Footing/Foundation/Slab
|
11/30/2017
|
Approved
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/27/2017
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/9/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/15/2018
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
3/16/2018
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
3/19/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/20/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/21/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/22/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/23/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
3/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
4/30/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
4/30/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/30/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
4/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/1/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/9/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/10/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/11/2018
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
5/23/2018
|
Approved
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
5/23/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/23/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
5/23/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
5/29/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/29/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
5/29/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/30/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
5/30/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/31/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/1/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/4/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/5/2018
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
6/6/2018
|
Approved
|
JOEY BUCHANAN
|
|
Insulation
|
6/6/2018
|
Approved
|
JOEY BUCHANAN
|
|
Verify Sprinkler Sign Off
|
6/6/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
6/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/13/2018
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
6/19/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
6/19/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/22/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/28/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
6/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/2/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/3/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/5/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
7/6/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/19/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/20/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/21/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
10/9/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
10/10/2018
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Final
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Final
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
10/10/2018
|
SGSOV Not Ready
|
JAMES POWERS
|
|
SUSMP-Std. Urban Storm Water
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Smoke Detectors
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
10/11/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
10/12/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/15/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/16/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/17/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/18/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/19/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
12/17/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
12/18/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
12/19/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
12/20/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
12/21/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/26/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/27/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/28/2018
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/29/2019
|
Approved
|
JOEY BUCHANAN
|
|
Final
|
5/29/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Green Building Final
|
5/29/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
SGSOV-Seismic Gas S/O Valve
|
5/29/2019
|
SGSOV Approved
|
JOEY BUCHANAN
|
|
SUSMP-Std. Urban Storm Water
|
5/29/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Smoke Detectors
|
5/29/2019
|
Approved
|
JOEY BUCHANAN
|
|
Wood Frame
|
5/29/2019
|
Approved
|
JOEY BUCHANAN
|
|
Final
|
6/5/2019
|
OK for TCO
|
JAMES POWERS
|
|
Green Building Final
|
6/5/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
SUSMP-Std. Urban Storm Water
|
6/5/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Special/Order Compliance
|
1/7/2020
|
Approved
|
JAMES POWERS
|
|
Final
|
2/6/2020
|
OK to Issue CofO
|
JAMES POWERS
|
|
SUSMP-Std. Urban Storm Water
|
2/6/2020
|
Approved
|
JAMES POWERS
|