5819 W CAZAUX DR 90068

Certificate Information: 5819 W CAZAUX DR 90068

Application / Permit
16010-10000-02665
Plan Check / Job No.
B16LA09153
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 12/8/2017
Issuing Office
Metro
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2016 APPLICANT
Assigned to Plan Check Engineer 7/14/2016 NEGAR NEJAD
Green Plans Picked Up 7/25/2016 APPLICANT
Corrections Issued 7/29/2016 NEGAR NEJAD
Quality Review Completed 8/9/2016 BILL STUTSMAN
Building Plans Picked Up 9/9/2016 APPLICANT
Applicant returned to address corrections 10/28/2016 NEGAR NEJAD
Applicant returned to address corrections 11/9/2016 NEGAR NEJAD
Applicant returned to address corrections 7/12/2017 NEGAR NEJAD
Applicant returned to address corrections 9/22/2017 NEGAR NEJAD
Applicant returned to address corrections 10/26/2017 NEGAR NEJAD
Plan Check Approved 12/8/2017 NEGAR NEJAD
Issued 12/8/2017 LADBS
CofO in Progress 11/11/2023 JOAQUIN GREENOUGH
CofO Issued 11/17/2023 DEROLD HAUFF
Permit Finaled 11/17/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2017 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 1/6/2017 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 1/6/2017 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 1/6/2017 ROCHELLE DUNGCA
"D" conditions Cleared 1/9/2017 AZEEN KHANMALEK
ZI Cleared 1/9/2017 AZEEN KHANMALEK
CPC Cleared 1/11/2017 AZEEN KHANMALEK
CPC Cleared 1/11/2017 AZEEN KHANMALEK
CPC Cleared 1/11/2017 AZEEN KHANMALEK
Miscellaneous Cleared 1/11/2017 AZEEN KHANMALEK
Miscellaneous Cleared 1/11/2017 AZEEN KHANMALEK
Work Adjacent to Public Way Cleared 1/11/2017 RAVIL MANAPOV
ZI Cleared 1/11/2017 AZEEN KHANMALEK
Eng Process Fee Ord 176,300 Cleared 1/13/2017 ADRIAN SANCHEZ
Sewer availability Cleared 1/17/2017 SEVAK ISAKHAYAN
BHO/Hillside ordinance Cleared 2/28/2017 CELINA MORENO
Miscellaneous Cleared 2/28/2017 CELINA MORENO
Miscellaneous Cleared 2/28/2017 TERRY PHAN
Permit Cleared 2/28/2017 CELINA MORENO
Disturb/Remove Protected Trees Cleared 3/1/2017 LUIS TORRES
Green Code Cleared 8/28/2017 JIVAR AFSHAR
Hydrant and Access approval Cleared 10/20/2017 JOHN CONNEALLY
Low Impact Development Cleared 10/20/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/20/2017 JAMES KHO
Excavation more than 5-ft deep Cleared 10/26/2017 CALOSHA APPROVED
GPI Written Notices Cleared 10/26/2017 NEGAR NEJAD
Grading Pre-Inspection Cleared 10/26/2017 NEGAR NEJAD

Contact Information

Architect Andrew, Liang; Lic. No.: C35850       ,
Contractor Owner-Builder       ,
Engineer Baad, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Faul, James David; Lic. No.: C52258 6473 TREFOIL AVE      OAK PARK, CA 91377
Engineer Salter, David R; Lic. No.: C69911 2323 28TH ST      SANTA MONICA, CA 90405
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Gladson, Richard; Lic. No.: EG1758 1545 VICTORY BL      GLENDALE, CA 91201

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2019 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 6/10/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 7/15/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 7/15/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 7/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Grounding or Bonding 7/15/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 7/15/2020 Partial Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 7/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 7/17/2020 Conditional Approval ROBERT CORNELL
Pre-Inspection 8/4/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 9/9/2020 Not Ready for Inspection BRIAN SULLIVAN
Insulation 9/9/2020 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 9/9/2020 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/9/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/10/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/8/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 11/10/2020 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 11/10/2020 Partial Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 11/10/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/17/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 1/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 2/24/2021 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 2/24/2021 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 2/24/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 6/9/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/9/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 8/12/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 8/12/2021 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 8/12/2021 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/12/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 10/15/2021 Partial Approval CRAIG DAVIS
Green Building Rough 10/15/2021 Not Ready for Inspection CRAIG DAVIS
Reinforced Concrete Frame 10/15/2021 Partial Approval CRAIG DAVIS
Verify Sprinkler Sign Off 10/15/2021 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 2/16/2022 Partial Approval BRIAN SULLIVAN
Green Building Rough 2/16/2022 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 2/16/2022 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 2/16/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 3/29/2022 Not Ready for Inspection CRAIG DAVIS
Reinforced Concrete Frame 3/29/2022 Partial Approval CRAIG DAVIS
Verify Sprinkler Sign Off 3/29/2022 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 5/5/2022 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 5/6/2022 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 8/2/2022 Partial Approval RYAN SALAZAR
Green Building Rough 8/2/2022 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 8/2/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 8/2/2022 Partial Approval RYAN SALAZAR
Reinforced Concrete Frame 8/2/2022 Partial Approval RYAN SALAZAR
Verify Sprinkler Sign Off 8/2/2022 Partial Approval RYAN SALAZAR
Sewer 8/19/2022 Approved STUART CHAPMAN
Green Building Rough 9/1/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/1/2022 Partial Approval BRIAN SULLIVAN
Reinforced Concrete Frame 9/1/2022 Corrections Issued BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/1/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Conditional Approval JOAQUIN GREENOUGH
Shower Pan 10/4/2022 Approved JOAQUIN GREENOUGH
Reinforced Masonry Frame 10/12/2022 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 11/14/2022 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 1/4/2023 Approved JOAQUIN GREENOUGH
Reinforced Masonry Frame 1/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 1/17/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 2/16/2023 Partial Approval RAUL BARAJAS
Insulation 2/16/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 2/28/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 2/28/2023 Approved BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 2/28/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/3/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 4/7/2023 Partial Approval JOAQUIN GREENOUGH
Insulation 4/7/2023 Partial Approval JOAQUIN GREENOUGH
Service/Power Release 4/7/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 4/25/2023 Approved JOAQUIN GREENOUGH
Special/Order Compliance 4/25/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/5/2023 Approved JOAQUIN GREENOUGH
Insulation 6/5/2023 Partial Approval JOAQUIN GREENOUGH
Insulation 8/29/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Final 9/15/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved JOAQUIN GREENOUGH
Verify Rec and Parks Fee Memo 9/15/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 9/22/2023 Approved JOAQUIN GREENOUGH
HVAC-Final 10/16/2023 Approved JOAQUIN GREENOUGH
Final 11/1/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/1/2023 Approved JOAQUIN GREENOUGH
Green Building Final 11/1/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 11/1/2023 Approved JOAQUIN GREENOUGH
Reinforced Concrete Frame 11/1/2023 Approved JOAQUIN GREENOUGH
Smoke Detectors 11/1/2023 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 11/1/2023 Approved JOAQUIN GREENOUGH
Final 11/6/2023 Conditional Approval JOAQUIN GREENOUGH
Final 11/11/2023 OK to Issue CofO JOAQUIN GREENOUGH