19525 W NORDHOFF ST Bldg A 91324

Certificate Information: 19525 W NORDHOFF ST Bldg A 91324

Application / Permit
16010-10000-02125
Plan Check / Job No.
B16LA07386
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 6 STORY MIXED USE APARTMENT (215 UNITS) AND RESTAURANT/RETAIL (CORE & SHELL ONLY) OVER PARKING PER VTT63625 M8.ZA2005-7584(ZV)(SPR)(PA2). THE BUILDING INCLUDES 4 STORIES TYPE V-A RESIDENTIAL APARTMENT OVER 2 STORIES TYPE I-A RESTAURANT, GARAGE, DWELLING UNITS AND 1 SUBTERRANEAN PARKING LEVEL. BLDG "A"
Permit Issued
Issued on 10/12/2017
Issuing Office
Metro
Current Status
CofO Issued on 3/26/2021
Certificate of Occupancy
168931 - CofO Issued More Information
168931 - CofO Issued More Information

Permit Application Status History

Submitted 5/31/2016 APPLICANT
Assigned to Plan Check Engineer 7/7/2016 ARMEN JIVALAGIAN
Corrections Issued 7/20/2016 ARMEN JIVALAGIAN
Quality Review Completed 8/1/2016 CHARLES CHANG
Applicant returned to address corrections 2/14/2017 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/16/2017 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/10/2017 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/27/2017 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/7/2017 ARMEN JIVALAGIAN
Plan Check Approved 10/12/2017 ARMEN JIVALAGIAN
Issued 10/12/2017 LADBS
Permit Closed-Status Void 6/4/2020 ROBERT COLE
Re-Activate Permit 6/12/2020 ROBERT COLE
TCO Issued (Expire Date: 02-23-2021) 8/27/2020 RICKEY JACKSON
CofO in Progress 3/24/2021 RICKEY JACKSON
Permit Finaled 3/24/2021 RICKEY JACKSON
CofO Issued 3/26/2021 RICKEY JACKSON
Permit Finaled 3/26/2021 RICKEY JACKSON

Permit Application Clearance Information

Internal circulation Cleared 7/19/2016 ARMEN JIVALAGIAN
Transportation Demand Ord. Cleared 7/19/2016 ARMEN JIVALAGIAN
Address approval Cleared 8/1/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 8/19/2016 YESENIA DIAZ
Highway dedication Cleared 8/19/2016 YESENIA DIAZ
Permit Cleared 8/19/2016 YESENIA DIAZ
CPC Cleared 8/23/2016 BRIAN CARR
ZA Case Cleared 8/23/2016 BRIAN CARR
ZA Case Cleared 8/23/2016 BRIAN CARR
Tract Map conditions Cleared 9/1/2016 BRIAN CARR
ZA Case Cleared 9/1/2016 BRIAN CARR
Hydrant and Access approval Cleared 9/8/2016 JOHN DALLAS
Construction near power lines Cleared 10/6/2016 OSCAR CASTRO
Driveway location Cleared 1/12/2017 KEN AITCHISON
"T" removal Cleared 3/30/2017 BRIAN CARR
Low Impact Development Cleared 7/5/2017 MARTIN FRAGOSO
Miscellaneous Cleared 8/29/2017 BRIAN CARR
Miscellaneous Cleared 8/29/2017 BRIAN CARR
Opn space landscape/Water mgmt Cleared 8/29/2017 BRIAN CARR
Prkng lot landscape/Water mgmt Cleared 8/29/2017 BRIAN CARR
Site Plan review Cleared 8/29/2017 BRIAN CARR
ZA Case Cleared 8/29/2017 BRIAN CARR
DAS Clearance Cleared 9/7/2017 ARMEN JIVALAGIAN
Roof/Waste drainage to street Cleared 9/7/2017 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/20/2017 ADRIAN SANCHEZ
Food Service Establishment Cleared 9/21/2017 AMPHORN WONG
Work Adjacent to Public Way Cleared 9/21/2017 CHIU TAM
"Q" conditions Cleared 9/22/2017 BRIAN CARR
CPC Cleared 9/22/2017 BRIAN CARR
Private street Cleared 9/22/2017 BRIAN CARR
Tract Map conditions Cleared 9/22/2017 BRIAN CARR
Tract Map conditions Cleared 9/22/2017 BRIAN CARR
ZA Case Cleared 9/22/2017 BRIAN CARR
Green Code Cleared 10/3/2017 DONALD CRICHLOW
Fire Marshall Fire Life Safety Cleared 10/10/2017 OSCAR SALGADO JR
Building over 3-story or 36-ft Cleared 10/11/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/11/2017 CALOSHA APPROVED

Contact Information

Architect Perkowitz, Simon; Lic. No.: C24026 111 W OCEAN BLVD 21ST FL   PERKOWITZ & RUTH    LONG BEACH, CA 90802
Contractor Owner-Builder       ,
Engineer Andersen, Read Lewis; Lic. No.: GE2810 2527 FRESNO ST      FRESNO, CA 93721
Engineer Eosakul, Dissakorn; Lic. No.: S5226 8363 EDGE WOOD ST      CHINO, CA 91708

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/17/2017 Partial Inspection ROBERT COLE
Deputy Grading 10/31/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/1/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/2/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/3/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/6/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/7/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/8/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/9/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/13/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/14/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/15/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/16/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 11/16/2017 Not Ready for Inspection ROBERT COLE
Deputy Grading 11/17/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/20/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/21/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/27/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/28/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/29/2017 Conditional Approval ROBERT COLE
Deputy Grading 11/30/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/1/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/4/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/5/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 12/5/2017 Partial Approval ROBERT COLE
Deputy Grading 12/6/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/7/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 12/7/2017 Partial Approval ROBERT COLE
Deputy Grading 12/8/2017 Conditional Approval CAMERON CHABAN
Deputy Grading 12/12/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/13/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 12/13/2017 Partial Approval ROBERT COLE
Deputy Grading 12/14/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/15/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/18/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 12/18/2017 Partial Approval ROBERT COLE
Deputy Grading 12/19/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/20/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/21/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/22/2017 No Access for Inspection TROY CHRISTIAN
Green Building Rough 12/22/2017 No Access for Inspection TROY CHRISTIAN
Reinforced Concrete Frame 12/22/2017 No Access for Inspection TROY CHRISTIAN
Deputy Grading 12/26/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/27/2017 Conditional Approval ROBERT COLE
Deputy Grading 12/28/2017 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 12/28/2017 Partial Approval ROBERT COLE
Deputy Grading 12/29/2017 Conditional Approval ROBERT COLE
Deputy Grading 1/2/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/3/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/3/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/3/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 1/3/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/4/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 1/4/2018 Partial Approval ROBERT COLE
Deputy Grading 1/5/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/8/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/8/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/8/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 1/8/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/9/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/10/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/11/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/11/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/11/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/11/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 1/11/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/12/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/12/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/16/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/16/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/16/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 1/16/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/17/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/17/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 1/17/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/18/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/18/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/18/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 1/18/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 1/19/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/19/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 1/19/2018 Partial Approval ROBERT COLE
Deputy Grading 1/22/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/22/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/23/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/23/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/24/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 1/24/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/24/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/25/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 1/26/2018 Conditional Approval JAMES STEPHENS
Deputy Grading 1/30/2018 Conditional Approval ROBERT COLE
Deputy Grading 1/31/2018 Conditional Approval ROBERT COLE
Green Building Rough 1/31/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 1/31/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 1/31/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/1/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 2/1/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/1/2018 Conditional Approval ROBERT COLE
Deputy Grading 2/2/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/2/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 2/2/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 2/5/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/5/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 2/5/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 2/6/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/6/2018 Conditional Approval ROBERT COLE
Green Building Rough 2/6/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/6/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 2/6/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/6/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/7/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/7/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/7/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 2/7/2018 Partial Approval ROBERT COLE
