Pre-Inspection
|
6/21/2018
|
Partial Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/15/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
8/15/2018
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
8/15/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
8/15/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
8/27/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/30/2018
|
Approved
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/31/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/4/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
9/4/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/18/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2018
|
Approved
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
9/20/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
9/25/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
9/25/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
9/26/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
9/26/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
9/28/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
9/28/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
9/28/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/28/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
10/1/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
10/1/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
10/4/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
10/5/2018
|
Approved
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
10/15/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
10/17/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
10/22/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
10/23/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
10/29/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
10/30/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
11/1/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
11/20/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
11/20/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/3/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/3/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/4/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/5/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/5/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/10/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/13/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2018
|
No Access for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
12/20/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/21/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
1/2/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/2/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
1/10/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
1/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/24/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
1/25/2019
|
Approved
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
2/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
2/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
2/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
2/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
3/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
3/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
3/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
3/11/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
3/14/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
3/14/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
3/14/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
3/14/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
4/1/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/1/2019
|
Partial Approval
|
LARRY ARNICK
|
|
METHANE-Rough
|
4/1/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/1/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/1/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/5/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
4/5/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
4/5/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/5/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/5/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/19/2019
|
Approved
|
LARRY ARNICK
|
|
Green Building Rough
|
4/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
METHANE-Rough
|
4/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/19/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/22/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
4/25/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
4/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/17/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
5/17/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
5/17/2019
|
Order to Comply Issued
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
6/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/14/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
6/14/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/21/2019
|
Partial Inspection
|
LESLIE TRUJILLO
|
|
Green Building Rough
|
6/21/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
6/26/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
6/26/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/28/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
6/28/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
6/28/2019
|
Approved
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/28/2019
|
Approved
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/10/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
7/10/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/15/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
7/15/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/23/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
7/23/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/12/2019
|
Approved
|
LARRY ARNICK
|
|
Green Building Rough
|
8/12/2019
|
Approved
|
LARRY ARNICK
|
|
Final
|
12/9/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
12/9/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Final
|
12/9/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
12/9/2019
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
12/9/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
12/9/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Final
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Final
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
METHANE-Barrier
|
12/23/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
METHANE-Final
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
METHANE-Rough
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
METHANE-Subgrade
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Reinforced Masonry Frame
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
SGSOV-Seismic Gas S/O Valve
|
12/23/2019
|
SGSOV Not Ready
|
DANIEL MC AULIFFE
|
|
Smoke Detectors
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Structural Steel Frame
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Verify Sprinkler Sign Off
|
12/23/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
12/23/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Final
|
12/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
12/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Final
|
12/24/2019
|
Approved
|
LARRY ARNICK
|
|
METHANE-Barrier
|
12/24/2019
|
Approved
|
LARRY ARNICK
|
|
METHANE-Final
|
12/24/2019
|
Approved
|
LARRY ARNICK
|
|
METHANE-Rough
|
12/24/2019
|
Approved
|
LARRY ARNICK
|
|
METHANE-Subgrade
|
12/24/2019
|
Approved
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
12/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
12/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
12/24/2019
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
12/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Structural Steel Frame
|
12/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
12/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
12/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Pre-Inspection
|
1/6/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/15/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Wood Frame
|
1/15/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Final
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
2/19/2020
|
Approved
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
2/19/2020
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
2/19/2020
|
Approved
|
LARRY ARNICK
|
|
Structural Steel Frame
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
2/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
3/11/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
3/11/2020
|
Approved
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
3/11/2020
|
Approved
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
3/11/2020
|
SGSOV Approved
|
LARRY ARNICK
|
|
Structural Steel Frame
|
3/11/2020
|
Approved
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
3/11/2020
|
Approved
|
LARRY ARNICK
|
|
Wood Frame
|
3/11/2020
|
Approved
|
LARRY ARNICK
|
|
Final
|
3/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
3/24/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Final
|
4/6/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
9/4/2020
|
Conditional Approval
|
LARRY ARNICK
|