15329 W DE PAUW ST 90272

Certificate Information: 15329 W DE PAUW ST 90272

Application / Permit
16010-10000-02813
Plan Check / Job No.
B16LA09699
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCT A 3 STORY (INCLUDING MEZZANINE LEVEL) SINGLE FAMILY DWELLING WITH A BASEMENT.
Permit Issued
Issued on 12/6/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2016 APPLICANT
Assigned to Plan Check Engineer 7/21/2016 YOUNG KIM
Green Plans Picked Up 8/5/2016 APPLICANT
Corrections Issued 9/29/2016 YOUNG KIM
Quality Review Completed 10/11/2016 WING SUEN
Building Plans Picked Up 10/13/2016 APPLICANT
Applicant returned to address corrections 1/24/2018 YOUNG KIM
Applicant returned to address corrections 2/9/2018 YOUNG KIM
Applicant returned to address corrections 2/13/2018 YOUNG KIM
Applicant returned to address corrections 2/16/2018 YOUNG KIM
Applicant returned to address corrections 2/23/2018 YOUNG KIM
Applicant returned to address corrections 3/30/2018 YOUNG KIM
Applicant returned to address corrections 5/4/2018 YOUNG KIM
Applicant returned to address corrections 6/7/2018 YOUNG KIM
Plan Check Approved 11/14/2018 YOUNG KIM
Issued 12/6/2018 LADBS
CofO in Progress 7/11/2022 ANDREW NAVE
CofO in Progress 7/11/2022 ANDREW NAVE
Permit Finaled 7/12/2022 KENNETH NAGLE
CofO Issued 7/12/2022 KENNETH NAGLE
Permit Finaled 7/12/2022 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 2/6/2018 PHONG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/6/2018 PHONG NGUYEN
Permit Cleared 2/6/2018 PHONG NGUYEN
Roof/Waste drainage to street Cleared 2/6/2018 PHONG NGUYEN
Excavation more than 5-ft deep Cleared 2/9/2018 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/9/2018 YOUNG KIM
Sewer availability Cleared 2/14/2018 STEVEN JIN
GPI Written Notices Cleared 2/16/2018 YOUNG KIM
Hydrant and Access approval Cleared 3/23/2018 JOHN CONNEALLY
Coastal Zone Cleared 3/29/2018 NOAH MCCOY
Miscellaneous Cleared 3/29/2018 NOAH MCCOY
ZI Cleared 3/29/2018 NOAH MCCOY
Green Code Cleared 4/10/2018 JONATHAN QUACH
Low Impact Development Cleared 4/23/2018 SAM NAVID

Contact Information

Architect Olfati,, Ali; Lic. No.: C22217 5199 EAST PACIFIC COAST HWY # 611      LONG BEACH, CA 90804
Contractor Owner-Builder       ,
Engineer Kamboj,, Naresh Chander; Lic. No.: C21893 7838 QUIMBY AVE      CANOGA PARK, CA 91304
Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626
Geologist Zweigler,, Robert Ingraham; Lic. No.: EG1210 196 DIRT ROAD      THOUSAND OAKS, CA 91361