Deputy Grading 2/8/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/8/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/8/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 2/8/2018 Partial Approval ROBERT COLE
Deputy Grading 2/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/9/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 2/9/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 2/9/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/9/2018 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 2/9/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Grading 2/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/12/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/12/2018 Conditional Approval ROBERT COLE
Deputy Grading 2/13/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/13/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/13/2018 Conditional Approval ROBERT COLE
Green Building Rough 2/13/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/13/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 2/13/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/14/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/14/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/14/2018 Conditional Approval ROBERT COLE
Deputy Grading 2/15/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/15/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/15/2018 Conditional Approval ROBERT COLE
Green Building Rough 2/15/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/15/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/15/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 2/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/16/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/16/2018 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 2/16/2018 Partial Approval ROBERT COLE
Deputy Grading 2/20/2018 Approved BRIAN MILLER
Deputy Grading 2/21/2018 Conditional Approval ROBERT COLE
Deputy Grading 2/22/2018 Conditional Approval ROBERT COLE
Deputy Grading 2/23/2018 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 2/23/2018 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 2/23/2018 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/23/2018 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/26/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/26/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 2/26/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/27/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/27/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/27/2018 Conditional Approval ROBERT COLE
Green Building Rough 2/27/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 2/27/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/27/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 2/28/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/28/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 2/28/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 2/28/2018 Partial Approval ROBERT COLE
Deputy Grading 3/1/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/1/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/1/2018 Conditional Approval ROBERT COLE
Green Building Rough 3/1/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/1/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 3/1/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/2/2018 No Access for Inspection ROBERT COLE
Deputy Reinf. Masonry 3/2/2018 No Access for Inspection ROBERT COLE
Deputy Shotcrete 3/2/2018 No Access for Inspection ROBERT COLE
Special/Order Compliance 3/2/2018 No Access for Inspection ROBERT COLE
Green Building Rough 3/5/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/5/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/5/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/6/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/6/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/6/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 3/6/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/7/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/7/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/7/2018 Conditional Approval ROBERT COLE
Green Building Rough 3/7/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/7/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 3/7/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/8/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/8/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/8/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 3/8/2018 Partial Approval ROBERT COLE
Deputy Grading 3/9/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 3/9/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 3/9/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 3/12/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/13/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/13/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 3/14/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/14/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/14/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/15/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/15/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/16/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/16/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 3/16/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/19/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/19/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/19/2018 Conditional Approval ROBERT COLE
Green Building Rough 3/19/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/19/2018 Partial Approval ROBERT COLE
Special/Order Compliance 3/19/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/19/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/20/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/21/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/21/2018 Conditional Approval ROBERT COLE
Green Building Rough 3/21/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/21/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/21/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 3/22/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/22/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/23/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 3/23/2018 Conditional Approval JAMES STEPHENS
Deputy Grading 3/27/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/27/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 3/27/2018 Conditional Approval ROBERT COLE
Deputy Grading 3/28/2018 Conditional Approval ROBERT COLE
Deputy Grading 3/29/2018 Conditional Approval ROBERT COLE
Green Building Rough 3/29/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 3/29/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 3/29/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 3/30/2018 Conditional Approval ROBERT COLE
Green Building Rough 4/2/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/2/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 4/2/2018 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 4/3/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 4/4/2018 Partial Approval ROBERT COLE
Green Building Rough 4/5/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/5/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 4/5/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/5/2018 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 4/7/2018 Off-Hour Fees Due
Special/Order Compliance 4/7/2018 Off-Hour Fees Due
Deputy Reinf. Concrete 4/9/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/9/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/9/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 4/10/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/10/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/10/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 4/10/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 4/11/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/11/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/11/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 4/11/2018 Off-Hour Fees Due
Deputy Reinf. Concrete 4/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/12/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 4/13/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/13/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/13/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/16/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/17/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/17/2018 Conditional Approval ROBERT COLE
Deputy Grading 4/18/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/18/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/18/2018 Conditional Approval ROBERT COLE
Green Building Rough 4/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/18/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 4/18/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 4/19/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 4/19/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 4/19/2018 Conditional Approval JAMES STEPHENS
Deputy Grading 4/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 4/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/20/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/23/2018 Approved JEFFREY DURAN
Deputy Shotcrete 4/23/2018 Approved JEFFREY DURAN
Reinforced Concrete Frame 4/23/2018 Partial Approval JEFFREY DURAN
Deputy Grading 4/24/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/24/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/24/2018 Conditional Approval ROBERT COLE
Green Building Rough 4/24/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/24/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/24/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 4/25/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/25/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/25/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 4/25/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 4/26/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/26/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/26/2018 Conditional Approval ROBERT COLE
Green Building Rough 4/26/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/26/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 4/26/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 4/27/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/27/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/30/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 4/30/2018 Conditional Approval ROBERT COLE
