8404 N WOODLEY PL Unit #8 91343

Certificate Information: 8404 N WOODLEY PL Unit #8 91343

Application / Permit
16010-10000-02569
Plan Check / Job No.
B16LA08797
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Three story SFD with attached garage(PLAN 1A) Small lot subdivision pursuant to Tentative Tract Map No. 72747-SL. A cerfiticate of occupancy(temporary or final) shall not be issued under after the final map has been recorded.
Permit Issued
Issued on 7/19/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2016 APPLICANT
Assigned to Plan Check Engineer 6/30/2016 STEVEN KIM
Corrections Issued 7/6/2016 STEVEN KIM
Quality Review Completed 7/7/2016 TIEN JEN WANG
Building Plans Picked Up 7/11/2016 APPLICANT
Green Plans Picked Up 7/20/2016 APPLICANT
Applicant returned to address corrections 10/18/2016 STEVEN KIM
Applicant returned to address corrections 3/1/2017 STEVEN KIM
Applicant returned to address corrections 3/20/2017 STEVEN KIM
Applicant returned to address corrections 3/22/2017 STEVEN KIM
Plan Check Approved 3/23/2017 STEVEN KIM
Issued 7/19/2017 LADBS
CofO in Progress 7/2/2021 JOSEPH SAGEN
CofO Issued 7/14/2021 MICHAEL SMITH
Permit Finaled 7/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/12/2016 ARNULFO NUNO
Eng Process Fee Ord 176,300 Cleared 7/12/2016 ARNULFO NUNO
Hydrant and Access approval Cleared 7/15/2016 ROBERT DUFF
Miscellaneous Cleared 7/18/2016 COLLINS ALLAN
Highway dedication Cleared 9/7/2016 RICHARD SOUTHERLAND
Sewer availability Cleared 9/19/2016 ARNULFO NUNO
Miscellaneous Cleared 12/20/2016 JAMES KHO
Low Impact Development Cleared 1/5/2017 AYMAN JABBOURI
Tract Map conditions Cleared 1/12/2017 TRACY WILLIAMS
Roof/Waste drainage to street Cleared 3/2/2017 IRENE CHIA
Permit Cleared 3/7/2017 LEE GUILBEAUX
"Q" conditions Cleared 3/16/2017 TREVOR MARTIN
Green Code Cleared 3/16/2017 DAVID MATSON
Green Code Cleared 3/16/2017 DAVID MATSON
Miscellaneous Cleared 3/16/2017 TREVOR MARTIN
"T" removal Cleared 3/22/2017 TREVOR MARTIN
APC Cleared 3/22/2017 TREVOR MARTIN

Contact Information

Contractor G B U Construction Inc; Lic. No.: 983852-B 24009 VENTURA BLVD   STE, 200    HIDDEN HILLS, CA 91302
Engineer Babayan, Raffi Samuel; Lic. No.: C72168 1140 N COLUMBUS AVE 112      GLENDALE, CA 91202
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/13/2018 Corrections Issued DONALD SUNSERI
Underground Mechanical 3/14/2018 Approved DONALD SUNSERI
Footing/Foundation/Slab 4/4/2018 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 4/20/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/23/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/24/2018 Not Ready for Inspection BRUCE ROZAK
Interior/Exterior Lathing 4/24/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/30/2018 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 5/3/2018 Partial Approval BRUCE ROZAK
Drywall Nailing 5/7/2018 Not Ready for Inspection BRUCE ROZAK
Green Building Rough 5/7/2018 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/8/2018 Partial Approval BRUCE ROZAK
Interior/Exterior Lathing 5/9/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/18/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/24/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/29/2018 Not Ready for Inspection BRUCE ROZAK
Drywall Nailing 5/30/2018 Partial Approval BRUCE ROZAK
Underground Mechanical 5/31/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/18/2018 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/9/2018 Approved DONALD SUNSERI
PLUMBING-Rough 10/9/2018 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 10/31/2018 Partial Approval DONALD SUNSERI
Green Building Rough 10/31/2018 Not Ready for Inspection DONALD SUNSERI
HVAC-Rough 10/31/2018 Not Ready for Inspection DONALD SUNSERI
Verify Sprinkler Sign Off 10/31/2018 Not Ready for Inspection DONALD SUNSERI
Wood Frame 11/14/2018 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/17/2018 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 12/17/2018 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 12/17/2018 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/17/2018 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 12/17/2018 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/24/2018 Approved JOHN KIDWELL
Green Building Rough 12/24/2018 Approved JOHN KIDWELL
HVAC-Rough 12/24/2018 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/24/2018 Approved JOHN KIDWELL
Drywall Nailing 1/14/2019 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/14/2019 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 1/18/2019 Approved JOHN KIDWELL
PLUMBING-Rough 1/25/2019 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 1/28/2019 Not Ready for Inspection JOHN KIDWELL
Shower Pan 1/28/2019 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/28/2019 Approved DONALD SUNSERI
Underground Mechanical 2/4/2020 Not Ready for Inspection JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 3/2/2020 SGSOV Not Ready JOSEPH SAGEN
Smoke Detectors 3/2/2020 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 3/6/2020 No Access for Inspection JOSEPH SAGEN
PLUMBING-Final 3/6/2020 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 3/9/2020 Not Ready for Inspection DONALD SUNSERI
PLUMBING-Final 3/9/2020 Not Ready for Inspection DONALD SUNSERI
Gas Test 4/23/2020 Partial Approval JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 4/23/2020 SGSOV Not Ready JOSEPH SAGEN
Gas Test 4/27/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 4/27/2020 SGSOV Approved JOSEPH SAGEN
Service/Power Release 5/14/2020 Approved SEAN WIRCH
ELECTRICAL-Final 12/4/2020 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 12/4/2020 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 12/4/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 6/16/2021 Approved JOSEPH SAGEN
Green Building Final 6/16/2021 Approved JOSEPH SAGEN
Smoke Detectors 6/16/2021 Not Ready for Inspection JOSEPH SAGEN
Final 7/1/2021 OK to Issue CofO JOSEPH SAGEN
HVAC-Final 7/1/2021 Approved JOSEPH SAGEN
Smoke Detectors 7/1/2021 Approved JOSEPH SAGEN