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2019 No Access for Inspection RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 4/10/2019 Not Ready for Inspection ANDREW NAVE
Piling/Pier/Caisson 4/10/2019 Not Ready for Inspection ANDREW NAVE
Pre-Inspection 4/10/2019 Approved ANDREW NAVE
Piling/Pier/Caisson 5/13/2019 Partial Inspection ANDREW NAVE
Deputy Reinf. Concrete 5/16/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 5/16/2019 Partial Approval ANDREW NAVE
Deputy Steel/Welding 6/3/2019 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 6/19/2019 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 6/20/2019 Conditional Approval MICHAEL TEMPLE
Deputy Steel/Welding 6/21/2019 No Access for Inspection ANDREW NAVE
Footing/Foundation/Slab 7/29/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 8/14/2019 Partial Approval DAVID FEILER
Deputy Steel/Welding 8/21/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 8/22/2019 Partial Approval ANDREW NAVE
Deputy Steel/Welding 8/28/2019 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 8/30/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 8/30/2019 Partial Approval ANDREW NAVE
Deputy Shotcrete 9/13/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 9/26/2019 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 9/30/2019 Partial Approval ANDREW NAVE
Deputy Shotcrete 10/1/2019 Conditional Approval ANDREW NAVE
PLUMBING-Rough 10/9/2019 Corrections Issued ANDREW NAVE
ELECTRICAL-Rough 10/15/2019 Partial Approval DAVID FEILER
Footing/Foundation/Slab 10/15/2019 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/15/2019 Partial Approval DAVID FEILER
Deputy Reinf. Concrete 10/21/2019 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 11/1/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 11/8/2019 Partial Approval DAVID FEILER
Deputy Reinf. Concrete 11/12/2019 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 11/13/2019 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 12/6/2019 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/6/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 12/12/2019 Approved ANDREW NAVE
Deputy Steel/Welding 1/6/2020 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 1/9/2020 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 1/30/2020 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 2/5/2020 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 5/13/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Corrections Issued ANDREW NAVE
Verify Sprinkler Sign Off 5/13/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 5/14/2020 Corrections Issued ANDREW NAVE
Deputy Wood Construction 5/21/2020 Conditional Approval ANDREW NAVE
Deputy Wood Construction 6/4/2020 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 6/25/2020 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Corrections Issued ANDREW NAVE
Interior/Exterior Lathing 7/8/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Corrections Issued ANDREW NAVE
PLUMBING-Rough 7/22/2020 Conditional Approval ANDREW NAVE
Sewer 7/22/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval ANDREW NAVE
Deputy Wood Construction 9/15/2020 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Approved ANDREW NAVE
Shower Pan 9/15/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 9/16/2020 Not Ready for Inspection ANDREW NAVE
Shower Pan 9/16/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 9/21/2020 Partial Inspection ANDREW NAVE
Interior/Exterior Lathing 9/30/2020 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 11/6/2020 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 11/12/2020 Not Ready for Inspection ANDREW NAVE
Green Building Rough 11/12/2020 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 11/12/2020 Corrections Issued ANDREW NAVE
Insulation 11/12/2020 Not Ready for Inspection ANDREW NAVE
Verify Sprinkler Sign Off 11/12/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 11/19/2020 Partial Inspection ANDREW NAVE
Green Building Rough 11/19/2020 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 11/30/2020 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 12/7/2020 Not Ready for Inspection ANDREW NAVE
Green Building Rough 12/7/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 12/7/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 12/15/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Approved ANDREW NAVE
PLUMBING-Rough 12/15/2020 Approved ANDREW NAVE
HVAC-Rough 1/14/2021 Conditional Approval ANDREW NAVE
Insulation 1/14/2021 Not Ready for Inspection ANDREW NAVE
Drywall Nailing 2/22/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 2/22/2021 Approved ANDREW NAVE
Drywall Nailing 3/24/2021 Partial Approval ANDREW NAVE
Drywall Nailing 4/1/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 4/1/2021 Partial Approval ANDREW NAVE
Drywall Nailing 4/6/2021 Partial Approval ANDREW NAVE
Gas Test 5/19/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 5/19/2021 Approved ANDREW NAVE
Underground Mechanical 5/19/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 6/2/2021 Partial Inspection ANDREW NAVE
Underground Mechanical 6/2/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 6/9/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 11/19/2021 Approved ANDREW NAVE
ELECTRICAL-Final 12/23/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 3/15/2022 Corrections Issued ANDREW NAVE
HVAC-Final 3/17/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 3/18/2022 Corrections Issued ANDREW NAVE
Gas Test 3/18/2022 Approved ANDREW NAVE
HVAC-Final 3/18/2022 Approved ANDREW NAVE
PLUMBING-Final 3/18/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 3/31/2022 Approved ANDREW NAVE
Green Building Final 4/6/2022 Corrections Issued ANDREW NAVE
Service/Power Release 4/6/2022 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 4/6/2022 Approved ANDREW NAVE
Service/Power Release 4/12/2022 Approved ANDREW NAVE
Green Building Final 4/26/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/31/2022 Approved ANDREW NAVE
Drywall Nailing 5/31/2022 Approved ANDREW NAVE
Final 5/31/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved ANDREW NAVE
Structural Steel Frame 5/31/2022 Approved ANDREW NAVE
Special/Order Compliance 6/15/2022 Corrections Issued ANDREW NAVE
Final 6/29/2022 Corrections Issued ANDREW NAVE
Final 7/11/2022 OK to Issue CofO ANDREW NAVE
PLUMBING-Final 7/11/2022 Approved ANDREW NAVE
Special/Order Compliance 7/11/2022 Approved ANDREW NAVE