Green Building Rough 4/30/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 4/30/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 4/30/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/1/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/1/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 5/1/2018 Partial Inspection ROBERT COLE
Deputy Reinf. Masonry 5/2/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/2/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/2/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/2/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/2/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/3/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/3/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 5/3/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 5/4/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/4/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/7/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/7/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/7/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/7/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 5/7/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/7/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/8/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/8/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/9/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/9/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 5/9/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 5/10/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/10/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/10/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/10/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/10/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/11/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/11/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 5/11/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 5/14/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/14/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/14/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/15/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/15/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 5/15/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/16/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/17/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/17/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/17/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/17/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 5/17/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/18/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/18/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/21/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/21/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/21/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/21/2018 Partial Inspection ROBERT COLE
Reinforced Masonry Frame 5/21/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/21/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 5/22/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/22/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 5/22/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 5/23/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/23/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/24/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/24/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/24/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/24/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/24/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 5/25/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/25/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/25/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 5/29/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 5/30/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/30/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/31/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 5/31/2018 Conditional Approval ROBERT COLE
Green Building Rough 5/31/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/31/2018 Partial Inspection ROBERT COLE
Reinforced Masonry Frame 5/31/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/31/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 6/4/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 6/4/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/4/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 6/4/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 6/4/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 6/4/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 6/5/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 6/5/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 6/5/2018 Partial Inspection ROBERT COLE
Deputy Reinf. Masonry 6/6/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 6/6/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/6/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/6/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 6/6/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/6/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 6/7/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 6/7/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/8/2018 Conditional Approval ROBERT COLE
Deputy Shotcrete 6/8/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/8/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/8/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 6/8/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 6/11/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/11/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 6/11/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 6/11/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 6/12/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 6/12/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 6/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/14/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/14/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/14/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/14/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 6/14/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/14/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 6/15/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/15/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/18/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/18/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 6/18/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/18/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/19/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/19/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 6/19/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/20/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/21/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/21/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/22/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/22/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/25/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/25/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/25/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/25/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 6/25/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/25/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/26/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/26/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 6/27/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/27/2018 Conditional Approval ROBERT COLE
Green Building Rough 6/27/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/27/2018 Partial Approval ROBERT COLE
Special/Order Compliance 6/27/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/27/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 6/27/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/28/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/28/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 6/28/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/29/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 6/29/2018 Conditional Approval JAMES STEPHENS
Special/Order Compliance 6/30/2018 Off-Hour Fees Due
Special/Order Compliance 6/30/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 7/2/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 7/2/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/2/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 7/2/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/2/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/2/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/3/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 7/3/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 7/3/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/5/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 7/5/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 7/6/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 7/6/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 7/9/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/9/2018 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 7/9/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/9/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/10/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/10/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/10/2018 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 7/10/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/10/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 7/10/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/11/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/11/2018 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 7/11/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/12/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/12/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 7/12/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/12/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 7/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/17/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/18/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 7/18/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 7/19/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/19/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 7/19/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/19/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/19/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 7/20/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/24/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 7/24/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/24/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/24/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 7/30/2018 Conditional Approval ROBERT COLE
