14623 W SUTTON ST 91403
Certificate Information: 14623 W SUTTON ST 91403
- Application / Permit
- 16010-10000-02221
- Plan Check / Job No.
- B16LA07745
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- DETACHED ACCESSORY LIVING QUARTERS (13'3" x 19'6") WITH ATTACHED TRELLIS (19'0" x 35'0")
- Permit Issued
- Issued on 12/13/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2016 | APPLICANT |
| Green Plans Picked Up | 6/20/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2016 | PRANITA SHAH |
| Corrections Issued | 7/6/2016 | PRANITA SHAH |
| Quality Review Completed | 7/13/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 7/15/2016 | APPLICANT |
| Applicant returned to address corrections | 11/21/2017 | PRANITA SHAH |
| Applicant returned to address corrections | 5/30/2018 | PRANITA SHAH |
| Applicant returned to address corrections | 6/19/2018 | PRANITA SHAH |
| Plan Check Approved | 12/5/2018 | PRANITA SHAH |
| Issued | 12/13/2018 | LADBS |
| CofO in Progress | 4/17/2026 | MICHAEL CORTEZ |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Green Code | Cleared | 5/14/2018 | ALDO UBAU |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/13/2018 | GILBERT URREA |
| Sewer availability | Cleared | 8/13/2018 | LEE GUILBEAUX |
| Green Code | Cleared | 10/10/2018 | PRANITA SHAH |
| Low Impact Development | Cleared | 10/10/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 10/10/2018 | JEANETTE VONG |
| Construction near power lines | Cleared | 11/30/2018 | RIDWAN HARDY |
Contact Information
| Contractor | Roth Craig D; Lic. No.: 1006385-B | 602 ROSARIO DRIVE THOUSAND OAKS, CA 91362 |
| Engineer | Namvar, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/18/2018 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 1/24/2019 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/1/2019 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2019 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 9/9/2020 | Approved | CHARLES POWELL |
| HVAC-Rough | 9/9/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 9/9/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 9/17/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 9/17/2020 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 9/17/2020 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 9/17/2020 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 10/15/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 10/15/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 10/15/2020 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 10/15/2020 | Approved | CHARLES POWELL |
| Underground Mechanical | 10/15/2020 | Corrections Issued | CHARLES POWELL |
| Verify Sprinkler Sign Off | 10/15/2020 | Approved | CHARLES POWELL |
| Insulation | 11/2/2020 | Not Ready for Inspection | DAVID MATSON |
| Insulation | 11/9/2020 | Approved | CHARLES POWELL |
| Underground Mechanical | 11/9/2020 | Approved | CHARLES POWELL |
| HVAC-Rough | 1/5/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 3/10/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 3/10/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 9/10/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 10/10/2024 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/17/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 1/15/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/17/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 6/26/2025 | Approved | JACK KARGODORIAN |
| Final | 3/6/2026 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 3/6/2026 | No Access for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 3/6/2026 | No Access for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/6/2026 | No Access for Inspection | MISAEL ESPARZA |
| Final | 3/10/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 3/10/2026 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | MICHAEL CORTEZ |
| Smoke Detectors | 3/10/2026 | Corrections Issued | MICHAEL CORTEZ |
| Special/Order Compliance | 3/10/2026 | Corrections Issued | MICHAEL CORTEZ |
| Final | 4/17/2026 | OK to Issue CofO | MICHAEL CORTEZ |
| Service/Power Release | 4/17/2026 | Approved | MICHAEL CORTEZ |
| Smoke Detectors | 4/17/2026 | Approved | MICHAEL CORTEZ |