2100-2106 E 99TH PL BLDG 8-1 90002

Certificate Information: 2100-2106 E 99TH PL BLDG 8-1 90002

Application / Permit
16010-10000-02994
Plan Check / Job No.
B16LA11293
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 3-STORY 5-UNIT APARTMENT.
Permit Issued
Issued on 3/24/2017
Issuing Office
Metro
Current Status
CofO Issued on 2/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2016 APPLICANT
Assigned to Plan Check Engineer 7/28/2016 JOHN FRANCIA
Corrections Issued 8/4/2016 JOHN FRANCIA
Quality Review Completed 8/4/2016 CHARMIE HUYNH
Building Plans Picked Up 8/4/2016 APPLICANT
Disabled Access Plans Picked Up 8/4/2016 APPLICANT
Green Plans Picked Up 8/4/2016 APPLICANT
Applicant returned to address corrections 8/31/2016 JOHN FRANCIA
Applicant returned to address corrections 9/15/2016 JOHN FRANCIA
Applicant returned to address corrections 11/1/2016 JOHN FRANCIA
Applicant returned to address corrections 11/3/2016 JOHN FRANCIA
Applicant returned to address corrections 11/8/2016 JOHN FRANCIA
Applicant returned to address corrections 11/22/2016 JOHN FRANCIA
Applicant returned to address corrections 12/6/2016 JOHN FRANCIA
Plan Check Approved 12/15/2016 JOHN FRANCIA
Issued 3/24/2017 LADBS
TCO Issued (Expire Date: 02-01-2020) 8/5/2019 WINSTON DUNNING
CofO in Progress 2/6/2020 JAMES POWERS
CofO Issued 2/7/2020 DAVID TSAU
Permit Finaled 2/7/2020 DAVID TSAU

Permit Application Clearance Information

Encroachment in public way Cleared 8/29/2016 JAMES KHO
Work Adjacent to Public Way Cleared 8/29/2016 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/1/2016 CELINA MORENO
Driveway location Cleared 9/29/2016 TAIMOUR TANAVOLI
Internal circulation Cleared 9/29/2016 TAIMOUR TANAVOLI
Hydrant and Access approval Cleared 9/30/2016 JOHN CONNEALLY
Highway dedication Cleared 11/10/2016 JAMES KHO
Permit Cleared 11/28/2016 ZEMAMU GEBREWOLD
Miscellaneous Cleared 12/2/2016 ALAN COMO
Miscellaneous Cleared 12/2/2016 ALAN COMO
Miscellaneous Cleared 12/2/2016 ALAN COMO
Frnt yard landscape/Water mgmt Cleared 12/5/2016 HERMAN VAN BUREN
Private street Cleared 12/5/2016 HERMAN VAN BUREN
Private street Cleared 12/5/2016 HERMAN VAN BUREN
Tract Map conditions Cleared 12/5/2016 HERMAN VAN BUREN
Address approval Cleared 12/6/2016 CARL MILLS
Building over 3-story or 36-ft Cleared 12/13/2016 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 12/13/2016 SUSIE ADAMIAN
Green Code Cleared 12/13/2016 JOHN FRANCIA
Green Code Cleared 12/13/2016 JOHN FRANCIA
Low Impact Development Cleared 12/13/2016 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/13/2016 ZEMAMU GEBREWOLD
DAS Clearance Cleared 12/15/2016 SHINE LIN
Sewer availability Cleared 12/15/2016 CELINA MORENO
Specific Plan Cleared 12/15/2016 ALAN COMO
Specific Plan Cleared 12/15/2016 ALAN COMO