Green Building Rough 7/30/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 7/30/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/30/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 7/30/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 8/1/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/1/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/1/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 8/1/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 8/3/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/3/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 8/3/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/3/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/3/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 8/3/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 8/6/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/6/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 8/6/2018 Partial Inspection ROBERT COLE
Deputy Reinf. Masonry 8/7/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/7/2018 Partial Approval ROBERT COLE
Footing/Foundation/Slab 8/7/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/7/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/8/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/9/2018 Conditional Approval ROBERT COLE
Green Building Rough 8/9/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/9/2018 Partial Inspection ROBERT COLE
Reinforced Masonry Frame 8/9/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 8/9/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/10/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 8/13/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/13/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 8/13/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/13/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/13/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 8/13/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/14/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/14/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 8/14/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/15/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/16/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 8/16/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 8/17/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 8/17/2018 Conditional Approval ROBERT COLE
Deputy Grading 8/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/20/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/20/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/20/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 8/21/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/21/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/21/2018 Partial Inspection ROBERT COLE
Green Building Rough 8/21/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/21/2018 Partial Inspection ROBERT COLE
Reinforced Masonry Frame 8/21/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 8/21/2018 Not Ready for Inspection ROBERT COLE
Deputy Grading 8/22/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/22/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/22/2018 Partial Approval ROBERT COLE
Deputy Grading 8/23/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/23/2018 Conditional Approval ROBERT COLE
Deputy Grading 8/24/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 8/24/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 8/24/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 8/27/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 8/27/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 8/28/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 8/28/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 8/28/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 8/29/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/29/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/29/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 8/30/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 8/30/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 8/30/2018 Partial Inspection ROBERT COLE
Deputy Reinf. Masonry 8/31/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 8/31/2018 Conditional Approval ROBERT COLE
Green Building Rough 8/31/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 8/31/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 8/31/2018 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 8/31/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 9/4/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 9/4/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/4/2018 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 9/5/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 9/5/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 9/5/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/6/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 9/6/2018 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 9/7/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/7/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 9/7/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 9/11/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/12/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 9/12/2018 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 9/12/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 9/12/2018 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 9/12/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/14/2018 Partial Approval ROBERT COLE
Reinforced Masonry Frame 9/14/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 9/17/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 9/17/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 9/18/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 9/18/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/18/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 9/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 9/18/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 9/18/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 9/18/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 9/18/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 9/19/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 9/19/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 9/20/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 9/20/2018 Conditional Approval ROBERT COLE
Special/Order Compliance 9/20/2018 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 9/21/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 9/21/2018 Conditional Approval JAMES STEPHENS
Green Building Rough 9/24/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 9/24/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 9/24/2018 Partial Inspection ROBERT COLE
Deputy Steel/Welding 9/25/2018 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 9/26/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 9/28/2018 Not Ready for Inspection ROBERT COLE
Green Building Rough 9/28/2018 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 9/28/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 9/28/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/1/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/1/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/1/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/2/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/2/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/2/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 10/3/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/3/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 10/3/2018 Conditional Approval ROBERT COLE
Green Building Rough 10/3/2018 Not Ready for Inspection ROBERT COLE
Insulation 10/3/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 10/3/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 10/3/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/4/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/4/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/4/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 10/9/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/9/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/9/2018 Not Ready for Inspection CAMERON CHABAN
Deputy Drilled-In Anchors 10/10/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/10/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/10/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 10/11/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/11/2018 Conditional Approval ROBERT COLE
Green Building Rough 10/11/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 10/11/2018 Not Ready for Inspection ROBERT COLE
Wood Frame 10/11/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/12/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/12/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 10/12/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/12/2018 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/15/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/15/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/15/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/16/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/16/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 10/17/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/17/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 10/18/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/18/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 10/18/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 10/19/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 10/19/2018 Conditional Approval JAMES STEPHENS
