175 S AVENUE 57 90042

Certificate Information: 175 S AVENUE 57 90042

Application / Permit
16010-10000-02137
Plan Check / Job No.
B16LA07396
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story Single Family Dwelling over Basement Garage per Small Lot Subdivision VTT-73072-SL (Lot #5)
Permit Issued
Issued on 11/15/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2016 APPLICANT
Assigned to Plan Check Engineer 6/30/2016 MARJAN SHENASI
Green Plans Picked Up 7/5/2016 APPLICANT
Corrections Issued 7/27/2016 MARJAN SHENASI
Quality Review Completed 8/5/2016 GUANG MIN TUNG
Building Plans Picked Up 8/9/2016 APPLICANT
Applicant returned to address corrections 7/26/2017 MARJAN SHENASI
Applicant returned to address corrections 8/9/2017 MARJAN SHENASI
Applicant returned to address corrections 8/16/2017 MARJAN SHENASI
Applicant returned to address corrections 9/6/2017 MARJAN SHENASI
Applicant returned to address corrections 9/20/2017 MARJAN SHENASI
Applicant returned to address corrections 9/27/2017 MARJAN SHENASI
Applicant returned to address corrections 10/11/2017 MARJAN SHENASI
Applicant returned to address corrections 11/8/2017 MARJAN SHENASI
Plan Check Approved 11/15/2017 MARJAN SHENASI
Issued 11/15/2017 LADBS
CofO in Progress 2/7/2025 BRENDAN MORELLI
Permit Finaled 2/17/2025 DEROLD HAUFF
CofO Issued 2/17/2025 DEROLD HAUFF
Permit Finaled 2/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/4/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 1/11/2017 ROBERT DUFF
Miscellaneous Cleared 2/14/2017 FIPE LEILUA
ZA Case Cleared 2/14/2017 FIPE LEILUA
Sewer availability Cleared 6/6/2017 RAVIL MANAPOV
Low Impact Development Cleared 7/11/2017 IDA MEISAMI-FARD
Permit Cleared 7/13/2017 LINDA MARGARET
Eng Process Fee Ord 176,300 Cleared 7/24/2017 RAVIL MANAPOV
Grading Pre-Inspection Cleared 7/26/2017 MARJAN SHENASI
Miscellaneous Cleared 7/27/2017 ARMENIA AGUILAR
Roof/Waste drainage to street Cleared 7/27/2017 ARMENIA AGUILAR
Green Code Cleared 8/2/2017 DAVID MATSON
Highway dedication Cleared 8/17/2017 ARMENIA AGUILAR
Building over 3-story or 36-ft Cleared 9/20/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/20/2017 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 10/23/2017 CHIU TAM
ZA Case Cleared 10/24/2017 MARITZA PRZEKOP
Miscellaneous Cleared 10/25/2017 JESSE RAMOS
HPOZ Cleared 11/3/2017 ARIANE BRISKI
Miscellaneous Cleared 11/3/2017 ARIANE BRISKI

Contact Information

Architect Lee, Wan; Lic. No.: C30792 530 MOLINO STREET SUITE 220      LOS ANGELES, CA 90013
Contractor R A Construction; Lic. No.: 831437-B P O BOX 261185      ENCINO, CA 91426
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Doss, Richard E; Lic. No.: C48987 30141 AGOURA RD 200      AGOURA HILLS, CA 91301
Engineer Zweigler, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Hoek, Johan; Lic. No.: EG2544 1575 N EL MOLINO AVE      PASADENA, CA 91104

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/1/2019 Corrections Issued SCOTT FINNILA
Deputy Reinf. Concrete 11/5/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 11/6/2019 Not Ready for Inspection MICHAEL FAUNCE
Footing/Foundation/Slab 11/14/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/29/2020 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/12/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 1/12/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/25/2021 Partial Approval ALEJANDRO DE ARTOLA
Deputy Steel/Welding 4/28/2021 Partial Approval SCOTT FINNILA
Deputy Steel/Welding 5/3/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 5/25/2021 Partial Approval SCOTT FINNILA
Green Building Rough 5/25/2021 Partial Approval SCOTT FINNILA
Deputy Steel/Welding 6/23/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval SCOTT FINNILA
Deputy Wood Construction 6/25/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 6/30/2021 Corrections Issued SCOTT FINNILA
Drywall Nailing 7/1/2021 Partial Approval SCOTT FINNILA
Green Building Rough 7/1/2021 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval SCOTT FINNILA
Deputy Wood Construction 7/30/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 8/4/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Partial Approval SCOTT FINNILA
Deputy Wood Construction 8/30/2021 Partial Approval SCOTT FINNILA
Deputy Wood Construction 9/10/2021 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 9/14/2021 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 9/20/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Partial Approval SCOTT FINNILA
Green Building Rough 9/20/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 1/5/2022 Partial Approval SCOTT FINNILA
Deputy Wood Construction 3/14/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 2/27/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/6/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 3/8/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/8/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/13/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 3/13/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 3/13/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/28/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/28/2023 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/16/2023 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/4/2023 Partial Inspection ALIZAH MAYAGOITIA
Insulation 8/10/2023 Corrections Issued ALIZAH MAYAGOITIA
Insulation 8/15/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 8/24/2023 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 9/6/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/25/2023 Approved ALIZAH MAYAGOITIA
Pre-Inspection 9/25/2023 Corrections Issued ALIZAH MAYAGOITIA
Shower Pan 9/25/2023 Approved ALIZAH MAYAGOITIA
Grading Pre-Inspection 10/20/2023 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 11/17/2023 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 11/17/2023 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 11/29/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/1/2023 Corrections Issued ALIZAH MAYAGOITIA
Pre-Inspection 12/5/2023 Partial Inspection SCOTT FINNILA
Special/Order Compliance 12/5/2023 Partial Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/28/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 1/9/2024 Partial Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 1/25/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 3/5/2024 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 3/18/2024 Not Ready for Inspection JOSEPH MCGARRY
Pre-Inspection 3/20/2024 Partial Approval JOSEPH MCGARRY
Drywall Nailing 4/1/2024 Approved JOSEPH MCGARRY
Reinforced Masonry Frame 5/10/2024 Partial Inspection JOSEPH MCGARRY
Reinforced Masonry Frame 5/24/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 7/3/2024 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 8/28/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 8/28/2024 Corrections Issued BRENDAN MORELLI
Final 8/28/2024 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 8/28/2024 Approved BRENDAN MORELLI
Green Building Final 8/28/2024 Approved BRENDAN MORELLI
HVAC-Final 8/28/2024 Approved BRENDAN MORELLI
PLUMBING-Final 8/28/2024 Not Ready for Inspection BRENDAN MORELLI
Reinforced Concrete Frame 8/28/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Approved BRENDAN MORELLI
Service/Power Release 8/28/2024 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 8/28/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/6/2024 Approved BRENDAN MORELLI
Final 9/6/2024 Not Ready for Inspection BRENDAN MORELLI
Gas Test 9/6/2024 Approved BRENDAN MORELLI
PLUMBING-Final 9/6/2024 Approved BRENDAN MORELLI
Service/Power Release 9/24/2024 Approved BRENDAN MORELLI
Final 1/27/2025 Not Ready for Inspection BRENDAN MORELLI
Final 2/7/2025 OK to Issue CofO BRENDAN MORELLI