3670 N BUENA PARK DR 91604
Certificate Information: 3670 N BUENA PARK DR 91604
- Application / Permit
- 16010-10000-02936
- Plan Check / Job No.
- B16LA09912
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3 STORY SFD OVER BASEMENT GARAGE
- Permit Issued
- Issued on 4/18/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2016 | HANS SANTIAGO |
| Corrections Issued | 7/26/2016 | HANS SANTIAGO |
| Quality Review Completed | 7/29/2016 | BILL STUTSMAN |
| Building Plans Picked Up | 8/4/2016 | APPLICANT |
| Green Plans Picked Up | 8/4/2016 | APPLICANT |
| Applicant returned to address corrections | 9/30/2016 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/22/2016 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/13/2017 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/15/2017 | HANS SANTIAGO |
| Plan Check Approved | 2/23/2017 | Andrew Santiago |
| Plan Check Approved | 4/18/2017 | Andrew Santiago |
| Issued | 4/18/2017 | LADBS |
| CofO in Progress | 4/15/2025 | CHRISTOPHE COCHRAN |
| CofO Issued | 4/30/2025 | RUBEN SALAS |
| Permit Finaled | 4/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 9/2/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 9/2/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 9/2/2016 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 9/2/2016 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 12/2/2016 | ALFREDO JARA |
| BHO/Hillside ordinance | Cleared | 12/6/2016 | IRENE CHIA |
| Permit | Cleared | 12/9/2016 | ERIK MUNOZ |
| Green Code | Cleared | 12/12/2016 | JIVAR AFSHAR |
| Low Impact Development | Cleared | 12/19/2016 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/19/2016 | ADRIAN SANCHEZ |
| Building over 3-story or 36-ft | Cleared | 2/15/2017 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 2/15/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/15/2017 | Andrew Santiago |
| Grading Pre-Inspection | Cleared | 2/15/2017 | Andrew Santiago |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Zweigler, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Zweigler, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/13/2018 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/28/2018 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/2/2018 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Piling/Pier/Caisson | 3/5/2018 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 3/6/2018 | Conditional Approval | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 11/30/2018 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 4/25/2019 | Partial Approval | RAYMOND KEHOE |
| Masonry Wall/Backfill | 5/6/2019 | Partial Approval | RAYMOND KEHOE |
| PLUMBING-Rough | 7/8/2019 | Not Ready for Inspection | RAYMOND KEHOE |
| Underground Mechanical | 7/9/2019 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 9/4/2019 | Partial Approval | RAYMOND KEHOE |
| Wood Frame | 3/10/2021 | No Access for Inspection | JOHN HAYES |
| Reinforced Concrete Frame | 5/18/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Shotcrete | 6/6/2022 | Conditional Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 6/7/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/24/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 6/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/12/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Gas Test | 4/3/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 4/3/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 4/27/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 9/1/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 9/1/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 9/12/2023 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 9/13/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 9/13/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Sewer | 9/14/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 9/14/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 9/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 10/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/20/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/20/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 1/17/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/17/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Final | 3/28/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/28/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 3/28/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 3/28/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/28/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/15/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Reinforced Concrete Frame | 4/15/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/15/2025 | Approved | CHRISTOPHE COCHRAN |