Deputy Drilled-In Anchors 10/22/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/22/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/22/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/23/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/23/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/23/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 10/24/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/24/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/24/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 10/25/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/25/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/25/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/26/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 10/26/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 10/29/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 10/29/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 10/31/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 10/31/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 10/31/2018 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 11/1/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 11/1/2018 Conditional Approval ROBERT COLE
Deputy Drilled-In Anchors 11/2/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 11/2/2018 Conditional Approval JAMES STEPHENS
Deputy Drilled-In Anchors 11/5/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/5/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/6/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/7/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Partial Inspection ROBERT COLE
Drywall Nailing 11/14/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/15/2018 Partial Inspection ROBERT COLE
Drywall Nailing 11/16/2018 Partial Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/16/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 11/19/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 11/19/2018 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/19/2018 Partial Approval ROBERT COLE
Drywall Nailing 11/26/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 11/27/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/29/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/4/2018 Not Ready for Inspection ROBERT COLE
Insulation 12/4/2018 Partial Approval ROBERT COLE
Insulation 12/6/2018 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 12/7/2018 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 12/10/2018 Conditional Approval ROBERT COLE
Insulation 12/10/2018 Not Ready for Inspection ROBERT COLE
Pre-Inspection 12/12/2018 Partial Inspection ROBERT COLE
Insulation 12/13/2018 Not Ready for Inspection ROBERT COLE
Insulation 12/14/2018 Not Ready for Inspection JEFFREY DURAN
Insulation 12/18/2018 Partial Approval ROBERT COLE
Insulation 12/19/2018 Partial Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/21/2018 Partial Inspection ROBERT COLE
Insulation 12/21/2018 Partial Inspection ROBERT COLE
Insulation 12/27/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/28/2018 Not Ready for Inspection ROBERT COLE
Insulation 12/28/2018 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/31/2018 Partial Inspection ROBERT COLE
Insulation 12/31/2018 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 1/2/2019 Partial Approval ROBERT COLE
Insulation 1/2/2019 Partial Inspection ROBERT COLE
Drywall Nailing 1/8/2019 Not Ready for Inspection ROBERT COLE
Insulation 1/8/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/9/2019 Not Ready for Inspection ROBERT COLE
Insulation 1/9/2019 Not Ready for Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 1/14/2019 Partial Inspection ROBERT COLE
Insulation 1/22/2019 Partial Approval ROBERT COLE
Drywall Nailing 1/23/2019 Partial Approval ROBERT COLE
Insulation 1/23/2019 Partial Approval ROBERT COLE
Insulation 1/24/2019 Partial Inspection ROBERT COLE
Insulation 1/25/2019 Partial Approval JEFFREY DURAN
Insulation 1/28/2019 Partial Approval ROBERT COLE
Drywall Nailing 1/29/2019 Partial Inspection ROBERT COLE
Insulation 1/29/2019 Partial Inspection ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 2/1/2019 Corrections Issued ROBERT COLE
Insulation 2/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/6/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/7/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 2/7/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 2/8/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 2/11/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/11/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/12/2019 Not Ready for Inspection ROBERT COLE
Insulation 2/13/2019 Partial Approval ROBERT COLE
Insulation 2/15/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 2/19/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 2/20/2019 Conditional Approval ROBERT COLE
Insulation 2/20/2019 Partial Inspection ROBERT COLE
Drywall Nailing 2/21/2019 Partial Inspection ROBERT COLE
Insulation 2/21/2019 Partial Inspection ROBERT COLE
Drywall Nailing 3/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/1/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/4/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/4/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/5/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/5/2019 Partial Approval ROBERT COLE
Drywall Nailing 3/6/2019 Partial Inspection ROBERT COLE
Insulation 3/6/2019 Partial Inspection ROBERT COLE
Drywall Nailing 3/8/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/8/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/11/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/11/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/12/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 3/12/2019 Partial Approval ROBERT COLE
Insulation 3/12/2019 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 3/13/2019 Conditional Approval ROBERT COLE
Drywall Nailing 3/13/2019 Corrections Issued ROBERT COLE
Insulation 3/13/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/14/2019 Partial Inspection ROBERT COLE
Insulation 3/14/2019 Partial Inspection ROBERT COLE
Drywall Nailing 3/15/2019 Partial Inspection ROBERT COLE
Insulation 3/15/2019 Partial Inspection ROBERT COLE
Drywall Nailing 3/18/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/18/2019 Partial Approval ROBERT COLE
Drywall Nailing 3/19/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/19/2019 Partial Approval ROBERT COLE
Drywall Nailing 3/20/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/20/2019 Partial Inspection ROBERT COLE
Green Building Rough 3/21/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/21/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 3/21/2019 Partial Inspection ROBERT COLE
Deputy Reinf. Masonry 3/22/2019 Conditional Approval DANNY RODRIGUEZ
Drywall Nailing 3/22/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/22/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/28/2019 Partial Approval ROBERT COLE
Insulation 3/28/2019 Partial Approval ROBERT COLE
Wood Frame 3/28/2019 Partial Approval ROBERT COLE
Drywall Nailing 3/29/2019 Not Ready for Inspection ROBERT COLE
Insulation 3/29/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/1/2019 Partial Approval ROBERT COLE
Drywall Nailing 4/2/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/2/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/4/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/4/2019 Partial Approval ROBERT COLE
Drywall Nailing 4/5/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 4/5/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/8/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/8/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/9/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/9/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/10/2019 Partial Inspection ROBERT COLE
Insulation 4/10/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/11/2019 Partial Inspection ROBERT COLE
Insulation 4/11/2019 Partial Inspection ROBERT COLE
Drywall Nailing 4/12/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/12/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/15/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/15/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/16/2019 Partial Inspection ROBERT COLE
Insulation 4/16/2019 Partial Inspection ROBERT COLE
Drywall Nailing 4/17/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/17/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/18/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/18/2019 Partial Approval ROBERT COLE
Drywall Nailing 4/23/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/23/2019 Partial Approval ROBERT COLE
Drywall Nailing 4/24/2019 Partial Inspection ROBERT COLE
Insulation 4/24/2019 Partial Inspection ROBERT COLE
Drywall Nailing 4/25/2019 Partial Inspection ROBERT COLE
Insulation 4/25/2019 Partial Inspection ROBERT COLE
Deputy Reinf. Concrete 4/26/2019 Conditional Approval ROBERT COLE
Drywall Nailing 4/26/2019 Not Ready for Inspection ROBERT COLE
Insulation 4/26/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/29/2019 Partial Approval ROBERT COLE
Insulation 4/29/2019 Partial Approval ROBERT COLE
Drywall Nailing 4/30/2019 Partial Approval ROBERT COLE
Insulation 4/30/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/1/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/2/2019 Partial Approval ROBERT COLE
Insulation 5/2/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/3/2019 Not Ready for Inspection CAMERON CHABAN
Insulation 5/3/2019 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 5/6/2019 Partial Approval ROBERT COLE
Insulation 5/6/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/7/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/7/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/8/2019 Partial Approval ROBERT COLE
Insulation 5/8/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/9/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/9/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/10/2019 Partial Approval ROBERT COLE
Insulation 5/10/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/14/2019 Partial Inspection ROBERT COLE
Insulation 5/14/2019 Partial Inspection ROBERT COLE
Drywall Nailing 5/15/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/15/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/16/2019 Partial Approval JEFFREY DURAN
