559 N OXFORD AVE Lot 3-Unit typ B 90004

Certificate Information: 559 N OXFORD AVE Lot 3-Unit typ B 90004

Application / Permit
16010-10000-02067
Plan Check / Job No.
B16LA04872
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3-story SFD with attached 2-car garage Small lot subdivision pursuant to Tentative Tract Map No. 72899. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded.
Permit Issued
Issued on 8/31/2017
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2016 APPLICANT
Assigned to Plan Check Engineer 4/28/2016 CHIU TAM
Corrections Issued 5/27/2016 CHIU TAM
Quality Review Completed 6/3/2016 JOHN VASQUEZ
Building Plans Picked Up 6/6/2016 APPLICANT
Green Plans Picked Up 6/6/2016 APPLICANT
Applicant returned to address corrections 7/1/2016 CHIU TAM
Applicant returned to address corrections 7/19/2016 CHIU TAM
Applicant returned to address corrections 7/26/2016 CHIU TAM
Applicant returned to address corrections 8/18/2016 CHIU TAM
Applicant returned to address corrections 8/19/2016 CHIU TAM
Applicant returned to address corrections 8/31/2016 CHIU TAM
Applicant returned to address corrections 9/14/2016 CHIU TAM
Applicant returned to address corrections 9/16/2016 CHIU TAM
Applicant returned to address corrections 11/15/2016 EUGENE BARBEAU
Applicant returned to address corrections 7/19/2017 EUGENE BARBEAU
Plan Check Approved 7/27/2017 EUGENE BARBEAU
Issued 8/31/2017 LADBS
CofO in Progress 1/7/2022 ALEJANDRO DE ARTOLA
Permit Finaled 1/8/2022 DEROLD HAUFF
CofO Issued 1/8/2022 DEROLD HAUFF
Permit Finaled 1/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/19/2016 JACOB BIGLER
Low Impact Development Cleared 7/22/2016 RYAN HUDSON
Eng Process Fee Ord 176,300 Cleared 11/22/2016 ALFREDO JARA
Hydrant and Access approval Cleared 11/22/2016 JOHN CONNEALLY
Highway dedication Cleared 4/7/2017 ADRIAN SANCHEZ
Green Code Cleared 4/28/2017 KATHRYN BUTTERWORTH
Project located in CRA area Cleared 5/11/2017 CRAIG BULLOCK
Miscellaneous Cleared 6/29/2017 ARMENIA AGUILAR
Permit Cleared 6/29/2017 ARMENIA AGUILAR
Roof/Waste drainage to street Cleared 6/29/2017 ARMENIA AGUILAR
Building over 3-story or 36-ft Cleared 7/19/2017 CALOSHA APPROVED
Tract Map conditions Cleared 7/25/2017 BRIAN CARR
Sewer availability Cleared 7/26/2017 ADRIAN SANCHEZ
Hold Cleared 11/22/2017 TERESA MUI

Contact Information

Architect Vanos, Vincent Jay; Lic. No.: C22269 2747 MARQUETTE DR      TOPANGA, CA 90290
Contractor Faliv Ezak; Lic. No.: 656355-B 10660 WILSHIRE BLVD 1208      LOS ANGELES, CA 90024
Engineer Mallak, Nabil Michel; Lic. No.: S5351 6385 GREEN VALLEY CIR 218      CULVER CITY, CA 90230
Engineer Samiee, Mohammad Esmail; Lic. No.: C46172 PO BOX 834      SAN DIMAS, CA 91773

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/8/2018 Partial Approval SCOTT FINNILA
Deputy Steel/Welding 3/7/2018 Partial Approval SCOTT FINNILA
Deputy Steel/Welding 3/8/2018 Partial Approval SCOTT FINNILA
Deputy Steel/Welding 3/9/2018 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 3/29/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/29/2018 Corrections Issued SCOTT FINNILA
Underground Mechanical 3/29/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/2/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/11/2018 Approved SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 4/12/2018 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/1/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/2/2018 Conditional Approval DOMINIC DANERI
Drywall Nailing 5/3/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/9/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/9/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/4/2018 Partial Approval SCOTT FINNILA
Wood Frame 6/4/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/5/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 6/7/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/7/2018 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 6/11/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/22/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/3/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/10/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/12/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/13/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/24/2018 No Access for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/1/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/2/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/6/2018 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/8/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/9/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/10/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/14/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/5/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/15/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/22/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/23/2018 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/29/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 10/29/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 10/29/2018 Partial Inspection ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/27/2018 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/4/2018 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/4/2018 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/4/2018 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/5/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 12/5/2018 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/7/2018 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/12/2018 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/12/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/12/2018 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/3/2019 Approved ALEJANDRO DE ARTOLA
Green Building Rough 1/3/2019 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/3/2019 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/8/2019 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/18/2019 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/23/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Drywall Nailing 1/24/2019 Order to Comply Issued ALEJANDRO DE ARTOLA
Shower Pan 3/11/2019 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/12/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/13/2019 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 4/17/2019 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 2/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 3/3/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/11/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/26/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/26/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/14/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/14/2020 Approved ALEJANDRO DE ARTOLA
Final 7/15/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/5/2020 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/15/2021 Approved ALEJANDRO DE ARTOLA
Final 7/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/15/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/15/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Smoke Detectors 7/15/2021 Approved ALEJANDRO DE ARTOLA
Structural Steel Frame 7/15/2021 Approved ALEJANDRO DE ARTOLA
Final 12/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/28/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/30/2021 Approved ALEJANDRO DE ARTOLA
Final 1/6/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 1/6/2022 Approved ALEJANDRO DE ARTOLA