6181 W TEMPLE HILL DR 90068

Certificate Information: 6181 W TEMPLE HILL DR 90068

Application / Permit
16010-10000-02010
Plan Check / Job No.
B16LA07160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND RECREATION ROOM.
Permit Issued
Issued on 11/16/2017
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2016 APPLICANT
Assigned to Plan Check Engineer 6/30/2016 BIDYUT RATH
Green Plans Picked Up 6/30/2016 APPLICANT
Corrections Issued 7/8/2016 BIDYUT RATH
Quality Review Completed 7/18/2016 KESETE HAREGOT
Building Plans Picked Up 7/21/2016 APPLICANT
Applicant returned to address corrections 8/5/2016 BIDYUT RATH
Applicant returned to address corrections 5/8/2017 BIDYUT RATH
Applicant returned to address corrections 5/22/2017 BIDYUT RATH
Applicant returned to address corrections 6/15/2017 BIDYUT RATH
Applicant returned to address corrections 7/20/2017 BIDYUT RATH
Applicant returned to address corrections 7/20/2017 MINYE PAK
Applicant returned to address corrections 9/5/2017 BIDYUT RATH
Applicant returned to address corrections 9/6/2017 BIDYUT RATH
Applicant returned to address corrections 9/11/2017 BIDYUT RATH
Applicant returned to address corrections 9/22/2017 ARMEN JIVALAGIAN
Plan Check Approved 11/15/2017 ARMEN JIVALAGIAN
Issued 11/16/2017 LADBS
CofO in Progress 3/29/2024 ROY SPAULDING
CofO in Progress 4/1/2024 ROY SPAULDING
CofO in Progress 4/1/2024 ROY SPAULDING
CofO Issued 4/1/2024 RONALD MYRICK
Permit Finaled 4/1/2024 RONALD MYRICK

Permit Application Clearance Information

Low Impact Development Cleared 3/8/2017 MARTIN FRAGOSO
Address approval Cleared 3/14/2017 JAMES MORALEZ
BHO/Hillside ordinance Cleared 3/14/2017 JAMES MORALEZ
BHO/Hillside ordinance Cleared 3/14/2017 JAMES MORALEZ
BHO/Hillside ordinance Cleared 3/14/2017 JAMES MORALEZ
BHO/Hillside ordinance Cleared 3/14/2017 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 3/14/2017 JAMES MORALEZ
Permit Cleared 3/14/2017 JAMES MORALEZ
Roof/Waste drainage to street Cleared 3/14/2017 JAMES MORALEZ
Sewer availability Cleared 3/14/2017 JAMES MORALEZ
Grading Pre-Inspection Cleared 9/5/2017 BIDYUT RATH
Green Code Cleared 9/5/2017 JIVAR AFSHAR
Hydrant and Access approval Cleared 9/7/2017 ROBERT DUFF
Excavation more than 5-ft deep Cleared 11/13/2017 CALOSHA APPROVED

Contact Information

Contractor Pierre Builders Inc; Lic. No.: 616112-B 15330 ARCHWOOD STREET      VAN NUYS, CA 91406
Engineer Nohroodi, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042
Engineer Salehipour, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/14/2018 Approved LUIS BARRALES
Excavation/Setback/Form/Re-Bar 3/16/2018 Partial Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 4/12/2018 Partial Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 6/6/2018 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 6/6/2018 Partial Approval LUIS BARRALES
Deputy Reinf. Concrete 6/14/2018 Approved LUIS BARRALES
Excavation/Setback/Form/Re-Bar 7/19/2018 Partial Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 10/18/2018 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 10/26/2018 Partial Approval ELMER BLAND
PLUMBING-Rough 11/1/2018 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 11/2/2018 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 11/30/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 12/4/2018 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/4/2018 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/6/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/13/2018 Conditional Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 3/4/2019 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/6/2019 Partial Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/17/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/21/2019 Partial Approval LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 7/25/2019 Not Ready for Inspection ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Corrections Issued ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 8/8/2019 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Approved ROBERT CORNELL
ELECTRICAL-Rough 8/21/2019 Corrections Issued ROBERT CORNELL
PLUMBING-Rough 8/22/2019 Approved ROBERT CORNELL
HVAC-Rough 8/26/2019 Corrections Issued ROBERT CORNELL
HVAC-Rough 8/29/2019 Approved ROBERT CORNELL
Drywall Nailing 9/23/2019 Not Ready for Inspection ROBERT CORNELL
Green Building Rough 9/23/2019 Approved ROBERT CORNELL
Drywall Nailing 10/7/2019 Corrections Issued ROBERT CORNELL
Special/Order Compliance 10/9/2019 Partial Inspection ROBERT CORNELL
Insulation 10/15/2019 Conditional Approval ROBERT CORNELL
Interior/Exterior Lathing 1/27/2020 Approved ROBERT CORNELL
BUILDING-Rough-Frame 3/16/2021 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 3/16/2021 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Final 3/16/2021 Corrections Issued JOSEPH MCGARRY
Green Building Final 3/16/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 3/16/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 3/16/2021 Corrections Issued JOSEPH MCGARRY
Reinforced Concrete Frame 3/16/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/16/2021 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 3/16/2021 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 3/16/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 3/16/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 3/31/2021 Conditional Approval BRIAN SULLIVAN
Drywall Nailing 3/31/2021 Conditional Approval BRIAN SULLIVAN
Final 3/31/2021 Not Ready for Inspection BRIAN SULLIVAN
Gas Test 3/31/2021 Approved BRIAN SULLIVAN
Green Building Final 3/31/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Not Ready BRIAN SULLIVAN
Pre-Inspection 4/7/2021 Not Ready for Inspection BRAD BESCOS
Special/Order Compliance 4/7/2021 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 4/9/2021 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 6/11/2021 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 6/11/2021 Partial Inspection BRAD BESCOS
ELECTRICAL-Final 6/30/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 7/15/2021 Partial Inspection RAUL BARAJAS
PLUMBING-Final 7/15/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 7/28/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Final 7/28/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Not Ready COREY HUPP
Special/Order Compliance 9/29/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 11/15/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/15/2021 Partial Approval CHRIS CHRISTENSEN
Final 11/15/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/15/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 11/15/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 11/30/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Final 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 11/30/2021 Partial Inspection RUBEN SALAS
ELECTRICAL-Final 6/13/2022 Approved BRIAN SULLIVAN
Final 6/13/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 6/13/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/13/2022 Approved BRIAN SULLIVAN
Service/Power Release 6/13/2022 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 6/13/2022 Partial Inspection RUBEN SALAS
Special/Order Compliance 9/10/2022 Order to Comply Issued BRIAN SULLIVAN
Pre-Inspection 9/16/2022 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 9/16/2022 Not Ready for Inspection RUBEN SALAS
Service/Power Release 1/16/2024 Not Ready for Inspection ROY SPAULDING
Service/Power Release 1/19/2024 Approved RAUL BARAJAS
Final 2/26/2024 Partial Approval ROY SPAULDING
Final 3/29/2024 OK to Issue CofO ROY SPAULDING