Contact Information

Architect Vasquez, Ernesto M; Lic. No.: C9135 3 MACARTHUR PL. #850      SANTA ANA, CA 92707
Contractor Cannon Constructors South Inc; Lic. No.: 900698-B 17000 VENTURA BLVD #301      ENCINO, CA 91316
Engineer Nam, Young-Keun; Lic. No.: S4029 17 SANTA EUGENIA      IRVINE, CA 92606
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/20/2017 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 11/30/2017 Approved JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/11/2018 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/22/2018 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/28/2018 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 3/1/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/2/2018 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/9/2018 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/12/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/15/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/16/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/19/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/20/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/21/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/22/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/23/2018 Partial Approval JAMES POWERS
Deputy Wood Construction 3/29/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/2/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/3/2018 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 4/4/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/5/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/6/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/9/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/10/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/24/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/25/2018 Approved JOEY BUCHANAN
Deputy Fireproofing 4/26/2018 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 4/26/2018 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 4/27/2018 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 4/27/2018 Partial Approval JOEY BUCHANAN
Green Building Rough 4/30/2018 Not Ready for Inspection JAMES POWERS
Pre-Inspection 4/30/2018 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 4/30/2018 Not Ready for Inspection JAMES POWERS
Wood Frame 4/30/2018 Partial Approval JAMES POWERS
Insulation 5/9/2018 Not Ready for Inspection JAMES POWERS
Insulation 5/21/2018 Partial Approval JAMES POWERS
Green Building Rough 5/23/2018 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/23/2018 Not Ready for Inspection JAMES POWERS
Wood Frame 5/23/2018 OK to Expire Permit JAMES POWERS
Interior/Exterior Lathing 5/24/2018 Approved JOEY BUCHANAN
Interior/Exterior Lathing 5/25/2018 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 5/29/2018 Partial Approval JAMES POWERS
Drywall Nailing 5/29/2018 Not Ready for Inspection JAMES POWERS
Insulation 5/29/2018 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/29/2018 Not Ready for Inspection JAMES POWERS
Wood Frame 5/29/2018 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 5/30/2018 Partial Approval JAMES POWERS
Deputy Wood Construction 5/30/2018 Partial Approval JAMES POWERS
Insulation 5/30/2018 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 5/31/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/1/2018 Partial Approval JAMES POWERS
Insulation 6/1/2018 Approved JAMES POWERS
Deputy Wood Construction 6/13/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/22/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/2/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/3/2018 Partial Approval JAMES POWERS
Drywall Nailing 7/3/2018 Approved JAMES POWERS
Deputy Steel/Welding 7/5/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/6/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/9/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/10/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/11/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/12/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/13/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/30/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/31/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/1/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/2/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/3/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/7/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/8/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2018 Partial Approval JAMES POWERS
Pre-Inspection 8/9/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/14/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/15/2018 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 8/16/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2018 Partial Approval JAMES POWERS
Masonry Wall/Backfill 8/31/2018 Approved JAMES POWERS
Deputy Drilled-In Anchors 9/19/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/20/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/21/2018 Partial Approval JAMES POWERS
Pre-Inspection 10/1/2018 Partial Approval JAMES POWERS
Final 10/10/2018 Not Ready for Inspection JAMES POWERS
Green Building Final 10/10/2018 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/10/2018 SGSOV Not Ready JAMES POWERS
SUSMP-Std. Urban Storm Water 10/10/2018 Not Ready for Inspection JAMES POWERS
Smoke Detectors 10/10/2018 Approved JAMES POWERS
Verify Sprinkler Sign Off 10/10/2018 Not Ready for Inspection JAMES POWERS
Wood Frame 10/10/2018 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/15/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/24/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/24/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/25/2018 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/25/2018 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/26/2018 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/26/2018 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/13/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/17/2018 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 12/18/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/19/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/20/2018 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/21/2018 Partial Approval JAMES POWERS
Final 4/2/2019 Not Ready for Inspection JAMES POWERS
Green Building Final 4/2/2019 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/2/2019 SGSOV No Gas JAMES POWERS
SUSMP-Std. Urban Storm Water 4/2/2019 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/2/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 4/2/2019 Partial Approval JAMES POWERS
Final 5/7/2019 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 5/7/2019 Not Ready for Inspection JOEY BUCHANAN
SUSMP-Std. Urban Storm Water 5/7/2019 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 5/7/2019 Approved JOEY BUCHANAN
Wood Frame 5/7/2019 Approved JOEY BUCHANAN
Final 6/5/2019 OK for TCO JAMES POWERS
Green Building Final 6/5/2019 Approved JAMES POWERS
SUSMP-Std. Urban Storm Water 6/5/2019 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 1/7/2020 Approved JAMES POWERS
Final 2/6/2020 OK to Issue CofO JAMES POWERS
SUSMP-Std. Urban Storm Water 2/6/2020 Approved JAMES POWERS