Deputy Reinf. Concrete
|
1/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/31/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/1/2018
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
2/2/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
2/5/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/6/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
2/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/9/2018
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
2/28/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/1/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/2/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2018
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
4/23/2018
|
Partial Approval
|
JOEY BUCHANAN
|
|
Piling/Pier/Caisson
|
4/23/2018
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
5/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/22/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/4/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/6/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/8/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/9/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/10/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/10/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/16/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/20/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/27/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/28/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
8/31/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/4/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/5/2018
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
9/5/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/6/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
9/7/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/14/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/18/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/19/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/19/2018
|
Approved
|
JAMES POWERS
|
|
Pre-Inspection
|
10/10/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/22/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/23/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/24/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/25/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
10/26/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
10/29/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/30/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/31/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/1/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/1/2018
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/2/2018
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/5/2018
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
11/19/2018
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
11/20/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
11/21/2018
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
11/28/2018
|
Approved
|
JAMES POWERS
|
|
Drywall Nailing
|
12/11/2018
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
1/8/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/13/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/14/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/15/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
3/18/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/9/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/10/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/11/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/12/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/15/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
4/23/2019
|
Approved
|
TED RIES
|
|
Deputy Steel/Welding
|
4/25/2019
|
Approved
|
TED RIES
|
|
Deputy Steel/Welding
|
4/26/2019
|
Approved
|
TED RIES
|
|
Deputy Steel/Welding
|
4/29/2019
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
6/5/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/17/2019
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
6/18/2019
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
6/19/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/20/2019
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
6/21/2019
|
Approved
|
JOEY BUCHANAN
|
|
Final
|
8/8/2019
|
OK for TCO
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
Green Building Rough
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
8/8/2019
|
SGSOV No Gas
|
JAMES POWERS
|
|
Smoke Detectors
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
8/8/2019
|
Approved
|
JAMES POWERS
|
|
Special/Order Compliance
|
2/7/2020
|
Approved
|
JAMES POWERS
|
|
Final
|
2/12/2020
|
OK to Issue CofO
|
JAMES POWERS
|