNETKA AVENUE      WINNETKA, CA 91306
Contractor Owner-Builder       ,
Engineer Berger,, Phillip M; Lic. No.: C13128 2760 E 4TH ST APT 321      NATIONAL CITY, CA 91950
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781
Engineer Tsao,, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/24/2021 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 4/26/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 4/27/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 5/28/2021 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 6/14/2021 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/14/2021 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 6/14/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/15/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/30/2021 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 7/1/2021 Not Ready for Inspection RICHARD STEINBACH
PLUMBING-Rough 7/8/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 7/15/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/16/2021 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 7/23/2021 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 7/26/2021 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/26/2021 Conditional Approval RAUL BARAJAS
Green Building Rough 7/26/2021 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 7/26/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 7/26/2021 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 7/28/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/5/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/9/2021 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/11/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/12/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/19/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/20/2021 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 9/3/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/7/2021 Not Ready for Inspection RICHARD STEINBACH
Deputy Reinf. Concrete 9/9/2021 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/13/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 9/17/2021 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 12/9/2021 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 12/27/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/10/2022 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 3/11/2022 Conditional Approval RAUL BARAJAS
Drywall Nailing 6/10/2022 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/6/2023 Conditional Approval RAUL BARAJAS
Final 1/6/2023 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/6/2023 Approved RAUL BARAJAS
Green Building Final 1/6/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 1/6/2023 Approved RAUL BARAJAS
Reinforced Concrete Frame 1/6/2023 Conditional Approval RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 1/6/2023 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 1/6/2023 Approved RAUL BARAJAS
Structural Steel Frame 1/6/2023 Conditional Approval RAUL BARAJAS
Verify Sprinkler Sign Off 1/6/2023 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 3/24/2023 Corrections Issued RAUL BARAJAS
Service/Power Release 3/29/2023 Partial Inspection RAUL BARAJAS
Service/Power Release 4/3/2023 Conditional Approval RAUL BARAJAS
Service/Power Release 4/13/2023 Approved RAUL BARAJAS
Sewer 4/13/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/9/2023 Approved RAUL BARAJAS
Final 5/9/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Final 5/9/2023 Approved RAUL BARAJAS
Reinforced Concrete Frame 5/9/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved RAUL BARAJAS
Structural Steel Frame 5/9/2023 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 5/9/2023 Approved RAUL BARAJAS
Pre-Inspection 9/20/2023 Partial Inspection RAUL BARAJAS
Final 12/14/2023 Corrections Issued RAUL BARAJAS
Special/Order Compliance 12/20/2023 Not Ready for Inspection RAUL BARAJAS
Final 1/3/2024 Corrections Issued RAUL BARAJAS
Final 1/12/2024 OK to Issue CofO RAUL BARAJAS