Insulation 5/16/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/17/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 5/17/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/20/2019 Partial Inspection ROBERT COLE
Insulation 5/20/2019 Partial Inspection ROBERT COLE
Drywall Nailing 5/21/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/21/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/22/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/22/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/23/2019 Partial Approval ROBERT COLE
Insulation 5/23/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/24/2019 Partial Approval ROBERT COLE
Insulation 5/24/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/28/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/28/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 5/29/2019 Partial Approval ROBERT COLE
Insulation 5/29/2019 Partial Approval ROBERT COLE
Drywall Nailing 5/30/2019 Not Ready for Inspection ROBERT COLE
Insulation 5/30/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/3/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/3/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/4/2019 Partial Approval ROBERT COLE
Insulation 6/4/2019 Partial Approval ROBERT COLE
Drywall Nailing 6/5/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/5/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/6/2019 Partial Approval ROBERT COLE
Insulation 6/6/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/7/2019 Partial Approval ROBERT COLE
Insulation 6/7/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/10/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/10/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/11/2019 Partial Approval ROBERT COLE
Insulation 6/11/2019 Partial Approval ROBERT COLE
Drywall Nailing 6/12/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/12/2019 Partial Approval ROBERT COLE
Drywall Nailing 6/13/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/13/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/14/2019 Partial Approval MILLARD ARDOIN
Insulation 6/14/2019 Partial Approval MILLARD ARDOIN
Drywall Nailing 6/17/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/17/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/18/2019 Corrections Issued ROBERT COLE
Insulation 6/18/2019 Partial Approval ROBERT COLE
Drywall Nailing 6/19/2019 Not Ready for Inspection ROBERT COLE
Insulation 6/19/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/20/2019 Partial Inspection ROBERT COLE
Insulation 6/20/2019 Partial Inspection ROBERT COLE
Drywall Nailing 6/24/2019 Partial Approval ROBERT COLE
Insulation 6/24/2019 Not Ready for Inspection ROBERT COLE
Interior/Exterior Lathing 6/24/2019 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/25/2019 Conditional Approval ROBERT COLE
Drywall Nailing 6/25/2019 Partial Approval ROBERT COLE
Insulation 6/25/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/26/2019 Partial Approval ROBERT COLE
Insulation 6/26/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/27/2019 Partial Inspection ROBERT COLE
Insulation 6/27/2019 Partial Inspection ROBERT COLE
Drywall Nailing 6/28/2019 Partial Approval MILLARD ARDOIN
Insulation 6/28/2019 Partial Approval MILLARD ARDOIN
Drywall Nailing 7/1/2019 Partial Approval ROBERT COLE
Insulation 7/1/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/2/2019 Partial Approval ROBERT COLE
Insulation 7/2/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/8/2019 Partial Approval ROBERT COLE
Insulation 7/8/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 7/10/2019 Partial Approval ROBERT COLE
Insulation 7/10/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/11/2019 Partial Inspection ROBERT COLE
Insulation 7/11/2019 Partial Inspection ROBERT COLE
Drywall Nailing 7/15/2019 Partial Approval ROBERT COLE
Insulation 7/15/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/16/2019 Partial Approval ROBERT COLE
Insulation 7/16/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/18/2019 Not Ready for Inspection ROBERT COLE
Insulation 7/18/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/19/2019 Partial Approval ROBERT COLE
Insulation 7/19/2019 Not Ready for Inspection ROBERT COLE
Deputy Steel/Welding 7/22/2019 Conditional Approval ROBERT COLE
Drywall Nailing 7/22/2019 Partial Approval ROBERT COLE
Insulation 7/22/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 7/23/2019 Conditional Approval ROBERT COLE
Drywall Nailing 7/23/2019 Partial Approval ROBERT COLE
Insulation 7/23/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 7/24/2019 Conditional Approval ROBERT COLE
Drywall Nailing 7/24/2019 Not Ready for Inspection ROBERT COLE
Insulation 7/24/2019 Partial Inspection ROBERT COLE
Deputy Steel/Welding 7/25/2019 Conditional Approval ROBERT COLE
Drywall Nailing 7/25/2019 Partial Approval ROBERT COLE
Insulation 7/25/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/29/2019 Partial Approval ROBERT COLE
Insulation 7/29/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/30/2019 Not Ready for Inspection ROBERT COLE
Insulation 7/30/2019 Partial Approval ROBERT COLE
Drywall Nailing 7/31/2019 Partial Inspection ROBERT COLE
Insulation 7/31/2019 Partial Inspection ROBERT COLE
Drywall Nailing 8/1/2019 Partial Approval ROBERT COLE
Insulation 8/1/2019 Partial Approval ROBERT COLE
Insulation 8/2/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 8/2/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/5/2019 Partial Approval ROBERT COLE
Insulation 8/5/2019 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 8/6/2019 Conditional Approval ROBERT COLE
Drywall Nailing 8/6/2019 Partial Approval ROBERT COLE
Insulation 8/6/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 8/7/2019 Conditional Approval ROBERT COLE
Drywall Nailing 8/7/2019 Corrections Issued ROBERT COLE
Insulation 8/7/2019 Partial Inspection ROBERT COLE
Drywall Nailing 8/8/2019 Partial Inspection ROBERT COLE
Insulation 8/8/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/9/2019 Partial Approval DANNY RODRIGUEZ
Insulation 8/9/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/13/2019 Partial Approval ROBERT COLE
Insulation 8/13/2019 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 8/13/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 8/14/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/14/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 8/15/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/15/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/20/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/20/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 8/20/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/21/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/21/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 8/22/2019 Partial Inspection ROBERT COLE
Insulation 8/22/2019 Partial Inspection ROBERT COLE
Drywall Nailing 8/26/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/26/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 8/27/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/27/2019 Corrections Issued ROBERT COLE
Drywall Nailing 8/28/2019 Partial Approval ROBERT COLE
Insulation 8/28/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/29/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/29/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 8/29/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/3/2019 Partial Approval ROBERT COLE
Special/Order Compliance 9/3/2019 Corrections Issued ROBERT COLE
Drywall Nailing 9/4/2019 Partial Approval ROBERT COLE
Insulation 9/4/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/5/2019 Partial Approval ROBERT COLE
Insulation 9/5/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 9/6/2019 Conditional Approval JAMES STEPHENS
Drywall Nailing 9/9/2019 Partial Approval ROBERT COLE
Insulation 9/9/2019 Partial Approval ROBERT COLE
Drywall Nailing 9/10/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/10/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/11/2019 Partial Approval ROBERT COLE
Insulation 9/11/2019 Partial Approval ROBERT COLE
Drywall Nailing 9/12/2019 Partial Approval ROBERT COLE
Insulation 9/12/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 9/12/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 9/13/2019 Conditional Approval ROBERT COLE
Deputy Steel/Welding 9/13/2019 Conditional Approval ROBERT COLE
Drywall Nailing 9/13/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/13/2019 Partial Approval ROBERT COLE
Deputy Steel/Welding 9/16/2019 Conditional Approval ROBERT COLE
Drywall Nailing 9/16/2019 Partial Inspection ROBERT COLE
Insulation 9/16/2019 Partial Inspection ROBERT COLE
Deputy Grading 9/17/2019 Conditional Approval ROBERT COLE
Drywall Nailing 9/17/2019 Partial Approval ROBERT COLE
Masonry Wall/Backfill 9/17/2019 Partial Approval ROBERT COLE
Drywall Nailing 9/18/2019 Partial Inspection ROBERT COLE
Insulation 9/18/2019 Partial Inspection ROBERT COLE
Drywall Nailing 9/19/2019 Partial Approval ROBERT COLE
Insulation 9/19/2019 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 9/20/2019 Conditional Approval JAMES STEPHENS
Insulation 9/20/2019 Not Ready for Inspection JAMES STEPHENS
Light Gage Steel Frame 9/20/2019 Partial Approval JAMES STEPHENS
Drywall Nailing 9/23/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/23/2019 Partial Approval ROBERT COLE
Drywall Nailing 9/24/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/24/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/25/2019 Partial Approval ROBERT COLE
Insulation 9/25/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/26/2019 Not Ready for Inspection ROBERT COLE
Insulation 9/26/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/27/2019 Partial Approval ROBERT COLE
Insulation 9/27/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/30/2019 Partial Inspection ROBERT COLE
Insulation 9/30/2019 Partial Inspection ROBERT COLE
Drywall Nailing 10/1/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/1/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/2/2019 Partial Approval ROBERT COLE
Insulation 10/2/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/3/2019 Partial Approval ROBERT COLE
