4454 N SUNNYCREST DR 90065

Certificate Information: 4454 N SUNNYCREST DR 90065

Application / Permit
16010-10000-02798
Plan Check / Job No.
B16LA09637
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH 2 CAR GARAGE, REAR DECKS-SPLT LEVEL, STREET WIDENING-HILLSIDE
Permit Issued
Issued on 6/10/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2016 APPLICANT
Assigned to Plan Check Engineer 8/4/2016 KRIKOR MANOUKIAN
Corrections Issued 8/6/2016 KRIKOR MANOUKIAN
Quality Review Completed 8/26/2016 CHIU TAM
Building Plans Picked Up 9/12/2016 APPLICANT
Green Plans Picked Up 9/12/2016 APPLICANT
Applicant returned to address corrections 5/22/2017 KRIKOR MANOUKIAN
Applicant returned to address corrections 12/31/2018 KAVIAN REFAHI
Plan Check Approved 1/10/2019 KAVIAN REFAHI
Issued 6/10/2019 LADBS
CofO in Progress 8/8/2023 CRAIG VAUGHAN
CofO Issued 8/8/2023 RONALD MYRICK
Permit Finaled 8/8/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 5/22/2017 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 5/22/2017 RAVIL MANAPOV
Green Code Cleared 5/22/2017 MICKEY YAMASHITA
Grading Pre-Inspection Cleared 6/13/2017 KRIKOR MANOUKIAN
Excavation more than 5-ft deep Cleared 6/27/2017 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 7/11/2017 ROCHELLE DUNGCA
Sewer availability Cleared 7/11/2017 ROCHELLE DUNGCA
GPI Written Notices Cleared 8/2/2017 KRIKOR MANOUKIAN
Hydrant and Access approval Cleared 8/17/2018 JOHN CONNEALLY
BHO/Hillside ordinance Cleared 8/27/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 8/27/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 8/27/2018 NAZILA NOORIFAR
Permit Cleared 8/27/2018 NAZILA NOORIFAR
Roof/Waste drainage to street Cleared 8/27/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 11/30/2018 STEVE MELGAR
Low Impact Development Cleared 12/28/2018 MARTIN FRAGOSO
Supp. Use District POD/CDO/TDO Cleared 1/8/2019 LATANYA ROUX
ZA Case Cleared 1/8/2019 LATANYA ROUX

Contact Information

Contractor Next Construction Inc; Lic. No.: 1049511-B 13902 HARBOR BLVD #2A      GARDEN GROVE, CA 92843
Engineer , ; Lic. No.: C86223 1840 S GAFFEY ST   382    SAN PEDRO, CA 90731
Engineer Zhang, Jiefu; Lic. No.: S5270 1205 SOUTH 4TH ST      ALHAMBRA, CA 91801
Geologist Farrell, Keith Gregory; Lic. No.: EG1314 501 VALIDO ROAD      ARCADIA, CA 91007

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2019 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 7/30/2019 Corrections Issued RUBEN SALAS
Grading Pre-Inspection 8/9/2019 Partial Inspection CRAIG VAUGHAN
Pre-Inspection 8/9/2019 Partial Inspection CRAIG VAUGHAN
Deputy Reinf. Concrete 10/16/2019 No Access for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 11/1/2019 Corrections Issued CRAIG VAUGHAN
Piling/Pier/Caisson 11/6/2019 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 11/13/2019 No Access for Inspection CRAIG VAUGHAN
Deputy Reinf. Concrete 11/14/2019 Approved MICHAEL FAUNCE
Deputy Drilled-In Anchors 1/7/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/7/2020 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 1/28/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/28/2020 Partial Approval CRAIG VAUGHAN
Deputy Other (see comments) 1/30/2020 No Access for Inspection CRAIG VAUGHAN
Deputy Shotcrete 1/30/2020 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval CRAIG VAUGHAN
Insulation 2/12/2020 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval RUBEN SALAS
Special/Order Compliance 2/24/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 3/12/2020 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 No Access for Inspection CRAIG VAUGHAN
Green Building Rough 3/12/2020 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/12/2020 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2020 Partial Approval CRAIG VAUGHAN
Wood Frame 3/16/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 3/23/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/25/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/25/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 4/22/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval CRAIG VAUGHAN
Deck 5/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 5/14/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/11/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Deck 6/24/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/24/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 6/24/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 6/24/2020 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 6/24/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/9/2020 Not Ready for Inspection CRAIG VAUGHAN
Deck 7/9/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/9/2020 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 7/9/2020 Approved CRAIG VAUGHAN
Green Building Rough 7/9/2020 Approved CRAIG VAUGHAN
Grounding or Bonding 7/9/2020 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/9/2020 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/9/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 7/14/2020 Approved CRAIG VAUGHAN
Deck 7/14/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 7/14/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/14/2020 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/14/2020 Approved CRAIG VAUGHAN
HVAC-Rough 7/16/2020 Not Ready for Inspection COREY HUPP
HVAC-Rough 7/16/2020 Off-Hour Fees Due
Insulation 7/16/2020 Approved COREY HUPP
Insulation 7/16/2020 Off-Hour Fees Due
Drywall Nailing 7/22/2020 Approved COREY HUPP
Deck 7/24/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 7/24/2020 Approved CRAIG VAUGHAN
Pre-Inspection 8/3/2021 Partial Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 2/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 2/23/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/18/2022 Not Ready for Inspection JOSEPH MCGARRY
Pre-Inspection 3/18/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Final 7/7/2022 Not Ready for Inspection AMY COLIN
Sewer 7/7/2022 Approved AMY COLIN
Special/Order Compliance 7/7/2022 Approved AMY COLIN
Service/Power Release 2/27/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 4/6/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/6/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/11/2023 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/26/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/26/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/25/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/1/2023 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 6/5/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 6/5/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 6/5/2023 Approved CRAIG VAUGHAN
HVAC-Final 6/6/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 6/8/2023 Approved CRAIG VAUGHAN
HVAC-Final 6/8/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 6/8/2023 Approved CRAIG VAUGHAN
Final 8/7/2023 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 8/7/2023 Approved CRAIG VAUGHAN
Green Building Final 8/7/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 8/7/2023 Approved CRAIG VAUGHAN
Smoke Detectors 8/7/2023 Approved CRAIG VAUGHAN