1127 S SPAULDING AVE 90019

Certificate Information: 1127 S SPAULDING AVE 90019

Application / Permit
16010-10000-02146
Plan Check / Job No.
B16LA07400
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY APARTMENT BUILDING WITH SUBTERRANEAN PRIVATE GARAGE. 35% DENSITY BONUS SETTING ASIDE ONE UNIT (11% OF BASE DENSITY OF 9 UNITS) FOR VERY LOW INCOME HOUSEHOLD.
Permit Issued
Issued on 4/11/2018
Issuing Office
Valley
Current Status
CofO Issued on 9/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2016 APPLICANT
Disabled Access Plans Picked Up 6/22/2016 APPLICANT
Assigned to Plan Check Engineer 6/30/2016 RODNEY SAMIIAN
Corrections Issued 7/12/2016 RODNEY SAMIIAN
Quality Review Completed 7/14/2016 ABDUL CHEGENI
Building Plans Picked Up 7/18/2016 APPLICANT
Green Plans Picked Up 8/15/2016 APPLICANT
Applicant returned to address corrections 1/25/2017 RODNEY SAMIIAN
Applicant returned to address corrections 4/27/2017 RODNEY SAMIIAN
Applicant returned to address corrections 5/5/2017 RODNEY SAMIIAN
Applicant returned to address corrections 8/8/2017 RODNEY SAMIIAN
Applicant returned to address corrections 8/23/2017 RODNEY SAMIIAN
Applicant returned to address corrections 9/14/2017 RODNEY SAMIIAN
Applicant returned to address corrections 10/19/2017 RODNEY SAMIIAN
Plan Check Approved 3/8/2018 RODNEY SAMIIAN
Issued 4/11/2018 LADBS
TCO Issued (Expire Date: 09-27-2020) 3/31/2020 DAVID TSAU
CofO in Progress 4/21/2020 LARRY ARNICK
Permit Finaled 9/17/2020 TERRY HERR
CofO Issued 9/17/2020 TERRY HERR
Permit Finaled 9/17/2020 TERRY HERR

Permit Application Clearance Information

Address approval Cleared 7/22/2016 VALENTINO PUEBLOS
Eng Process Fee Ord 176,300 Cleared 7/22/2016 VALENTINO PUEBLOS
Construction within easement Cleared 8/5/2016 LUCIO FERRER
Highway dedication Cleared 1/17/2017 RAVIL MANAPOV
Housing density bonus Cleared 5/4/2017 LOUIE MILLER
DAS Clearance Cleared 7/21/2017 SHINE LIN
Green Code Cleared 7/26/2017 DONALD CRICHLOW
Hydrant and Access approval Cleared 8/24/2017 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 9/25/2017 ANDREW KO
Frnt yard landscape/Water mgmt Cleared 10/10/2017 ERIC CLAROS
Miscellaneous Cleared 10/10/2017 ERIC CLAROS
Opn space landscape/Water mgmt Cleared 10/10/2017 ERIC CLAROS
ZI Cleared 10/10/2017 ERIC CLAROS
Excavation more than 5-ft deep Cleared 10/19/2017 CALOSHA APPROVED
Permit Cleared 2/8/2018 ADRIAN SANCHEZ
Sewer availability Cleared 2/8/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 2/12/2018 SAM NAVID
Work Adjacent to Public Way Cleared 3/7/2018 BOK GOH
Building over 3-story or 36-ft Cleared 3/8/2018 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 3/8/2018 EDUARDO PEDROZA