Insulation 10/3/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/4/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/4/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 10/7/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/7/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/8/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/8/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/9/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/9/2019 Not Ready for Inspection ROBERT COLE
Deputy Drilled-In Anchors 10/10/2019 Conditional Approval ROBERT COLE
Drywall Nailing 10/10/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/10/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/11/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/11/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/17/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/17/2019 Partial Approval ROBERT COLE
Insulation 10/17/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 10/17/2019 Partial Approval ROBERT COLE
Drywall Nailing 10/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 10/21/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/21/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/22/2019 Partial Approval ROBERT COLE
Insulation 10/22/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/23/2019 Partial Approval ROBERT COLE
Insulation 10/23/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/24/2019 Partial Inspection ROBERT COLE
Insulation 10/24/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/28/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/28/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/29/2019 Partial Approval ROBERT COLE
Masonry Wall/Backfill 10/29/2019 Partial Approval ROBERT COLE
Drywall Nailing 10/30/2019 Partial Approval ROBERT COLE
Insulation 10/30/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/31/2019 Not Ready for Inspection ROBERT COLE
Insulation 10/31/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/4/2019 Not Ready for Inspection ROBERT COLE
Insulation 11/4/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/5/2019 Partial Approval ROBERT COLE
Insulation 11/5/2019 Partial Approval ROBERT COLE
T-Bar Ceiling 11/5/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 11/7/2019 Partial Inspection ROBERT COLE
Green Building Rough 11/7/2019 Not Ready for Inspection ROBERT COLE
Insulation 11/7/2019 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 11/7/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 11/7/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/8/2019 Not Ready for Inspection ROBERT COLE
Insulation 11/8/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/12/2019 Partial Approval ROBERT COLE
Insulation 11/12/2019 Not Ready for Inspection ROBERT COLE
Insulation 11/13/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 11/13/2019 Partial Approval ROBERT COLE
Reinforced Masonry Frame 11/13/2019 Partial Inspection ROBERT COLE
Drywall Nailing 11/14/2019 Corrections Issued ROBERT COLE
T-Bar Ceiling 11/14/2019 Partial Inspection ROBERT COLE
Drywall Nailing 11/18/2019 Partial Inspection ROBERT COLE
Light Gage Steel Frame 11/18/2019 Partial Inspection ROBERT COLE
T-Bar Ceiling 11/18/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/19/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 11/19/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/20/2019 Partial Inspection ROBERT COLE
Light Gage Steel Frame 11/20/2019 Partial Inspection ROBERT COLE
Drywall Nailing 11/21/2019 Partial Approval ROBERT COLE
T-Bar Ceiling 11/21/2019 Not Ready for Inspection ROBERT COLE
Insulation 11/22/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 11/22/2019 Partial Approval ROBERT COLE
Deputy Wood Construction 11/26/2019 Conditional Approval ROBERT COLE
Drywall Nailing 11/26/2019 Partial Approval ROBERT COLE
T-Bar Ceiling 11/26/2019 Partial Inspection ROBERT COLE
Drywall Nailing 11/27/2019 Partial Inspection ROBERT COLE
T-Bar Ceiling 11/27/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/2/2019 Partial Inspection ROBERT COLE
T-Bar Ceiling 12/2/2019 Partial Inspection ROBERT COLE
Drywall Nailing 12/3/2019 Not Ready for Inspection ROBERT COLE
Insulation 12/3/2019 Corrections Issued ROBERT COLE
Drywall Nailing 12/4/2019 Partial Inspection ROBERT COLE
Light Gage Steel Frame 12/4/2019 Partial Inspection ROBERT COLE
Insulation 12/5/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 12/5/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/6/2019 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 12/6/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/9/2019 Partial Approval ROBERT COLE
T-Bar Ceiling 12/9/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/10/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 12/10/2019 Partial Approval ROBERT COLE
Drywall Nailing 12/11/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 12/11/2019 Corrections Issued ROBERT COLE
Deputy Steel/Welding 12/12/2019 Conditional Approval ROBERT COLE
Drywall Nailing 12/12/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 12/12/2019 Partial Approval ROBERT COLE
Drywall Nailing 12/13/2019 Partial Approval JAMES STEPHENS
Light Gage Steel Frame 12/13/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 12/17/2019 Partial Approval JAMES STEPHENS
Structural Steel Frame 12/17/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 12/18/2019 Partial Approval JAMES STEPHENS
Light Gage Steel Frame 12/18/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 12/19/2019 Partial Approval JAMES STEPHENS
Light Gage Steel Frame 12/19/2019 Partial Approval JAMES STEPHENS
Drywall Nailing 12/23/2019 Partial Approval RICKEY JACKSON
Light Gage Steel Frame 12/23/2019 Not Ready for Inspection RICKEY JACKSON
Drywall Nailing 12/24/2019 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/24/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/26/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 12/26/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/27/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 12/27/2019 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 12/27/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/30/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 12/30/2019 Partial Approval ROBERT COLE
Drywall Nailing 12/31/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 12/31/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/2/2020 Partial Approval ROBERT COLE
Light Gage Steel Frame 1/2/2020 Partial Approval ROBERT COLE
Drywall Nailing 1/3/2020 Partial Approval ROBERT COLE
Light Gage Steel Frame 1/3/2020 Partial Approval ROBERT COLE
Insulation 1/6/2020 Partial Approval ROBERT COLE
Light Gage Steel Frame 1/6/2020 Partial Inspection ROBERT COLE
Drywall Nailing 1/7/2020 No Access for Inspection ROBERT COLE
Light Gage Steel Frame 1/7/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/8/2020 Partial Approval ROBERT COLE
Insulation 1/8/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/9/2020 Conditional Approval ROBERT COLE
Light Gage Steel Frame 1/9/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/10/2020 Partial Approval JAMES STEPHENS
Light Gage Steel Frame 1/10/2020 Partial Approval JAMES STEPHENS
Drywall Nailing 1/13/2020 Partial Approval ROBERT COLE
Insulation 1/13/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/14/2020 Partial Inspection ROBERT COLE
Interior/Exterior Lathing 1/14/2020 Partial Approval ROBERT COLE
Drywall Nailing 1/15/2020 Partial Approval ROBERT COLE
Drywall Nailing 1/16/2020 Partial Approval ROBERT COLE
Drywall Nailing 1/17/2020 Partial Approval ROBERT COLE
Insulation 1/17/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/21/2020 Partial Approval ROBERT COLE
Insulation 1/21/2020 Not Ready for Inspection ROBERT COLE
Insulation 1/23/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 1/23/2020 Partial Approval ROBERT COLE
Drywall Nailing 1/27/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 1/27/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/28/2020 Partial Approval JAMES STEPHENS
T-Bar Ceiling 1/28/2020 Partial Approval JAMES STEPHENS
Drywall Nailing 1/29/2020 Partial Approval ROBERT COLE
Insulation 1/29/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/30/2020 Not Ready for Inspection ROBERT COLE
Insulation 1/30/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 1/31/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 1/31/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/3/2020 Partial Approval JAMES STEPHENS
Insulation 2/3/2020 Partial Approval JAMES STEPHENS
Drywall Nailing 2/4/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 2/4/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/5/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 2/5/2020 Partial Approval ROBERT COLE
Drywall Nailing 2/6/2020 Partial Approval ROBERT COLE
Light Gage Steel Frame 2/6/2020 Partial Approval ROBERT COLE
Drywall Nailing 2/7/2020 Partial Approval JAMES STEPHENS
T-Bar Ceiling 2/7/2020 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 2/10/2020 Partial Approval ROBERT COLE
Interior/Exterior Lathing 2/10/2020 Corrections Issued ROBERT COLE
Drywall Nailing 2/11/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 2/11/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/12/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 2/12/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/13/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/13/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/14/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/14/2020 Not Ready for Inspection ROBERT COLE
Interior/Exterior Lathing 2/18/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 2/18/2020 Not Ready for Inspection ROBERT COLE
Final 2/19/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 2/19/2020 Not Ready for Inspection ROBERT COLE
Green Building Final 2/19/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 2/19/2020 Approved ROBERT COLE
Light Gage Steel Frame 2/19/2020 Partial Approval ROBERT COLE
Pre-Inspection 2/19/2020 Partial Inspection ROBERT COLE
Reinforced Concrete Frame 2/19/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 2/19/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 2/19/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 2/19/2020 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 2/19/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 2/19/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/20/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 2/20/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/21/2020 Partial Approval JAMES STEPHENS
