Pre-Inspection
|
1/24/2019
|
No Access for Inspection
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
4/10/2019
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Piling/Pier/Caisson
|
4/10/2019
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Pre-Inspection
|
4/10/2019
|
Approved
|
ANDREW NAVE
|
|
Piling/Pier/Caisson
|
5/13/2019
|
Partial Inspection
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
5/16/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
5/16/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
6/3/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
6/19/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
6/20/2019
|
Conditional Approval
|
MICHAEL TEMPLE
|
|
Deputy Steel/Welding
|
6/21/2019
|
No Access for Inspection
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
7/29/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
8/14/2019
|
Partial Approval
|
DAVID FEILER
|
|
Deputy Steel/Welding
|
8/21/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
8/22/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
8/28/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
8/30/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
8/30/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Shotcrete
|
9/13/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
9/26/2019
|
Partial Inspection
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
9/30/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Shotcrete
|
10/1/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
10/9/2019
|
Corrections Issued
|
ANDREW NAVE
|
|
ELECTRICAL-Rough
|
10/15/2019
|
Partial Approval
|
DAVID FEILER
|
|
Footing/Foundation/Slab
|
10/15/2019
|
Partial Inspection
|
DAVID FEILER
|
|
PLUMBING-Rough
|
10/15/2019
|
Partial Approval
|
DAVID FEILER
|
|
Deputy Reinf. Concrete
|
10/21/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
11/1/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
11/8/2019
|
Partial Approval
|
DAVID FEILER
|
|
Deputy Reinf. Concrete
|
11/12/2019
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
11/13/2019
|
Partial Approval
|
DAVID FEILER
|
|
BUILDING-Rough-Frame
|
12/6/2019
|
Corrections Issued
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
12/6/2019
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
12/12/2019
|
Approved
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
1/6/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
1/9/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
1/30/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
2/5/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/13/2020
|
Partial Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2020
|
Partial Approval
|
ANDREW NAVE
|
|
BUILDING-Rough-Frame
|
5/13/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2020
|
Corrections Issued
|
ANDREW NAVE
|
|
Verify Sprinkler Sign Off
|
5/13/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
HVAC-Rough
|
5/14/2020
|
Corrections Issued
|
ANDREW NAVE
|
|
Deputy Wood Construction
|
5/21/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Wood Construction
|
6/4/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
ELECTRICAL-Rough
|
6/25/2020
|
Approved
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2020
|
Corrections Issued
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
7/8/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/22/2020
|
Corrections Issued
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
7/22/2020
|
Conditional Approval
|
ANDREW NAVE
|
|
Sewer
|
7/22/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/4/2020
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Wood Construction
|
9/15/2020
|
Approved
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/15/2020
|
Approved
|
ANDREW NAVE
|
|
Shower Pan
|
9/15/2020
|
Approved
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
9/16/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Shower Pan
|
9/16/2020
|
Approved
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
9/21/2020
|
Partial Inspection
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
9/30/2020
|
Partial Approval
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
11/6/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
BUILDING-Rough-Frame
|
11/12/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Green Building Rough
|
11/12/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
HVAC-Rough
|
11/12/2020
|
Corrections Issued
|
ANDREW NAVE
|
|
Insulation
|
11/12/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Verify Sprinkler Sign Off
|
11/12/2020
|
Approved
|
ANDREW NAVE
|
|
BUILDING-Rough-Frame
|
11/19/2020
|
Partial Inspection
|
ANDREW NAVE
|
|
Green Building Rough
|
11/19/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
11/30/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
BUILDING-Rough-Frame
|
12/7/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Green Building Rough
|
12/7/2020
|
Approved
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
12/7/2020
|
Partial Approval
|
ANDREW NAVE
|
|
BUILDING-Rough-Frame
|
12/15/2020
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/15/2020
|
Approved
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
12/15/2020
|
Approved
|
ANDREW NAVE
|
|
HVAC-Rough
|
1/14/2021
|
Conditional Approval
|
ANDREW NAVE
|
|
Insulation
|
1/14/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Drywall Nailing
|
2/22/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
HVAC-Rough
|
2/22/2021
|
Approved
|
ANDREW NAVE
|
|
Drywall Nailing
|
3/24/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Drywall Nailing
|
4/1/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Interior/Exterior Lathing
|
4/1/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Drywall Nailing
|
4/6/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Gas Test
|
5/19/2021
|
Partial Approval
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
5/19/2021
|
Approved
|
ANDREW NAVE
|
|
Underground Mechanical
|
5/19/2021
|
Partial Approval
|
ANDREW NAVE
|
|
ELECTRICAL-Rough
|
6/2/2021
|
Partial Inspection
|
ANDREW NAVE
|
|
Underground Mechanical
|
6/2/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
6/9/2021
|
Partial Approval
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
11/19/2021
|
Approved
|
ANDREW NAVE
|
|
ELECTRICAL-Final
|
12/23/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
ELECTRICAL-Final
|
3/15/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
HVAC-Final
|
3/17/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
ELECTRICAL-Final
|
3/18/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Gas Test
|
3/18/2022
|
Approved
|
ANDREW NAVE
|
|
HVAC-Final
|
3/18/2022
|
Approved
|
ANDREW NAVE
|
|
PLUMBING-Final
|
3/18/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
ELECTRICAL-Final
|
3/31/2022
|
Approved
|
ANDREW NAVE
|
|
Green Building Final
|
4/6/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Service/Power Release
|
4/6/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Smoke Detectors
|
4/6/2022
|
Approved
|
ANDREW NAVE
|
|
Service/Power Release
|
4/12/2022
|
Approved
|
ANDREW NAVE
|
|
Green Building Final
|
4/26/2022
|
Approved
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
5/31/2022
|
Approved
|
ANDREW NAVE
|
|
Drywall Nailing
|
5/31/2022
|
Approved
|
ANDREW NAVE
|
|
Final
|
5/31/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
SGSOV-Seismic Gas S/O Valve
|
5/31/2022
|
SGSOV Approved
|
ANDREW NAVE
|
|
Structural Steel Frame
|
5/31/2022
|
Approved
|
ANDREW NAVE
|
|
Special/Order Compliance
|
6/15/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Final
|
6/29/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Final
|
7/11/2022
|
OK to Issue CofO
|
ANDREW NAVE
|
|
PLUMBING-Final
|
7/11/2022
|
Approved
|
ANDREW NAVE
|
|
Special/Order Compliance
|
7/11/2022
|
Approved
|
ANDREW NAVE
|