Contact Information

Architect Rule, Thomas James; Lic. No.: C24490 3405 NORTH KNOLL DR.      LOS ANGELES, CA 900681964
Architect Uriu, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2018 Partial Inspection LARRY ARNICK
Deputy Reinf. Concrete 8/15/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/15/2018 Partial Approval GREGORY POMISH
METHANE-Barrier 8/15/2018 Not Ready for Inspection GREGORY POMISH
METHANE-Subgrade 8/15/2018 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/27/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/28/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/30/2018 Approved LARRY ARNICK
Deputy Reinf. Concrete 8/31/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/4/2018 Conditional Approval LARRY ARNICK
Deputy Shotcrete 9/4/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/11/2018 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/18/2018 Not Ready for Inspection LARRY ARNICK
Green Building Rough 9/18/2018 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 9/18/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/18/2018 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/18/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/18/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/20/2018 Approved LARRY ARNICK
Masonry Wall/Backfill 9/20/2018 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 9/25/2018 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 9/25/2018 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/26/2018 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 9/26/2018 Partial Approval LARRY ARNICK
Green Building Rough 9/28/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 9/28/2018 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 9/28/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/28/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 10/1/2018 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/1/2018 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 10/1/2018 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/4/2018 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 10/5/2018 Approved LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/15/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 10/17/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/17/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/22/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 10/23/2018 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 10/29/2018 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/30/2018 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 11/1/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/20/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/20/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/3/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/3/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/4/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/5/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/5/2018 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 12/10/2018 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/13/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/17/2018 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/18/2018 No Access for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 12/20/2018 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 12/21/2018 Conditional Approval LARRY ARNICK
Deputy Wood Construction 1/2/2019 Conditional Approval LARRY ARNICK
Green Building Rough 1/2/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 1/2/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/2/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/2/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/10/2019 Partial Approval LARRY ARNICK
Green Building Rough 1/24/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 1/24/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/24/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/24/2019 Partial Approval LARRY ARNICK
Deputy Wood Construction 1/25/2019 Approved GREGORY POMISH
Deputy Wood Construction 2/19/2019 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/19/2019 Partial Approval LARRY ARNICK
Green Building Rough 2/19/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 2/19/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 2/19/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 2/19/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/21/2019 Partial Approval LARRY ARNICK
Green Building Rough 3/11/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 3/11/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 3/11/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/11/2019 Partial Approval LARRY ARNICK
Green Building Rough 3/14/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 3/14/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 3/14/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/14/2019 Partial Approval LARRY ARNICK
Green Building Rough 4/1/2019 Not Ready for Inspection LARRY ARNICK
Insulation 4/1/2019 Partial Approval LARRY ARNICK
METHANE-Rough 4/1/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/1/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/1/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/5/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 4/5/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 4/5/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/5/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/5/2019 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/8/2019 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/19/2019 Approved LARRY ARNICK
Green Building Rough 4/19/2019 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 4/19/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/19/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/19/2019 Conditional Approval LARRY ARNICK
Deputy Wood Construction 4/22/2019 Conditional Approval LARRY ARNICK
Drywall Nailing 4/25/2019 Partial Approval LARRY ARNICK
Green Building Rough 4/25/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/17/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 5/17/2019 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 5/17/2019 Order to Comply Issued LARRY ARNICK
Drywall Nailing 6/11/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/11/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 6/14/2019 Partial Approval LARRY ARNICK
Green Building Rough 6/14/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 6/21/2019 Partial Inspection LESLIE TRUJILLO
Green Building Rough 6/21/2019 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 6/26/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/26/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 6/28/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 6/28/2019 Not Ready for Inspection LARRY ARNICK
Insulation 6/28/2019 Approved LARRY ARNICK
Interior/Exterior Lathing 6/28/2019 Approved LARRY ARNICK
Drywall Nailing 7/10/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 7/10/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 7/15/2019 Partial Approval LARRY ARNICK
Green Building Rough 7/15/2019 Conditional Approval LARRY ARNICK
Drywall Nailing 7/23/2019 Partial Approval LARRY ARNICK
Green Building Rough 7/23/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 8/12/2019 Approved LARRY ARNICK
Green Building Rough 8/12/2019 Approved LARRY ARNICK
Final 12/9/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/9/2019 Conditional Approval LARRY ARNICK
Green Building Final 12/9/2019 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 12/9/2019 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 12/9/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/9/2019 Conditional Approval LARRY ARNICK
Final 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Green Building Final 12/23/2019 Partial Inspection DANIEL MC AULIFFE
METHANE-Barrier 12/23/2019 Partial Approval DANIEL MC AULIFFE
METHANE-Final 12/23/2019 Partial Inspection DANIEL MC AULIFFE
METHANE-Rough 12/23/2019 Partial Inspection DANIEL MC AULIFFE
METHANE-Subgrade 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 12/23/2019 Partial Inspection DANIEL MC AULIFFE
SGSOV-Seismic Gas S/O Valve 12/23/2019 SGSOV Not Ready DANIEL MC AULIFFE
Smoke Detectors 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Structural Steel Frame 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/23/2019 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 12/23/2019 Partial Inspection DANIEL MC AULIFFE
Final 12/24/2019 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 12/24/2019 Conditional Approval LARRY ARNICK
Green Building Final 12/24/2019 Approved LARRY ARNICK
METHANE-Barrier 12/24/2019 Approved LARRY ARNICK
METHANE-Final 12/24/2019 Approved LARRY ARNICK
METHANE-Rough 12/24/2019 Approved LARRY ARNICK
METHANE-Subgrade 12/24/2019 Approved LARRY ARNICK
Reinforced Concrete Frame 12/24/2019 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 12/24/2019 Conditional Approval LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 12/24/2019 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 12/24/2019 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 12/24/2019 Conditional Approval LARRY ARNICK
Verify Sprinkler Sign Off 12/24/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/24/2019 Conditional Approval LARRY ARNICK
Pre-Inspection 1/6/2020 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 1/15/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 1/15/2020 Partial Approval HAMID PISHEHVAR
Final 2/19/2020 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 2/19/2020 Approved LARRY ARNICK
Reinforced Concrete Frame 2/19/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 2/19/2020 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 2/19/2020 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 2/19/2020 Approved LARRY ARNICK
Structural Steel Frame 2/19/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 2/19/2020 Not Ready for Inspection LARRY ARNICK
Wood Frame 2/19/2020 Not Ready for Inspection LARRY ARNICK
Final 3/11/2020 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 3/11/2020 Approved LARRY ARNICK
Reinforced Masonry Frame 3/11/2020 Approved LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 3/11/2020 SGSOV Approved LARRY ARNICK
Structural Steel Frame 3/11/2020 Approved LARRY ARNICK
Verify Sprinkler Sign Off 3/11/2020 Approved LARRY ARNICK
Wood Frame 3/11/2020 Approved LARRY ARNICK
Final 3/19/2020 Not Ready for Inspection LARRY ARNICK
Final 3/24/2020 Conditional Approval LARRY ARNICK
Final 4/6/2020 Conditional Approval LARRY ARNICK
Special/Order Compliance 9/4/2020 Conditional Approval LARRY ARNICK