T-Bar Ceiling 2/21/2020 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 2/24/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/24/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/25/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/25/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/26/2020 Partial Approval ROBERT COLE
Special/Order Compliance 2/26/2020 Corrections Issued ROBERT COLE
T-Bar Ceiling 2/26/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/27/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/27/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 2/28/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 2/28/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/2/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 3/2/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/3/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/3/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/4/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/4/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/5/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 3/5/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/9/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 3/9/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/10/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/10/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/11/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 3/11/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/12/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 3/12/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/13/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/13/2020 Partial Inspection ROBERT COLE
Final 3/14/2020 Off-Hour Fees Due
Final 3/14/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 3/14/2020 Off-Hour Fees Due
Green Building Final 3/14/2020 Off-Hour Fees Due
Insulation 3/14/2020 Partial Approval ROBERT COLE
Reinforced Concrete Frame 3/14/2020 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/14/2020 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 3/14/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 3/14/2020 Off-Hour Fees Due
Verify Sprinkler Sign Off 3/14/2020 Off-Hour Fees Due
Wood Frame 3/14/2020 Off-Hour Fees Due
Drywall Nailing 3/16/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/16/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/17/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/17/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/18/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/18/2020 Not Ready for Inspection ROBERT COLE
Insulation 3/23/2020 Partial Approval ROBERT COLE
T-Bar Ceiling 3/23/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/24/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/24/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/25/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/25/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 3/26/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/26/2020 Partial Inspection ROBERT COLE
Drywall Nailing 3/31/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 3/31/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/1/2020 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 4/1/2020 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 4/1/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 4/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 4/8/2020 Not Ready for Inspection ROBERT COLE
Final 4/10/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 4/10/2020 Approved ROBERT COLE
Green Building Final 4/10/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 4/10/2020 Partial Approval ROBERT COLE
Reinforced Concrete Frame 4/10/2020 Partial Approval ROBERT COLE
SGSOV-Seismic Gas S/O Valve 4/10/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 4/10/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/10/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 4/10/2020 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 4/15/2020 Partial Inspection ROBERT COLE
Final 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Light Gage Steel Frame 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Concrete Frame 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
SGSOV-Seismic Gas S/O Valve 4/17/2020 SGSOV Not Ready HAMID PISHEHVAR
Smoke Detectors 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Verify Sprinkler Sign Off 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Wood Frame 4/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Drywall Nailing 4/21/2020 Partial Inspection ROBERT COLE
T-Bar Ceiling 4/21/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/21/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 4/21/2020 Not Ready for Inspection ROBERT COLE
Final 4/27/2020 Not Ready for Inspection ROBERT COLE
Green Building Final 4/27/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 4/27/2020 Corrections Issued ROBERT COLE
Reinforced Concrete Frame 4/27/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 4/27/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 4/27/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 4/27/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 4/27/2020 Not Ready for Inspection ROBERT COLE
Final 5/4/2020 Partial Inspection ROBERT COLE
Green Building Final 5/4/2020 Not Ready for Inspection ROBERT COLE
Insulation 5/4/2020 Off-Hour Fees Due
Insulation 5/4/2020 Partial Approval ROBERT COLE
Light Gage Steel Frame 5/4/2020 Corrections Issued ROBERT COLE
Reinforced Concrete Frame 5/4/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 5/4/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 5/4/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 5/4/2020 Off-Hour Fees Due
Verify Sprinkler Sign Off 5/4/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 5/4/2020 Not Ready for Inspection ROBERT COLE
Insulation 5/5/2020 Partial Inspection ROBERT COLE
Light Gage Steel Frame 5/5/2020 Partial Inspection ROBERT COLE
Drywall Nailing 5/12/2020 Partial Approval ROBERT COLE
Final 5/12/2020 Corrections Issued ROBERT COLE
Green Building Final 5/12/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 5/12/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/12/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 5/12/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 5/12/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/12/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 5/12/2020 Not Ready for Inspection ROBERT COLE
Final 5/22/2020 Not Ready for Inspection ROBERT COLE
Green Building Final 5/22/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 5/22/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 5/22/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 5/22/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 5/22/2020 Corrections Issued ROBERT COLE
T-Bar Ceiling 5/22/2020 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/22/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 5/22/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 6/2/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/2/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/4/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 6/12/2020 Partial Inspection ROBERT COLE
Final 6/15/2020 Partial Inspection ROBERT COLE
Green Building Final 6/15/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/15/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 6/15/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 6/15/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/15/2020 Corrections Issued ROBERT COLE
Verify Sprinkler Sign Off 6/15/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 6/15/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 6/16/2020 Partial Inspection ROBERT COLE
Final 6/19/2020 Partial Inspection ROBERT COLE
Green Building Final 6/19/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/19/2020 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Not Ready ROBERT COLE
Smoke Detectors 6/19/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 6/19/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 6/19/2020 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 6/22/2020 Corrections Issued ROBERT COLE
Drywall Nailing 6/23/2020 Approved ROBERT COLE
Special/Order Compliance 6/23/2020 Corrections Issued ROBERT COLE
Special/Order Compliance 6/24/2020 Corrections Issued ROBERT COLE
Verify Sprinkler Sign Off 6/24/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 6/24/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/25/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/26/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/30/2020 Partial Inspection ROBERT COLE
Drywall Nailing 7/16/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 7/16/2020 Partial Approval ROBERT COLE
Insulation 7/20/2020 Approved HAMID PISHEHVAR
Drywall Nailing 7/22/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/22/2020 Not Ready for Inspection JEFFREY FULTON
Final 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/10/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 8/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 8/11/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 8/12/2020 Partial Approval HAMID PISHEHVAR
Special/Order Compliance 8/13/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 8/17/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 8/18/2020 Not Ready for Inspection HAMID PISHEHVAR
Final 8/19/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 8/19/2020 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 8/19/2020 Approved HAMID PISHEHVAR
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved HAMID PISHEHVAR
Smoke Detectors 8/19/2020 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 8/19/2020 Approved HAMID PISHEHVAR
Wood Frame 8/19/2020 Approved HAMID PISHEHVAR
Special/Order Compliance 8/20/2020 Not Ready for Inspection DANIEL VARNUM
Final 8/21/2020 Partial Inspection JONATHAN QUACH
Special/Order Compliance 8/25/2020 Partial Inspection DANNY RODRIGUEZ
Final 9/11/2020 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 9/15/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 9/18/2020 Corrections Issued DANNY RODRIGUEZ
Pre-Inspection 11/25/2020 Not Ready for Inspection DANNY RODRIGUEZ
Final 1/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 2/16/2021 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/16/2021 No Access for Inspection DANNY RODRIGUEZ
Final 2/18/2021 Partial Inspection DANNY RODRIGUEZ
Final 3/24/2021 OK to Issue CofO RICKEY JACKSON